Princeton Digital Group TY1 Campus · Japan · Princeton Digital Group
PDG's two-building hyperscale colocation campus in Saitama City, Greater Tokyo, has a reported ultimate IT capacity of 96 MW. Phase 1 launched on 24 April 2025; contemporary reporting described continuing Phase 1 fit-out and Phase 2 site preparation. DC2 assessment documentation describes a build in progress with estimated live services on 30 June 2028. The campus capacity should not be treated as fully commissioned operational power.
Capacity statements: 4 · Sources: 11
96 MW (exact) · it · Ultimate two-building TY1 campus capacity; includes operational Phase 1 and subsequent build-out · 2025-04-24
48 MW (exact) · it · TY1 DC1 design critical IT capacity · 2025-01-31
48 MW (exact) · it · TY1 DC2 design critical IT capacity · 2025-01-31
100 MW (approx) · it · Historical ultimate campus development · 2022-06-13