Revision 3 · Current
2026-10-10 02:09 UTC
Published profile snapshot
EdgeConneX KUL03 Cyberjaya campus · Malaysia · EdgeConneX
EdgeConneX hyperscale campus in Cyberjaya, Malaysia. Originally announced as nine buildings on approximately 30 acres, with 22.4 MW initial capacity included within a 200 MW design. Later evidence describes a 270 MW project and three facilities with 72 MW IT load each; these figures and scopes remain unreconciled. Construction is supported, but commissioned capacity is unconfirmed. July 2026 reporting targets phase one for Q1 2027, versus the earlier Q1 2026 target.
Capacity statements: 9 · Sources: 15
200 MW (exact) · unspecified · Advertised full-build/design capacity; commissioned share unconfirmed · 2026-09-11
22.4 MW (exact) · unspecified · Cyberjaya initial capacity within advertised campus design · None
200 MW (exact) · unspecified · Cyberjaya advertised ultimate design · None
200 MW (gt) · unspecified · Cyberjaya campus announced in September 2023 · 2023-09-11
270 MW (exact) · unspecified · Cyberjaya overall project described by operator in June 2025 · 2025-06-25
22 MW (exact) · it · KUL21 tranche one, Lot 124702 · None
72 MW (exact) · it · KUL21 facility within Cyberjaya campus · None
72 MW (exact) · it · KUL22 facility within Cyberjaya campus · None
72 MW (exact) · it · KUL23 facility within Cyberjaya campus · None