NEXTDC M2 Melbourne · Australia · NEXTDC
Operational NEXTDC colocation site in Melbourne's Tullamarine suburb, opened in November 2017 and undergoing expansion. Published target and brochure capacities differ and do not establish commissioned capacity.
Capacity statements: 11 · Sources: 10
120 MW (gte) · it · M2 target IT capacity · 2026-10-09
150 MW (exact) · unspecified · M2 brochure headline capacity · 2026-10-09
72 MW (exact) · unspecified · M2 three-building expansion · 2026-10-09
40 MW (exact) · unspecified · Original M2 full build-out · 2018-03-16
120 MW (exact) · unspecified · M2 total planned power · 2024-08-27
11 MW (exact) · unspecified · M2 built capacity added during FY24 · 2024-06-30
18 MW (exact) · unspecified · M2 built capacity in progress · 2024-06-30
6 MW (exact) · unspecified · M2 built capacity added during 1H25 · 2024-12-31
18 MW (exact) · unspecified · M2 capacity in progress at 1H25 · 2024-12-31
20 MW (gte) · unspecified · Further M2 capacity in planning at 1H25 · 2024-12-31
30 MW (exact) · unspecified · M2 capacity continuing to be progressed at 1H26 · 2025-12-31