Switch Datacenters — Sustainable datacenter developer ↗
Published Date unavailable · Retrieved 2026-10-09
Operator identifies Amsterdam 4 as AMS4 in the Municipality of Diemen and advertises wholesale colocation.
Netherlands / Facility
AMS4 · Switch Datacenters Amsterdam 4
Operational wholesale colocation facility in Diemen in the Amsterdam market, created by redeveloping a logistics building. Municipal evidence places initial customer operation in January 2024. Reported design capacities exceed 5 MW, but conflicting 14 MW and 15–18 MW IT figures have not been reconciled and actual energized load is undisclosed. Heat reuse is a development objective rather than confirmed district heat delivery.
Statements retain their dates, definitions and development scope. Do not add these rows together.
| Claim / measurement | Scope and status | As of | Evidence and accounting |
|---|---|---|---|
| ≥15 MW IT load | AMS4 reported IT capacity range lower endpoint Operational · unclear | 2024-06-01 | Conflicting claim ↗ Excluded from capacity totals. Publication date; article reports 15–18 MW IT for opened facility. Paired range with c2, not additive and not proof of energized load. |
| 18 MW IT load | AMS4 reported IT capacity range upper endpoint Operational · unclear | 2024-06-01 | Conflicting claim ↗ Excluded from capacity totals. Publication date; upper endpoint of 15–18 MW range paired with c1. Design/nameplate scope and installed amount not independently established. |
| 14 MW IT load | AMS4 design ceiling reported by directory Operational · unclear | 2026-10-09 | Conflicting claim ↗ Excluded from capacity totals. Retrieval date of undated page, not commissioning or measurement date. Source says design allows up to 14 MW IT; conflicts with 15–18 MW report. |
Earlier brochure advertised service readiness in Q1 2023; actual municipal evidence places first customer in January 2024.
Supporting source ↗Another undated operator brochure advertised Q3 2023 readiness; not treated as actual opening.
Supporting source ↗Municipality reports first customer began in one of four halls in January 2024.
Supporting source ↗Company-submitted announcement describes AMS4 as fully operational.
Supporting source ↗Municipal executive approved an intention agreement with Switch to investigate a heat network.
Supporting source ↗Undated brochure design specification; earlier brochure reports 7,500 m². Land area and gross building area not independently established.
Source ↗Brochure design specification; four halls corroborated by municipality.
Source ↗Brochure specification, not verified energized MW. Earlier version mentions upgrade to 2 × 20 MVA without confirmed completion.
Source ↗Undated brochure design; current installed configuration not audited.
Source ↗Brochure availability claim; individual carrier installations not independently checked.
Source ↗Brochure claims; certificates, scope and validity not checked. PCI DSS readiness is not certification.
Source ↗Company announcement claim; procurement contracts and metered renewable matching not inspected.
Source ↗Municipality reported heat discharged to air in 2024; actual district heating delivery remains unconfirmed.
Source ↗Published operator sales contact; no contact attempted.
Source ↗Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-09
Operator identifies Amsterdam 4 as AMS4 in the Municipality of Diemen and advertises wholesale colocation.
Published Date unavailable · Retrieved 2026-10-09
Association lists AMS4 at Treubweg 9–11, Diemen, 1112BA; describes Switch as wholesale operator and developer.
Published Date unavailable · Retrieved 2026-10-09
Municipality reports a visit on 16 February 2024, first customer operation in January, four halls, reused distribution-building fabric and roof cooling; heat was then discharged to air.
Published 2024-09-03 · Retrieved 2026-10-09
Datacenter at Treubweg 11 on Verrijn Stuart industrial estate entered service early in 2024; calls Switch the owner and approves cooperation to investigate heat reuse.
Published Date unavailable · Retrieved 2026-10-09
Search-indexed official page identifies AMS4 as operational in Amsterdam (Diemen), Netherlands, developed and co-owned by DGFO with Switch. Opening redirects to ai-factories, which returned no readable body.
