Map
Sign in
← Explore registry

Australia / Site

AirTrunk SYD1

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

SYD1 Sydney West

Operational

Operational hyperscale campus in Huntingwood, Western Sydney, comprising multiple buildings. Operator sources report differing campus capacities of 121 MW+ and 130 MW+; these are not established live IT loads. The fifth and final building was reported completed in July 2022. SYD3 is a separately named nearby connected campus.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
AirTrunk
Ownership
Unknown / not established
Business model / scale
Colocation / Hyperscale
Region / metro
New South Wales / Sydney
City / locality
Huntingwood
Address
35 Huntingwood Drive, Huntingwood NSW 2148, Australia
Location
Published PeeringDB facility geocode associated with 35 Huntingwood Drive; street address corroborated by industry reporting, but marker and property boundaries were not independently verified.
Precision: approximate · -33.799523, 150.881568
View location on map →
Parent
Not assigned

Location detail

Published PeeringDB facility geocode associated with 35 Huntingwood Drive; street address corroborated by industry reporting, but marker and property boundaries were not independently verified.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.

35 Huntingwood Drive, Huntingwood NSW 2148, Australia

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
>130 MW
Unspecified power
SYD1 total multi-building campus capacity
Operational · cumulative
2026-10-09Conflicting claim ↗

Excluded from capacity totals. Undated operator page retrieved on this date; 130+MW is advertised campus capacity, not measured live load. Conflicts with 121 MW+ in the dated announcement.

>121 MW
Unspecified power
SYD1 campus capacity in Australian platform announcement
Operational · cumulative
2025-12-24Conflicting claim ↗

Excluded from capacity totals. As-of date is announcement publication date. Basis and reason for difference from 130+MW are unexplained.

>40 MW
Unspecified power
SYD1 fifth and final building/phase
Operational · incremental
2022-07-07Reported claim ↗

Excluded from capacity totals. As-of date is industry report publication date; report quotes operator completion announcement. Phase capacity overlaps campus totals and must not be added to them; completion does not establish live load.

Development timeline

  1. 2017-09 · actual_opening

    SYD1 opening

    Opening month reported in the FY24 operator sustainability report; grouped corporate history gives a differing April 2017 placement.

    Supporting source ↗
  2. 2021-01-14 · planning_submission

    Phase 5 fire engineering support

    Dated council-hosted letter supports a modification submission for the Huntingwood Phase 5 development.

    Supporting source ↗
  3. 2022-07 · actual_completion_reported

    Final building completion

    July 7 reporting confirms completion of the fifth building; exact completion day is not established.

    Supporting source ↗
  4. 2024-12-23 · announcement_completed_acquisition

    AirTrunk corporate acquisition completed

    Operator announces completed acquisition by a Blackstone-led consortium alongside CPP Investments.

    Supporting source ↗
  5. 2026-05-01 · announcement_actual_energization

    SYD1 rooftop solar energized

    Industry report confirms rooftop solar energization; exact energization day and capacity are undisclosed.

    Supporting source ↗

Disclosed specifications

Land area

7.4 hectares

Operator campus disclosure.

Source ↗

Technical data hall area

35,000 m²

Campus disclosure, not total gross floor area.

Source ↗

Office and storage area

7,600 m²

Operator campus disclosure.

Source ↗

Data halls

42

Campus total.

Source ↗

Power supply

132 kV diverse high-voltage feed

Voltage does not establish grid connection capacity in MW.

Source ↗

Design PUE

1.15

Design target, not current measured operational PUE.

Source ↗

Connectivity

Carrier neutral; multiple entry paths

Operator disclosure.

Source ↗

Security and hosting

Australian Government Certified Strategic hosting provider; designed for SCEC Zone 3 or higher

Operator wording; certification scope available upon request and not independently checked.

Source ↗

Public hosting partner

Datacom

Operator confirms dedicated onsite halls used for hosting and colocation; no hyperscale customer identities established.

