Microsoft cloud data-center campus in Kolabacken, Sundsberg, comprising HEL04 and planned HEL05/HEL06 buildings. Construction remained underway in September 2026. The 2024 EIA assessed approximately 144 MW combined IT capacity; this is a planned campus claim, not commissioned capacity. Fortum's neighboring heat-production plant is a separate asset.
Sources and references
Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-07
April 2026 update describes first-building facade/interior work and second-building foundations. June event address is Sundsbergin yritystie 19, 02450 Masala. Winthrop became main contractor in June 2025.
Published 2026-04-28 · Retrieved 2026-10-07
Microsoft confirms second-phase investment and permits for three separate Finnish campuses. First-phase construction expected to finish around the 2026–2027 year boundary, with commissioning preparation afterward; regional cloud services are intended.
Published 2025-04-22 · Retrieved 2026-10-07
Permit granted with commencement rights. Identifies Microsoft 3465 Finland Oy as applicant, parcel 257-483-0002-0126, 516530 m², and HEL05/HEL06 at Sundsbergin yritystie 19, 02450 Sundsberg. HEL04 was covered by the first-phase permit.
Published 2026-09-24 · Retrieved 2026-10-07
Explicit update date 24 September 2026. First building undergoing equipment installation, interior and external works; second building undergoing structural steel, facade, roofing and floor work. Backup-generator tests are upcoming.
Published Date unavailable · Retrieved 2026-10-07
Search-indexed original report passages identify the assessed three-building, approximately 50 ha project and approximately 144 MW IT capacity under VE1. Report is identified as 2024; exact publication day unavailable. Direct PDF opening failed, so evidence is limited to indexed passages.
Published Date unavailable · Retrieved 2026-10-07
Planning consultant identifies Kolabacken in Sundsberg and EKE-Rakennus Oy as historical landowner commissioning planning. Illustrative image is explicitly labeled a rendering.
Published 2026-05-06 · Retrieved 2026-10-07
Kolabacken and Hepokorpi heat plants have started using ambient-air heat pumps and electric boilers. Data-center waste heat integration is scheduled to start in phases in 2027. This does not establish data-center operation.
Published Date unavailable · Retrieved 2026-10-07
Municipality identifies its location in western Uusimaa adjoining the capital region and membership in Helsinki Region Transport.
Published 2025-03-14 · Retrieved 2026-10-07
Municipality distinguishes first-phase HEL04 from second-phase HEL05 and HEL06, two two-story data-center and office buildings.
Published Date unavailable · Retrieved 2026-10-07
Pages 12–13 locate the project between Länsiväylä, Kehä III and Sundsbergintie; identify HEL04/05/06 and two power supply connections. HEL04 backup-generator fuel-input power is approximately 160 MW, not IT capacity.
Profile field evidence
Name: Kirkkonummi datacenter project updates — Microsoft Local; Kirkkonummen datakeskus — Sweco
Aliases: Kirkkonummi datacenter project updates — Microsoft Local; Kirkkonummen datakeskus — Sweco
Kind: Microsoft käynnistää pääkaupunkiseudun datakeskusalueen toisen vaiheen rakentamisen; Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase; Microsoftin datakeskushankkeen toisen vaiheen rakentamislupa on vireillä
Country: Microsoft käynnistää pääkaupunkiseudun datakeskusalueen toisen vaiheen rakentamisen; Kirkkonummi, Finland — Project Updates — Winthrop Technologies; Fortum has started heat production at two large data centre sites in Finland
Region: Kirkkonummen asuinalueet — Municipality of Kirkkonummi
City: Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase; Kirkkonummen datakeskus — Sweco
Metro: Fortum has started heat production at two large data centre sites in Finland; Kirkkonummen asuinalueet — Municipality of Kirkkonummi
Address: Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase
Operator: Kirkkonummi datacenter project updates — Microsoft Local; Microsoft käynnistää pääkaupunkiseudun datakeskusalueen toisen vaiheen rakentamisen
Business Model: Microsoft käynnistää pääkaupunkiseudun datakeskusalueen toisen vaiheen rakentamisen
Statuses: Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase; Kirkkonummi, Finland — Project Updates — Winthrop Technologies; Microsoftin datakeskushankkeen toisen vaiheen rakentamislupa on vireillä
Summary: Microsoft käynnistää pääkaupunkiseudun datakeskusalueen toisen vaiheen rakentamisen; Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase; Kirkkonummi, Finland — Project Updates — Winthrop Technologies; Kirkkonummi — Ympäristövaikutusten arviointi; Fortum has started heat production at two large data centre sites in Finland
Location: Rakennuslupa LP-257-2024-02386 / Sundsbergin yritystie 19 — second phase; Kirkkonummi municipal executive board minutes — Microsoft environmental permit consultation