Revision 3 · Current

2026-09-11 12:15 UTC

Published profile snapshot

Google Elmina data center · Malaysia · Google

Google development at Elmina Business Park. A 2024 industry report attributes 80 MW to the initial Gamuda/Pearl construction project; the measurement basis and current full-campus MW remain unverified.

Capacity statements: 1 · Sources: 4

80 MW (exact) · unspecified · Initial Elmina construction project; current campus total not established · 2024-05-27

Revision 2

2026-09-11 11:26 UTC

Published profile snapshot

Google Elmina data center · Malaysia · Google

Google development at Elmina Business Park. A 2024 industry report attributes 80 MW to the initial Gamuda/Pearl construction project; the measurement basis and current full-campus MW remain unverified.

Capacity statements: 1 · Sources: 3

80 MW (exact) · unspecified · Initial Elmina construction project; current campus total not established · 2024-05-27

Revision 1

2026-09-11 10:44 UTC

Published profile snapshot

Google Elmina data center · Malaysia · Google

Discovery draft: >5 MW eligibility remains unconfirmed. Physical data-center development only; cloud region is not an additional facility. CSV's ~100 MW not corroborated.

Capacity statements: 0 · Sources: 1