Source ↗

Renewable energy

Energized rooftop solar array

Reported May 2026; capacity undisclosed.

Source ↗

General business contact

info@airtrunk.com; +61 2 9953 4780

Public general enquiries email and Sydney office telephone, not a dedicated facility contact.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

SYD1 Sydney West | AirTrunk ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies a multi-building Sydney West hyperscale campus with 130+MW total capacity and publishes area, connectivity, power-feed and efficiency specifications.

AirTrunk SYD1 - PeeringDB ↗

Published Date unavailable · Retrieved 2026-10-09

Facility entry names AirTrunk Operating Pty Ltd, 35 Huntingwood Drive, Huntingwood NSW 2148, country AU, and geocode -33.799523, 150.881568. Displayed last update is 2025-09-26.

Australia | Locations | AirTrunk ↗

Published Date unavailable · Retrieved 2026-10-09

Lists SYD1 separately from SYD2 and SYD3 and confirms Datacom provides hosting and colocation from dedicated SYD1 data halls.

AirTrunk SYD1 completion announcement on LinkedIn ↗

Published Date unavailable · Retrieved 2026-10-09

Accessible operator post confirms fifth-building completion and a 40+MW phase delivered two months ahead of schedule; describes nearby SYD3 as a connected campus. Exact publication date was not displayed.

AirTrunk Sustainability Report FY24 ↗

Published Date unavailable · Retrieved 2026-10-09

Opening table on page 5 lists SYD1 opening in September 2017 and includes it in operational reporting scope.

SafeAssure project profile — AirTrunk Operating ↗

Published Date unavailable · Retrieved 2026-10-09

Contractor profile identifies the SYD1 Phase 5 project at 24 Healy Circuit, Huntingwood, and AW Edwards as principal contractor. Its older campus figures differ from current disclosures.

Connect with AirTrunk ↗

Published Date unavailable · Retrieved 2026-10-09

Publishes general enquiries email and Sydney office telephone; office address is distinct from the facility.

The AirTrunk Story ↗

Published Date unavailable · Retrieved 2026-10-09

Grouped history places SYD1 opening under April 2017, differing from the September 2017 opening in the FY24 report; grouped milestones should not be interpreted as precise event dates.

Profile field evidence

Name: SYD1 Sydney West | AirTrunk; AirTrunk SYD1 - PeeringDB

Aliases: SYD1 Sydney West | AirTrunk

Kind: SYD1 Sydney West | AirTrunk; AirTrunk SYD1 completion announcement on LinkedIn

Country: AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne; AirTrunk SYD1 - PeeringDB; Australia | Locations | AirTrunk

Region: AirTrunk SYD1 - PeeringDB

City: AirTrunk SYD1 - PeeringDB; AirTrunk Huntingwood SYD1 Phase 5 — Fire Engineering Letter of Support

Metro: SYD1 Sydney West | AirTrunk; AirTrunk completes fifth building at 130MW Sydney campus

Address: AirTrunk SYD1 - PeeringDB; AirTrunk Announces SYD1 Campus Final Phase Completion

Operator: SYD1 Sydney West | AirTrunk; AirTrunk SYD1 - PeeringDB; Australia | Locations | AirTrunk

Business Model: Australia | Locations | AirTrunk

Scale: SYD1 Sydney West | AirTrunk

Statuses: Australia | Locations | AirTrunk; AirTrunk Sustainability Report FY24; AirTrunk completes installation of rooftop solar array at SYD1 data center in Sydney, Australia

Summary: SYD1 Sydney West | AirTrunk; AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne; AirTrunk completes fifth building at 130MW Sydney campus; AirTrunk SYD1 completion announcement on LinkedIn

Location: AirTrunk SYD1 - PeeringDB; AirTrunk Announces SYD1 Campus Final Phase Completion

Stable identifier: 1640e0ff-75e2-4810-84c3-cbd89758abdd