SYD3 Sydney West | AirTrunk ↗
Published Date unavailable · Retrieved 2026-10-09
Operator identifies Western Sydney hyperscale campus, 400+ MW total capacity, technical areas, power feed and design specifications.
Australia / Site
SYD3 Sydney West
AirTrunk hyperscale customer campus in Western Sydney, under construction. Published campus capacity exceeds 5 MW; commissioned IT load is undisclosed. Differently dated power claims and recent design changes require reconciliation.
Converted from coordinates printed on the cover of the September 2022 planning traffic assessment for 51 Huntingwood Drive. Its street description corroborates the property; point placement within the parcel was not visually verified.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.
Loading local map…
Statements retain their dates, definitions and development scope. Do not add these rows together.
| Claim / measurement | Scope and status | As of | Evidence and accounting |
|---|---|---|---|
| >320 MW IT load | Ultimate nine-phase SYD3 campus Planned · cumulative | 2021-11-04 | Reported claim ↗ Excluded from capacity totals. Announcement-date design IT load; not commissioned capacity. |
| >330 MW Unspecified power | SYD3 campus in Australian platform listing Unknown · cumulative | 2025-12-24 | Conflicting claim ↗ Excluded from capacity totals. Publication-date claim; basis and delivery state omitted. Relationship to other campus totals unresolved. |
| >400 MW Unspecified power | SYD3 campus under continued delivery Under Construction · cumulative | 2026-07-30 | Conflicting claim ↗ Excluded from capacity totals. Contract-announcement date; campus scale, not size of incremental contract or operational load. Also advertised by current operator facility page. |
| 400 MW Facility power | Approved development total power consumption Planned · cumulative | 2023-09-15 | Reported claim ↗ Excluded from capacity totals. As-of is original consent determination date shown on portal. Planning consumption differs in basis from IT load and is not evidence of electricity actually consumed. |
Nine-phase Western Sydney campus announced separately from nearby SYD1.
Supporting source ↗SSD-41589232 approved.
Supporting source ↗Bouygues subsidiary A W Edwards awarded €1.2 billion delivery contract.
Supporting source ↗MOD 2 consolidates shells and reduces approved GFA.
Supporting source ↗Contractor anticipates completion of announced expansion works; campus-wide commissioning is not established.
Supporting source ↗Advertised design; reconcile with later consent modification.
Source ↗Design statement; certification scope available on request, not independently established.
Source ↗Operator design comparison; baseline and actual performance undisclosed.
Source ↗August 2026 consent summary reduces original 122,546 m²; differs from advertised technical area and requires reconciliation.
Source ↗Approved consolidation from ten shells; mechanical plant relocated to ground level.
Source ↗2024 AirTrunk acquisition; registered site owner remains unknown.
Source ↗General customer enquiries and Sydney office telephone, not a facility-specific contact.
Source ↗Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-09
Operator identifies Western Sydney hyperscale campus, 400+ MW total capacity, technical areas, power feed and design specifications.
Published 2021-11-04 · Retrieved 2026-10-09
Announcement describes nine phases, 320+ MW IT load and proximity to separately named SYD1; page also displays a June 2024 update date.
Published 2025-12-24 · Retrieved 2026-10-09
Lists SYD3 among Australian campuses at 330 MW+; does not specify power basis or commissioned load.
Published 2026-07-30 · Retrieved 2026-10-09
A W Edwards awarded expanded delivery contract for 400+ MW SYD3; works scheduled from July 2026 through mid-2028.
Published Date unavailable · Retrieved 2026-10-09
SSD-41589232 approved 15 September 2023; describes 400 MW total power consumption in Blacktown LGA.
Published 2022-09-09 · Retrieved 2026-10-09
Cover gives 33°47′51.7″S, 150°52′33.6″E. Section 3.1 places property south of Huntingwood Drive, fronting the Western Motorway corridor.
Published Date unavailable · Retrieved 2026-10-09
Identifies SYD3 construction site and A W Edwards; April 2026 tour meeting address is 45 Huntingwood Drive, differing from planning address.
Published Date unavailable · Retrieved 2026-10-09
Modification approved 28 August 2026 consolidates ten shells into five, reduces GFA from 122,546 to 64,346 m² and relocates mechanical plant.
Published Date unavailable · Retrieved 2026-10-09
Operator continues to list SYD3 at 400+ MW as coming soon.
Published 2025-10-28 · Retrieved 2026-10-09
Confirms Blackstone and CPP Investments acquired AirTrunk in 2024 alongside founder Robin Khuda; this establishes corporate ownership, not property title.
Published Date unavailable · Retrieved 2026-10-09
Publishes general customer enquiries and Sydney office telephone; office address is distinct from facility.
Name: AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre; SYD3 Sydney West | AirTrunk
Aliases: SYD3 Sydney West | AirTrunk
Kind: SYD3 Sydney West | AirTrunk; AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre
Country: AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne; Bouygues Construction secures expanded contract for AirTrunk's major hyperscale data centre campus in Australia
Region: AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre; 51 Huntingwood Drive Data Centre | NSW Planning Portal
City: Data Centre Development: 51 Huntingwood Drive, Huntingwood — Traffic and Transport Assessment; NAWIC NSW site tour: AirTrunk SYD3 Data Centre at Huntingwood
Metro: SYD3 Sydney West | AirTrunk; AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre
Address: 51 Huntingwood Drive Data Centre | NSW Planning Portal; Data Centre Development: 51 Huntingwood Drive, Huntingwood — Traffic and Transport Assessment
Operator: SYD3 Sydney West | AirTrunk; AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre; Bouygues Construction secures expanded contract for AirTrunk's major hyperscale data centre campus in Australia
Business Model: SYD3 Sydney West | AirTrunk; AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre
Scale: SYD3 Sydney West | AirTrunk; AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre
Statuses: Bouygues Construction secures expanded contract for AirTrunk's major hyperscale data centre campus in Australia; Our Story | AirTrunk
Summary: AirTrunk expands Western Sydney region with new SYD3 hyperscale data centre; AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne; Bouygues Construction secures expanded contract for AirTrunk's major hyperscale data centre campus in Australia; 51 Huntingwood Drive Data Centre MOD 2 — Design Updates; Our Story | AirTrunk
Location: Data Centre Development: 51 Huntingwood Drive, Huntingwood — Traffic and Transport Assessment