北海道苫小牧データセンター — SoftBank facility page ↗
Published Date unavailable · Retrieved 2026-10-09
Names the facility, targets FY2026 opening, and describes future 700,000 m² grounds and receiving capacity above 300 MW.
Japan / Site
北海道苫小牧AIデータセンター · 北海道苫小牧データセンター · Hokkaido Tomakomai Data Center · Core Brain
AI data-center site in Tomakomai, Hokkaido, developed initially by SoftBank and IDC Frontier. Construction is documented, with first-phase opening targeted for FY2026, ending March 2027. Initial planned maximum receiving capacity is 50 MW; future campus disclosures describe 300 MW or more than 300 MW. These are receiving-power claims, not established IT load. Future expansion is planned; opening and energized capacity have not been established.
Statements retain their dates, definitions and development scope. Do not add these rows together.
| Claim / measurement | Scope and status | As of | Evidence and accounting |
|---|---|---|---|
| 50 MW Grid connection | Initial planned data-hall building maximum receiving capacity Planned · cumulative | 2026-10-09 | Reported claim ↗ Excluded from capacity totals. As-of is retrieval date of an undated operator KPI page; FY2026 operation is a target. Footnote defines receiving capacity, not IT load or measured energized capacity. |
| 300 MW Grid connection | Future maximum campus receiving capacity Planned · cumulative | 2026-10-09 | Conflicting claim ↗ Excluded from capacity totals. As-of is retrieval date; disclosure belongs to Integrated Report 2025, whose exact publication date was not established. Maximum 300 MW differs from above-300 MW language elsewhere; includes expansion and must not be added to initial 50 MW. |
| >300 MW Grid connection | Ultimate expanded site receiving capacity Planned · cumulative | 2023-11-07 | Conflicting claim ↗ Excluded from capacity totals. As-of is announcement date. Expected future receiving capacity exceeds 300 MW; current facility page repeats this wording. Conflicts with the integrated report’s maximum-300 MW wording; no IT-load conversion or summation is supported. |
SoftBank and IDC Frontier announced joint development and subsidy selection.
Supporting source ↗Operator reports ceremony held at the construction site.
Supporting source ↗Scheduled transfer announced in December 2025; current service page carries an effective-date absorption-split notice. Property-title transfer is not established.
Supporting source ↗SoftBank announced Nature Symbiosis Site certification for property woodland; this is not a data-center operational certification.
Supporting source ↗Target fiscal year ends March 31, 2027; an actual opening date was not established.
Supporting source ↗Future campus scale; not established building floor area or first-phase developed area.
Source ↗Announced suppliers are SB Power and Hokkaido Electric Power; actual procurement and operational performance are unconfirmed.
Source ↗Mixed internal and external compute use; retail colocation terms and named tenants were not established.
Source ↗Historical developer relationship; subsequent data-center business transfer to SoftBank is separately recorded.
Source ↗2025 report expectations, not independently established final expenditure.
Source ↗Announced June 30, 2026; applies to conserved woodland rather than facility uptime, energy efficiency or technical certification.
Source ↗Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-09
Names the facility, targets FY2026 opening, and describes future 700,000 m² grounds and receiving capacity above 300 MW.
Published 2023-11-07 · Retrieved 2026-10-09
Joint development in Tomakomai, Hokkaido; initial 50 MW scale, future receiving capacity above 300 MW, internal AI use and external academic/business access. Renewable supply planned from SB Power and Hokkaido Electric Power.
Published 2026-02-25 · Retrieved 2026-10-09
Identifies the named site in Tomakomai City, Hokkaido, Japan; explicitly under construction and targeting FY2026, ending March 31, 2027.
Published 2025-05-01 · Retrieved 2026-10-09
Reports actual groundbreaking on April 15, 2025; identifies SoftBank and subsidiary IDC Frontier as developers. Labels future-property imagery as a simulated rendering.
Published Date unavailable · Retrieved 2026-10-09
Printed page 23 targets first-phase completion and opening in FY2026 at 50 MW scale; describes future maximum receiving capacity of 300 MW, approximately ¥65 billion project cost and up to ¥30 billion subsidy.
Published Date unavailable · Retrieved 2026-10-09
FY2026 KPI targets Tomakomai operation at 50 MW; footnote explicitly defines this as maximum receiving capacity of the planned data-hall building.
Published 2025-12-25 · Retrieved 2026-10-09
Announces transfer of IDC Frontier’s data-center business to SoftBank, with scheduled effective date April 1, 2026.
Published Date unavailable · Retrieved 2026-10-09
Current SoftBank service lists Tomakomai and carries an April 1, 2026 notice concerning the data-center business absorption split.
Published Date unavailable · Retrieved 2026-10-09
Comment dated November 7, 2023 confirms SoftBank and IDC Frontier announced a data-center location in Tomakomai.
Published 2026-06-30 · Retrieved 2026-10-09
Announces Ministry of the Environment certification for woodland within the data-center property, alongside ongoing development and biodiversity conservation.
Published 2026-08-03 · Retrieved 2026-10-09
Recent operator report still describes development in progress, FY2026 opening planned, and approximately 700,000 m² site area.
Name: Building for the AI Era: An Inside Look at SoftBank Corp.’s Next-generation AI Data Center in Hokkaido; Laying the Foundation for the AI Era: Construction Begins on Hokkaido Tomakomai AI Data Center
Aliases: 北海道苫小牧データセンター — SoftBank facility page; Construction of Core Brain — SoftBank and IDC Frontier announcement; Building for the AI Era: An Inside Look at SoftBank Corp.’s Next-generation AI Data Center in Hokkaido
Kind: 北海道苫小牧データセンター — SoftBank facility page; Laying the Foundation for the AI Era: Construction Begins on Hokkaido Tomakomai AI Data Center
Region: Construction of Core Brain — SoftBank and IDC Frontier announcement; Building for the AI Era: An Inside Look at SoftBank Corp.’s Next-generation AI Data Center in Hokkaido
City: Construction of Core Brain — SoftBank and IDC Frontier announcement; Tomakomai mayor’s 2023 comments — SoftBank entry
Operator: 北海道苫小牧データセンター — SoftBank facility page; Absorption-type company split with wholly owned IDC Frontier; SoftBank data-center service
Statuses: Building for the AI Era: An Inside Look at SoftBank Corp.’s Next-generation AI Data Center in Hokkaido; SoftBank World 2026 exhibition report
Summary: Construction of Core Brain — SoftBank and IDC Frontier announcement; Building for the AI Era: An Inside Look at SoftBank Corp.’s Next-generation AI Data Center in Hokkaido; SoftBank Integrated Report 2025 — Long-term Growth Strategy; AIとの共存社会を支える次世代社会インフラの実現; Absorption-type company split with wholly owned IDC Frontier; SoftBank World 2026 exhibition report
Location: Construction of Core Brain — SoftBank and IDC Frontier announcement; Tomakomai mayor’s 2023 comments — SoftBank entry
Stable identifier: 5b64adc4-f9d3-480a-b9bf-b8f13564bec8