Nebius to construct 310 MW AI factory in Finland ↗
Published 2026-03-31 · Retrieved 2026-10-07
Operator announces Lappeenranta campus, up to 310 MW, first customer capacity expected in 2027, South Karelia location and proposed cooling/heat recovery.
Finland / Site
Pajarila data center · Pajarilan datakeskus
Nebius is developing and operating a multi-building AI cloud campus in Pajarila, with Polarnode supporting development and delivery and Fira constructing the first phase. Main construction began in July 2026; the first building is expected in the first half of 2027. Ultimate reported capacity is up to 310 MW; later phases remain planned and no operational capacity was established.
Statements retain their dates, definitions and development scope. Do not add these rows together.
| Claim / measurement | Scope and status | As of | Evidence and accounting |
|---|---|---|---|
| ≈310 MW Unspecified power | Ultimate multi-building campus; operator wording is up to 310 MW Planned · cumulative | 2026-03-31 | Reported claim ↗ Excluded from capacity totals. Announcement date. Upper-bound wording is preserved here because the qualifier vocabulary has no less-than-or-equal option. Not established as IT load or operational power. |
| ≈310 MW Unspecified power | Entire campus once completed Planned · cumulative | 2026-08-11 | Reported claim ↗ Excluded from capacity totals. Contractor publication date; approximately 310 MW total power capacity at completion, overlapping c1. |
| 60 MW Unspecified power | Development covered by January 2026 building permission Planned · unclear | 2026-01-27 | Reported claim ↗ Excluded from capacity totals. News publication and reported permit-decision date; historical permitted scope, not confirmed current first-phase IT capacity. |
| >300 MW Unspecified power | Total development after intended additional permit Planned · cumulative | 2026-01-27 | Reported claim ↗ Excluded from capacity totals. Historical news publication date; proposed expansion total overlaps subsequent 310 MW campus claims and must not be added to 60 MW. |
Yle reports city permission for Polarnode’s development; original permit decision was not inspected.
Supporting source ↗Operator announces Lappeenranta AI factory with first customer capacity expected in 2027.
Supporting source ↗City notice published May 12 schedules earthworks for May 13; later contractor confirms spring site preparation.
Supporting source ↗Fira confirms main construction activities commenced in July 2026.
Supporting source ↗Fira expects first data-center building completion during the first half of 2027; this is not evidence of commissioned capacity.
Supporting source ↗Nebius expects first capacity available to customers in 2027.
Supporting source ↗Campus land, not building floor area; operator separately rounds to approximately 100 acres.
Source ↗Separate from Nebius project ownership; subsequent lease arrangements not established.
Source ↗Supports preparation, permitting and construction services for this same campus.
Source ↗Operator says local water intake for server cooling is avoided; operating performance unverified.
Source ↗Opportunity described by operator; city FAQ says solutions remain under discussion, so no completed connection established.
Source ↗Forward-looking operator design statement; no site-specific procurement contract or achieved carbon intensity established.
Source ↗City FAQ design disclosure; despite closed-loop cooling, total project water use is not zero.
Source ↗Undated city FAQ attributes discussion to LUT professor emeritus; not a confirmed connection agreement or IT load. No dated capacity claim created.
Source ↗Source attribution does not imply independent verification or permission to reuse images.
Published 2026-03-31 · Retrieved 2026-10-07
Operator announces Lappeenranta campus, up to 310 MW, first customer capacity expected in 2027, South Karelia location and proposed cooling/heat recovery.
Published Date unavailable · Retrieved 2026-10-07
City identifies Nebius, Kettukuja south of Highway 6, two plots totaling 41 hectares and phased development with Polarnode.
Published Date unavailable · Retrieved 2026-10-07
City states land belongs to the city and is leased to Polarnode for 60 years; discusses approximately 300 MW electrical demand, heat-recovery negotiations and water-use design.
Published 2026-05-12 · Retrieved 2026-10-07
City announces earthworks scheduled for May 13; explicitly identifies Nebius as project owner/client and Polarnode as development, permitting and construction-services partner.
Published 2026-08-11 · Retrieved 2026-10-07
First-phase contractor confirms main construction commenced July 2026, first building expected in first half of 2027 and approximately 310 MW ultimate campus capacity.
Published Date unavailable · Retrieved 2026-10-07
City planning page describes industrial zoning south of Highway 6, about five kilometres east of central Lappeenranta; plan became legally effective June 14, 2022.
Published Date unavailable · Retrieved 2026-10-07
City PDF identifies the data-center area and Polarnode/Nebius plots; distinguishes the project from the broader planning area.
Published 2026-01-27 · Retrieved 2026-10-07
Yle reports building permission for a 60 MW development and intended later permit raising total power above 300 MW; operator was then unresolved.
Published 2026-08-11 · Retrieved 2026-10-07
Yle reports July 2026 building construction, Fira first-phase responsibility and publishes wide construction-site photographs attributed to Mikko Savolainen/Yle.
Published 2026-03-31 · Retrieved 2026-10-07
Industry report updated to identify Polarnode as developer of the Nebius campus; earlier 100/350 MW language is not reconciled with the current 310 MW announcement.
Name: Nebius to construct 310 MW AI factory in Finland; Pajarila data center
Aliases: Pajarila data center; Lappeenrannan Pajarilan datakeskuksen maanrakennustyöt alkavat 13.5.2026
Kind: Nebius to construct 310 MW AI factory in Finland; Construction and project development company Fira Selected as Main Contractor for One of Europe’s Largest AI Data Center Projects
Country: Nebius to construct 310 MW AI factory in Finland
Region: Nebius to construct 310 MW AI factory in Finland
City: Nebius to construct 310 MW AI factory in Finland; Pajarila data center
Address: Pajarila data center; Frequently Asked Questions — Pajarila data center
Operator: Pajarila data center
Owner: Frequently Asked Questions — Pajarila data center; Lappeenrannan Pajarilan datakeskuksen maanrakennustyöt alkavat 13.5.2026
Business Model: Nebius to construct 310 MW AI factory in Finland; Lappeenrannan Pajarilan datakeskuksen maanrakennustyöt alkavat 13.5.2026
Scale: Nebius to construct 310 MW AI factory in Finland; Construction and project development company Fira Selected as Main Contractor for One of Europe’s Largest AI Data Center Projects
Statuses: Construction and project development company Fira Selected as Main Contractor for One of Europe’s Largest AI Data Center Projects; Nebius to construct 310 MW AI factory in Finland
Location: Pajarila data center; Frequently Asked Questions — Pajarila data center; Pajarila Datakeskus — city location maps
Summary: Nebius to construct 310 MW AI factory in Finland; Lappeenrannan Pajarilan datakeskuksen maanrakennustyöt alkavat 13.5.2026; Construction and project development company Fira Selected as Main Contractor for One of Europe’s Largest AI Data Center Projects
Stable identifier: 467339b7-ccc0-4860-bbd4-0a7b1ec8a9fc