AI and cloud colocation facility within the Macquarie Park Data Centre Campus in Sydney’s north zone. Operator reports 47 MW ultimate IT load; initial 6 MW commissioning was targeted for September 2026, followed by a further 13 MW by June 2027. Actual service commencement is unconfirmed. IC2 and IC3 East are separate facilities sharing the campus; the newly acquired METC project is a separate campus.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Macquarie Data Centres
Ownership
Macquarie Technology Group
Business model / scale
Colocation / Hyperscale
Region / metro
New South Wales / Sydney
City / locality
Macquarie Park
Address
17–23 Talavera Road, Macquarie Park, New South Wales, Australia
Location
Property address established through NSW planning records; no corroborated facility point established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
47 MW
IT load
IC3 Super West ultimate facility capacity
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. Undated operator page retrieved on this date; ultimate IT load, not proof of commissioned capacity. Exceeds 5 MW eligibility threshold.

6 MW
IT load
IC3 Super West initial Phase 1 fitout
Under Construction · incremental
2026-08-26Reported claim ↗

Excluded from capacity totals. Announcement date; expected completion September 2026. IT basis corroborated by operator Phase 1 description in s7; actual delivery unconfirmed.

13 MW
Unspecified power
IC3 Super West additional Phase 2
Planned · incremental
2026-08-26Reported claim ↗

Excluded from capacity totals. Announcement date; additional deployment expected June 2027. Included within ultimate facility capacity.

19 MW
Unspecified power
IC3 Super West deployment supported by secured equipment
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. Retrieval date of FY26 presentation, whose publication day was not independently established. Represents initial 6 MW plus further 13 MW; equipment procurement is not commissioned IT capacity.

65 MW
IT load
Entire Macquarie Park campus including IC2, IC3 East and IC3 Super West
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. Undated development page retrieved on this date describes potential campus IT load; overlaps facility claims and must not be assigned solely to Super West.

38 MW
Facility power
IC3 Super West expansion in November 2023 planning assessment
Planned · incremental
2023-11-27Reported claim ↗

Excluded from capacity totals. Assessment signature date. Historical proposed total power consumption for expansion; incompatible with treating later 47 MW IT design as the same basis/design snapshot.

66 MW
Facility power
Entire Talavera Road campus after assessed expansion
Planned · cumulative
2023-11-27Reported claim ↗

Excluded from capacity totals. Assessment signature date; historical overall site consumption after expansion, including existing 28 MW. Distinct from later 65 MW campus IT claim.

Development timeline

  1. 2024-01-19 · actual_approval

    State significant development approved

    SSD-24299707 approved by Independent Planning Commission.

    Supporting source ↗
  2. 2025-12-03 · announcement

    External structure completion announced

    Operator published topping-out announcement; publication day is not assumed to be ceremony day.

    Supporting source ↗
  3. 2026-08-26 · announcement

    Phased delivery schedule reaffirmed

    Group results forecast September 2026 completion for initial 6 MW and June 2027 delivery of an additional 13 MW.

    Supporting source ↗
  4. 2026-09 · planned_completion

    Initial phase completion target

    Actual completion or service commencement not established by retrieved evidence.

    Supporting source ↗
  5. 2027-06 · planned_delivery

    Additional Phase 2 deployment

    Further 13 MW planned; retained as part of this facility rather than a separate site.

    Supporting source ↗

Disclosed specifications

Technical space

11,700 m²

Operator-reported technical space, not total gross building area.

Source ↗

Campus land area

Approximately 2 hectares

Entire existing Talavera Road property; not exclusive Super West footprint.

Source ↗

Cooling

Air and direct-to-chip liquid cooling

FY26 presentation describes flexible cloud, enterprise and AI deployment design.

Source ↗

Utilities readiness

End-state power and water reported commissioned

Utility readiness does not establish completed IT fitout or occupied capacity.

Source ↗

Campus relationship

Macquarie Park Data Centre Campus with IC2 and IC3 East

Named campus relationship retained in text; parent remains null because no linked parent record was supplied.

Source ↗

Initial investment

Approximately A$350 million

Phase 1 core and shell plus initial 6 MW IT fitout.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

IC3 Super West Data Centre ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies an Australian AI/cloud colocation facility at its Sydney north-zone campus, currently under construction, with 47 MW IT load and 11,700 square metres technical space.

FY26 Group Investor Presentation ↗

Published Date unavailable · Retrieved 2026-10-09

FY26 results presentation reports completed core and shell, ongoing mechanical/electrical fitout, initial 6 MW targeted for September 2026, equipment for a further 13 MW and 19 MW cumulative deployment, 47 MW design capacity, and 65 MW campus including IC2 and IC3 East. End-state power and water reported commissioned.

Sydney Data Centres and Colocation ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies IC3 Super West in Macquarie Park, New South Wales, as coming soon and lists 47 MW IT load.

IC3 Superwest Project ↗

Published Date unavailable · Retrieved 2026-10-09

Operator development page links statutory approvals and identifies potential campus IT load of 65 MW; occupation-certificate link could not be reliably inspected.

Profile field evidence

Name: IC3 Super West Data Centre

Aliases: FY26 Group Investor Presentation; Macquarie Technology delivers twelve consecutive years of EBITDA growth

Kind: IC3 Super West Data Centre; Treasurer ‘Tops Out’ Macquarie Data Centres’ newest 47MW AI and cloud data centre

Country: IC3 Super West Data Centre

Region: Sydney Data Centres and Colocation

City: Talavera Road Data Centre Campus Expansion — State Significant Development Assessment

Metro: IC3 Super West Data Centre; Sydney Data Centres and Colocation

Address: Talavera Road Data Centre Campus Expansion — State Significant Development Assessment

Operator: IC3 Super West Data Centre; Talavera Road Data Centre Campus Expansion — State Significant Development Assessment

Owner: Project Dawn — 2025 Investor Day Presentation

Business Model: IC3 Super West Data Centre

Scale: IC3 Super West Data Centre; IC3 Superwest Project

Statuses: IC3 Super West Data Centre; Macquarie Technology delivers twelve consecutive years of EBITDA growth

Summary: IC3 Super West Data Centre; FY26 Group Investor Presentation; Macquarie Technology delivers twelve consecutive years of EBITDA growth

Location: Talavera Road Data Centre Campus Expansion — State Significant Development Assessment