Iron Mountain Amsterdam campus (AMS-1) · Netherlands · Iron Mountain Data Centers

Haarlem colocation campus with operational AMS-1 and expansion projects. Operator reports 13.1 MW current power, exceeding 5 MW without establishing an IT-load basis. Expansion naming and ultimate capacity require reconciliation.

Capacity statements: 12 · Sources: 16

13.1 MW (exact) · unspecified · Current AMS-1 power capacity · 2026-10-09

13.1 MW (exact) · unspecified · AMS-1 total leaseable capacity · 2026-03-31

10 MW (exact) · unspecified · AMS-1 Phase 4 expansion · 2026-03-31

20 MW (exact) · unspecified · AMS-2 held for development · 2026-03-31

10 MW (exact) · it · Marketing-named AMS-2 expansion building · 2026-06-12

43.1 MW (exact) · unspecified · Amsterdam campus at full build-out · 2026-06-12

30 MW (exact) · it · AMS-1 campus at full build-out · 2026-04-12

14.1 MW (exact) · unspecified · AMS-1 total potential capacity in location overview · 2026-04-01

22.7 MW (exact) · facility · AMS-1 facility on operator campaign page · 2026-10-09

60 MW (exact) · unspecified · 23-acre campus capacity on operator campaign page · 2026-10-09

11 MW (approx) · unspecified · First location in historical EvoSwitch acquisition · 2018-05-30

27 MW (exact) · unspecified · First location's historical total potential capacity · 2018-05-30