Vantage's two-building hyperscale campus development in Ibaraki, Osaka Prefecture, has disclosed ultimate capacity of up to 68 MW critical IT load, including a 28 MW first facility named KIX11. Construction and topping out are documented; actual commissioning and current building-by-building status remain unresolved.
Sources and references
Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-09
Operator identifies KIX1 in Ibaraki, Japan; two buildings, up to 68 MW critical IT load and 28 MW first facility targeted for mid-2026. Initial open succeeded; subsequent opens failed.
Published 2024-05-23 · Retrieved 2026-10-09
Vantage-issued announcement identifies Ibaraki, Osaka Prefecture, groundbreaking, two seismic-isolated buildings, 28 MW first-building IT load and early-2026 target; Taisei is construction partner.
Published Date unavailable · Retrieved 2026-10-09
Undated sheet discloses campus area, building space, IT capacity, density, cooling, power infrastructure and connectivity design. URL path is not treated as publication date.
Published Date unavailable · Retrieved 2026-10-09
Public operator post confirms first facility KIX11 topped out, 28 MW IT capacity, early-2026 target and Taisei partnership. Only a relative post age was displayed.
Published Date unavailable · Retrieved 2026-10-09
Page 23 records Vantage's May 2024 construction announcement for Osaka KIX1 in Ibaraki City, Osaka Prefecture, serving hyperscalers and cloud providers.
Published Date unavailable · Retrieved 2026-10-09
Directory labels campus operational with expansion in progress, lists KIX12 under construction and supplies coordinates 34.85262, 135.53298 without property-point methodology.
Published Date unavailable · Retrieved 2026-10-09
Directory identifies KIX11 as operational, built 2026, at 6-chome-16 Saitoasagi, Ibaraki; reports 16-acre lot, conflicting with operator's 12-acre campus.
Published Date unavailable · Retrieved 2026-10-09
Directory marked last checked August 3, 2026 retains under-construction status and limits reliable location disclosure to Ibaraki. Its receiving-power labels differ from operator IT-load terminology.
Published 2026-09-11 · Retrieved 2026-10-09
Employer recruitment page updated September 11 describes startup work at a newly established Ibaraki data center; does not give an explicit commissioning date.
Published Date unavailable · Retrieved 2026-10-09
Opened industry report documents first-building topping out; image search exposed an aerial construction image. Capture date and reuse license were not established.
Profile field evidence
Name: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage Data Centersが日本第1号のキャンパスを着工
Aliases: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage Data Centersが日本第1号のキャンパスを着工
Kind: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage Data Centersが日本第1号のキャンパスを着工
Country: Osaka, Japan Data Center Campus — Vantage Data Centers; JETRO Invest Japan Report 2025
Region: Vantage Data Centersが日本第1号のキャンパスを着工; JETRO Invest Japan Report 2025
City: Osaka, Japan Data Center Campus — Vantage Data Centers; JETRO Invest Japan Report 2025
Metro: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage: Osaka KIX1 Campus — Baxtel
Operator: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage Data Centersが日本第1号のキャンパスを着工
Business Model: Vantage Data Centersが日本第1号のキャンパスを着工; Vantage Osaka (KIX1) — Baxtel
Scale: Vantage Data Centersが日本第1号のキャンパスを着工; JETRO Invest Japan Report 2025
Location: Osaka, Japan Data Center Campus — Vantage Data Centers; JETRO Invest Japan Report 2025
Summary: Osaka, Japan Data Center Campus — Vantage Data Centers; Vantage Data Centersが日本第1号のキャンパスを着工; Vantage APAC construction update: Osaka topping out; Vantage: Osaka KIX1 Campus — Baxtel; Vantage KIX1 — 日本のデータセンターマップ