Australia / Facility

D2 Darwin Data Centre · D2 Darwin

Under Construction

NEXTDC is developing D2 in Darwin CBD adjacent to its existing D1 facility. The operator advertises 6MW+ ultimate IT capacity, while its August 2026 presentation reports 1.5MW in progress for a contracted submarine cable and targets practical completion in 1HFY27. No operational opening was established.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
NEXTDC
Ownership
Unknown / not established
Business model / scale
Colocation / Edge
Region / metro
Northern Territory / Unknown
City / locality
Darwin
Address
2–6 Ryko Court, Darwin City, NT 0800, Australia
Location
Address identified through planning evidence and corroborating property directory; no independently sourced facility point established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
≥6 MW
IT load
D2 ultimate advertised IT capacity
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. Undated operator page observed on research date; 6MW+ is preserved as a lower-bound claim. Additional to Darwin footprint, not evidence that all capacity is built or operational.

≈6 MW
Unspecified power
D2 total planned power
Planned · cumulative
2026-08-27Reported claim ↗

Excluded from capacity totals. Presentation publication date; source says ~6MW+. Overlaps the advertised ultimate IT capacity and must not be added to it; approximation and plus sign retained here.

1.5 MW
IT load
D2 capacity in progress for a contracted submarine cable
Under Construction · incremental
2026-08-27Reported claim ↗

Excluded from capacity totals. Presentation publication date; page 18 reports 1.5MW in progress within its IT-capacity discussion. Page 30 describes initial capacity as ~1.5MW. This is a subset of ultimate D2 capacity, not an addition to 6MW+.

Development timeline

  1. 2026-03 · actual_reported

    Structural topping out reported

    Operator confirms structural topping out; March precision follows dated DCD reporting, not a verified ceremony date.

    Supporting source ↗
  2. 1HFY27 · planned

    Practical completion target

    August 2026 operator presentation retains a first-half FY27 practical-completion target. Actual completion and customer commissioning remain unestablished.

    Supporting source ↗

Disclosed specifications

Building

Seven levels

Builder describes the current D2 facility.

Source ↗

Data halls

Four

Builder disclosure; not a rack-capacity estimate.

Source ↗

Electrical infrastructure

Six prefabricated switch rooms; six generators

Ratings, redundancy configuration and fuel endurance not established.

Source ↗

Cooling

Six cooling towers

Cooling capacity, water use and liquid-cooling availability not established.

Source ↗

Certification target

Uptime Institute Tier IV

Operator labels this a target; achieved certification is not established.

Source ↗

Project architect

Hames Sharley

Builder identifies the architect and other project partners.

Source ↗

Connectivity development

1.5MW in progress for a new contracted submarine cable

Latest opened operator presentation; cable identity and commercial availability not independently established.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

D2 Darwin Data Centre ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies D2 in Darwin CBD, Northern Territory, in development; advertises 6MW+ IT capacity and target Uptime Institute Tier IV certification.

Development Consent Authority Darwin Division — PA2025/0044, Item 2 ↗

Published Date unavailable · Retrieved 2026-10-09

Search-indexed planning text explicitly identifies D2 at 2–6 Ryko Court, Darwin City, adjacent to D1 at 8 Ryko Court; proposes offices and a seven-storey data centre. Direct PDF opening failed, so full record and consent outcome were not inspected.

NEXTDC FY26 Results Presentation ↗

Published 2026-08-27 · Retrieved 2026-10-09

Pages 18 and 30 identify D2 as an edge network development with 1.5MW in progress for a contracted submarine cable; total planned power ~6MW+, initial capacity ~1.5MW, practical completion 1HFY27.

NEXTDC D2 Darwin Data Centre — Kapitol ↗

Published Date unavailable · Retrieved 2026-10-09

Builder identifies NEXTDC as client, Darwin Northern Territory location and under-construction status. Describes seven levels, four data halls, six prefabricated switch rooms, six generators and six cooling towers.

NEXTDC D2 Darwin Data Center — Data Center Map ↗

Published Date unavailable · Retrieved 2026-10-09

Directory corroborates 2–6 Ryko Court, 0800 Darwin, Australia, under-construction status and advertised suites, cages and private cabinets; identifies an adjoining Darwin campus listing.

Profile field evidence

Name: D2 Darwin Data Centre; NEXTDC D2 Darwin Data Centre — Kapitol

Aliases: D2 Darwin Data Centre; NEXTDC FY26 Results Presentation

Kind: NEXTDC D2 Darwin Data Centre — Kapitol

Country: NEXTDC D2 Darwin Data Center — Data Center Map; Australia's NextDC tops out 6MW data center in Darwin

Region: D2 Darwin Data Centre; NEXTDC D2 Darwin Data Centre — Kapitol

City: D2 Darwin Data Centre; NEXTDC D2 Darwin Data Centre — Kapitol

Address: Development Consent Authority Darwin Division — PA2025/0044, Item 2; NEXTDC D2 Darwin Data Center — Data Center Map

Operator: D2 Darwin Data Centre; NEXTDC FY26 Results Presentation

Business Model: NEXTDC D2 Darwin Data Center — Data Center Map; D2 Darwin Reaches Structural Completion — NEXTDC public post

Scale: NEXTDC FY26 Results Presentation

Statuses: NEXTDC FY26 Results Presentation; NEXTDC D2 Darwin Data Centre — Kapitol

Summary: D2 Darwin Data Centre; NEXTDC FY26 Results Presentation; NEXTDC D2 Darwin Data Centre — Kapitol

Location: Development Consent Authority Darwin Division — PA2025/0044, Item 2; NEXTDC D2 Darwin Data Center — Data Center Map

Stable identifier: c07bd760-f98c-4981-b38a-01b490b96205