Operational NEXTDC colocation facility in Macquarie Park, Sydney, Australia, distinct from S2 and S5. The operator reports 16 MW IT capacity; its Sydney comparison table describes this as target IT capacity. This exceeds 5 MW as a reported capacity claim, without establishing actual consumption or fully commissioned load.
Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
Site / building photo
Operator-labelled S1 Sydney front-of-building night exterior; capture date and visual suitability unverified.
Published date unknown · Captured date unknown · Checked 2026-10-09
Research-selected property image; reviewer must confirm site identity, suitability and rights before publication.
Published by NEXTDC. Photographer attribution and reuse licence not established; permission review required. Filename is not capture-date evidence. Publication and capture dates were not independently established.
Site profile
Operator
NEXTDC
Ownership
NEXTDC group
Business model / scale
Colocation / Hyperscale
Region / metro
New South Wales / Sydney
City / locality
Sydney
Address
4 Eden Park Drive, Macquarie Park NSW 2113, Australia
Location
Facility point reported by PeeringDB, agreeing with the destination marker encoded in NEXTDC's published Google Maps directions link and the addressed S1 building on Mapcarta/OpenStreetMap. Not surveyed; property boundaries and entrance position unverified. Precision: approximate · -33.785263, 151.13149 View location on map →
Parent
Not assigned
Location detail
Facility point reported by PeeringDB, agreeing with the destination marker encoded in NEXTDC's published Google Maps directions link and the addressed S1 building on Mapcarta/OpenStreetMap. Not surveyed; property boundaries and entrance position unverified.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.
4 Eden Park Drive, Macquarie Park NSW 2113, Australia
Loading local map…
Capacity evidence
Statements retain their dates, definitions and development scope. Do not add these rows together.
Claim / measurement
Scope and status
As of
Evidence and accounting
16 MW IT load
S1 facility advertised IT capacity; comparison table calls it target IT capacity Operational · cumulative
Excluded from capacity totals. As-of is retrieval date of undated operator page, not commissioning date. Reported capacity exceeds 5 MW; commissioned amount and consumption remain unknown. Target terminology is corroborated by s2 and s10.
≈11 MW IT load
Historical S1 planned maximum IT load, as if complete Planned · cumulative
Excluded from capacity totals. As-of is the valuation effective date. Historical design claim differs from current 16 MW advertising; intervening capacity changes were not established. Do not add to current capacity.
3 MW IT load
Historical initial S1 infrastructure configuration Under Construction · cumulative
Excluded from capacity totals. As-of is the valuation effective date. Initial infrastructure figure within the historical planned facility, not an additional 3 MW or evidence of current load.
Development timeline
2013-01 · actual ownership change
S1 property sold to APDC
Operator history records completed sale of S1, M1 and P1 property assets to APDC.
Operator identifies S1 in Macquarie Park and reports 16 MW IT capacity, 5,800 square metres technical space and 2,800 racks; describes cooling, redundancy and interconnection services.
Lists S1 at 4 Eden Park Drive separately from S2 and S5; identifies operating Sydney colocation facilities and labels S1's 16 MW as target IT capacity.
Australian Energy Regulator identifies S1 at 4 Eden Park Drive, Macquarie Park NSW 2113, Australia. Current exemption effective 2 September 2013; NEXTDC Limited and Enel X Australia are registrants, not necessarily joint property owners.
Operator publishes S1's street address and Google Maps directions link. The link encodes destination coordinates -33.7852629,151.1314902, distinct from its viewport centre.
Reports completed takeover of APDC, including underlying S1, M1 and P1 properties, during the half-year ended 31 December 2018. Supports group ownership; exact present titleholding entity unconfirmed.
Operator brochure describes S1 as hyperscale colocation and lists 16 MW target IT capacity, 5,800 square metres technical space, 2,800 racks, four data halls and seven interconnect rooms. Also records TRUE certification in August 2023. Publication date not established from filename.
Valuation letter dated 15 November 2012, effective 30 September 2012, describes S1's 9,642 square metre land parcel, planned 19,467 square metre GLA, approximately 11 MW ultimate IT load and initial 3 MW infrastructure. Describes three feeds totalling 20 MVA; MVA is not converted to MW.
Operator-labelled S1 Sydney front-of-building night exterior; capture date and visual suitability unverified. Original image: https://www.nextdc.com/hubfs/NXT_Facility_S1_ExteriorNight_2015.09_9096.jpg