Equinix AM6

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

Telecity AMS6

Operational

Operational Equinix colocation facility at Duivendrechtsekade 80A in Amsterdam's Amstel area. Published power ranges require reconciliation; the 2026 energy-generation application does not establish IT load or an approved expansion.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Equinix
Ownership
Unknown / not established
Business model / scale
Colocation / Unknown
Region / metro
North Holland / Amsterdam
City / locality
Amsterdam
Address
Duivendrechtsekade 80A, 1096 AH Amsterdam, Netherlands
Location
PeeringDB facility geocode associated with the operator-confirmed address; property-marker position and building footprint were not independently established.
Precision: approximate · 52.3377, 4.934929
View location on map →
Parent
Not assigned

Location detail

PeeringDB facility geocode associated with the operator-confirmed address; property-marker position and building footprint were not independently established.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.

Duivendrechtsekade 80A, 1096 AH Amsterdam, Netherlands

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
≥5 MW
Unspecified power
AM6 facility; lower endpoint of published 5–10 MW range
Operational · unclear
2020-10-14Reported claim ↗

Excluded from capacity totals. As-of is the document version date. Full reported range is 5–10 MW; no current IT-load measurement is established. Lower bound alone does not prove strictly greater than 5 MW.

≥10 MW
Unspecified power
AM6 directory entry; lower endpoint of published 10–20 MW range
Operational · unclear
2026-10-09Conflicting claim ↗

Excluded from capacity totals. As-of is retrieval of indexed evidence from the 2023 report, not commissioning or measurement date. Full range is 10–20 MW. PDF opening failed and the basis is undefined; do not aggregate with the older municipal range.

10 MW
Unspecified power
AM6 facility power access as described by InterEdge
Operational · unclear
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated webpage. Source says access to 10 MW but does not define IT, facility or grid basis. Compilation contains unit and numerical inconsistencies; retain only for reviewer comparison.

Development timeline

  1. 2017-Q3 · planned

    AM6 phase II target opening

    Equinix's Q1 2017 presentation targeted phase II for Q3 2017. Actual opening was not established.

    Supporting source ↗
  2. 2025-12-12 · actual_application_received

    Energy-generation permit application received

    Application OD2025-0041448 / DSO 2025121201355 received for energy generation supporting AM6; approval and implementation were not established.

    Supporting source ↗
  3. 2026-04-20 · announcement

    Provincial application notice published

    Notice describes a 50 MW-or-more energy-generation category. This is not an IT-load or grid-connection claim.

    Supporting source ↗

Disclosed specifications

Colocation area

6,000 m² (64,583 ft²)

Current operator technical table; not land area.

Source ↗

Building

Four-storey reinforced-concrete purpose-built data center

Operator description.

Source ↗

Minimum cabinet density

6 kVA

Electrical rating; not converted to kW.

Source ↗

UPS redundancy

N+1

Current operator table.

Source ↗

Cooling redundancy

N+2

Cooling technology and water usage not specified by this claim.

Source ↗

Power distribution

230 V / 400 V

Operator technical table.

Source ↗

Fire suppression

Mist/fogging

Operator technical table.

Source ↗

Operational coverage

24/7 on site

Equinix product documentation.

Source ↗

Metropolitan connectivity

Fibre Connect links to other Amsterdam Equinix IBXs

PeeringDB lists AM1/AM2, AM3, AM4, AM5, AM7 and AM11; availability requires current operator confirmation.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Equinix AM6 — Amsterdam data center ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies AM6 at Duivendrechtsekade 80A, Amsterdam, Netherlands; technical table gives colocation area, building description, density and redundancy.

State of the Dutch Data Centers 2023 — directory ↗

Published Date unavailable · Retrieved 2026-10-09

Search-indexed directory row identifies AM6 at the same address with 2,500–10,000 m², 1,000+ racks and 10–20 MW. Direct PDF opening failed; indexing was accessible. Exact publication date and power definition were not established.

Where to connect — AMS-IX Amsterdam ↗

Published Date unavailable · Retrieved 2026-10-09

Search indexing identifies Equinix Amsterdam Duivendrechtsekade (AM6), formerly Telecity AMS6. Opened page did not expose the dynamically populated facility list.

Equinix Q1 2017 Earnings Presentation ↗

Published Date unavailable · Retrieved 2026-10-09

Expansion table on slide 22 targets AM6 phase II for Q3 2017, approximately 1,950 sellable cabinet equivalents and $37 million capex; these are forecasts.

Equinix Amsterdam AM6 Data Center — Baxtel ↗

Published Date unavailable · Retrieved 2026-10-09

Lists an operational Amsterdam facility and an exterior photo captioned Equinix AM6 at Dusk, attributed to Baxtel. Uses address number 80 rather than operator's 80A; photo could not be fetched.

Netwerk — InterEdge B.V. ↗

Published Date unavailable · Retrieved 2026-10-09

AM6 entry reports access to 10 MW. Other entries and area units contain conspicuous inconsistencies, reducing confidence in this secondary compilation.

Profile field evidence

Name: Equinix AM6 — Amsterdam data center; Permit application received — Duivendrechtsekade 80A — energy generation for Equinix AM6

Aliases: Where to connect — AMS-IX Amsterdam

Kind: Equinix AM6 — Amsterdam data center; Equinix Colocation Availability

Country: Equinix AM6 — Amsterdam data center

Region: Equinix Colocation Availability

City: Equinix AM6 — Amsterdam data center; Permit application received — Duivendrechtsekade 80A — energy generation for Equinix AM6

Metro: Equinix Colocation Availability

Address: Equinix AM6 — Amsterdam data center; Equinix AM6 — Amsterdam, Duivendrechtsekade — PeeringDB; Permit application received — Duivendrechtsekade 80A — energy generation for Equinix AM6

Operator: Equinix AM6 — Amsterdam data center; Equinix Colocation Availability

Business Model: Equinix AM6 — Amsterdam data center; Equinix Colocation Availability

Statuses: Equinix Colocation Availability; Equinix Amsterdam AM6 Data Center — Baxtel

Summary: Equinix AM6 — Amsterdam data center; Equinix Colocation Availability; Amsterdam Duurzaam Digitaal — Vestigingsbeleid datacenters gemeente Amsterdam 2020–2030; State of the Dutch Data Centers 2023 — directory; Permit application received — Duivendrechtsekade 80A — energy generation for Equinix AM6

Location: Equinix AM6 — Amsterdam, Duivendrechtsekade — PeeringDB; Equinix AM6 — Amsterdam data center

Stable identifier: 3d3d8ce1-5df3-4bfd-ac30-ed2c8ee09c49