Published 2024-06-01 · Retrieved 2026-10-09
Reports opening, 15–18 MW IT capacity and 4,400 square metres of whitespace. Science Park/Oost wording is less precise than municipality-confirmed Diemen address.
Published Date unavailable · Retrieved 2026-10-09
Lists Treubweg 11, Netherlands, operation in 2024 and design up to 14 MW IT; provides operator brochure and property image attributed to Switch.
Published Date unavailable · Retrieved 2026-10-09
Undated operator brochure describes wholesale colocation, Treubweg 9–11, 7,400 square metres colocation space, 4,400 square metres whitespace, 2,300 racks, two 10 MVA feeders and cooling design; advertised readiness Q3 2023.
Published 2024-06-04 · Retrieved 2026-10-09
Submitted company announcement reports fully operational facility, closed cooling loop, offshore-wind green electricity and prospective heat network; customer names are undisclosed.
Published Date unavailable · Retrieved 2026-10-09
Project designer identifies Treubweg AMS4, reports 7–18 MW IT and describes responsibility for design and permitting.
Published 2026-03-17 · Retrieved 2026-10-09
Noord-Holland notice identifies GTDC B.V. as applicant at Treubweg 11 and approval of remediation evaluations; does not establish its ownership relationship to Switch.
Published Date unavailable · Retrieved 2026-10-09
Undated brochure reports 15 MW, readiness Q1 2023, 7,500 square metres colocation space and possible feeder upgrade; filename is not treated as publication date.
Published Date unavailable · Retrieved 2026-10-09
Accessible public post embeds Switch statement of 15–18 MW nearing completion, heat reuse capability and PUE 1.2. Only relative age displayed; calendar publication date unresolved.
Name: Switch Datacenters — Sustainable datacenter developer; Switch Datacenters AMS4 — Data Center Map
Aliases: Switch Datacenters — Sustainable datacenter developer
Kind: Werkbezoek aan datacenter — Diemen Gasvrij; Switch Datacenters AMS4 — operator three-page brochure
Country: Switch Datacenters AMS4 — operator three-page brochure; Switch Datacenters AMS4 — Data Center Map
Region: Beschikking saneringsevaluatie — Treubweg 11, Diemen
City: Switch Datacenters — Dutch Data Center Association; Werkbezoek aan datacenter — Diemen Gasvrij
Metro: Switch Datacenters — Sustainable datacenter developer; Switch Datacenters launches Amsterdam data center — DCD
Address: Switch Datacenters — Dutch Data Center Association; Switch Datacenters AMS4 — operator three-page brochure; B&W besluitenlijst 3 september 2024 — Gemeente Diemen
Operator: Switch Datacenters — Sustainable datacenter developer; Switch Datacenters — Dutch Data Center Association; Switch Datacenters AMS4 — Data Center Map
Owner: B&W besluitenlijst 3 september 2024 — Gemeente Diemen; VOLT AI Factories — infrastructure locations
Business Model: Switch Datacenters AMS4 — operator three-page brochure
Statuses: Werkbezoek aan datacenter — Diemen Gasvrij; B&W besluitenlijst 3 september 2024 — Gemeente Diemen; Switch Datacenters opent AMS4 — Emerce Industry Wire
Summary: Werkbezoek aan datacenter — Diemen Gasvrij; B&W besluitenlijst 3 september 2024 — Gemeente Diemen; Switch Datacenters launches Amsterdam data center — DCD; Switch Datacenters AMS4 — Data Center Map; Switch Datacenters AMS4 — operator three-page brochure; Switch Datacenters opent AMS4 — Emerce Industry Wire
Location: Switch Datacenters — Dutch Data Center Association; B&W besluitenlijst 3 september 2024 — Gemeente Diemen; Switch Datacenters AMS4 — operator three-page brochure
Stable identifier: 29c16abb-b217-431b-ba97-fab4ee9106c8