CDC's Eastern Creek campus in western Sydney comprises six operational data centres according to the current operator page, which reports over 200 MW of capacity without identifying the power basis. The campus is distinct from Marsden Park and neighboring Project Atlas. Historical operating, expansion and design figures overlap and must not be added.
Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.
Site profile
Operator
CDC Data Centres
Ownership
CDC
Business model / scale
Colocation / Unknown
Region / metro
New South Wales / Sydney
City / locality
Eastern Creek
Address
17 Roberts Road, Eastern Creek, NSW 2766, Australia
Location
Campus locator represented by the OpenStreetMap-derived EC1 building point published by Mapcarta. Roberts Road address corroborated by government consent; this is not a surveyed campus centroid or verified Google Maps marker. Precision: approximate · -33.818, 150.83948 View location on map →
Parent
Not assigned
Location detail
Campus locator represented by the OpenStreetMap-derived EC1 building point published by Mapcarta. Roberts Road address corroborated by government consent; this is not a surveyed campus centroid or verified Google Maps marker.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.
17 Roberts Road, Eastern Creek, NSW 2766, Australia
Loading local map…
Capacity evidence
Statements retain their dates, definitions and development scope. Do not add these rows together.
Claim / measurement
Scope and status
As of
Evidence and accounting
>200 MW Unspecified power
Eastern Creek campus; six operational data centres Operational · cumulative
Excluded from capacity totals. As-of is retrieval date of undated current operator page. Capacity basis and commissioned versus installed distinction are not stated.
123 MW Unspecified power
Eastern Creek EC1–EC4 combined Operational · cumulative
Excluded from capacity totals. As-of is unveiling date described in the article; historical CEO-reported combined capacity, overlapping current campus claim.
108 MW Unspecified power
Two additional Eastern Creek data centres Planned · incremental
Excluded from capacity totals. As-of is unveiling date. Construction was planned for 2023; article does not explicitly identify IT or facility basis. Historical proposal overlaps subsequent campus figures.
≥280 MW Unspecified power
Eastern Creek complete-campus design capacity Planned · cumulative
Excluded from capacity totals. As-of is retrieval date, not claim publication date: presentation is dated September 2025 with no day established. Displays 280MW+ and defines total built capacity based on current campus design; EC5/6 were then nearing completion. Not established as live IT load.
19 MW Unspecified power
Acquired Eastern Creek property, near-term expansion potential Planned · cumulative
Excluded from capacity totals. As-of is acquisition announcement date. Historical expansion potential, not actual delivered load, overlapping later campus claims.
Development timeline
2018-12-14 · announcement
Acquisition from DXC Technology announced
Infratil announced CDC's acquisition of the Eastern Creek facility and associated expansion land.
Operator identifies Eastern Creek as its first Sydney-region campus, states six operational data centres and over 200 MW capacity. Regional cooling and security statements are not separately quantified for this campus.
SSD-10330 concerns expansion of an existing data centre in Blacktown; approval dated 14 July 2020. Portal lists subsequent modifications, including high-voltage plant modification.
Schedule 1 identifies Canberra Data Centres Pty Ltd, 17 Roberts Road, Eastern Creek, Lot 2 DP 1159804. Modification table records building 5/6 changes on 17 April 2024 and generator/storage changes on 6 March 2026.
Presentation explicitly dated September 2025. Page 7 assigns Eastern Creek 280 MW+ total built capacity based on current campus design and describes EC5/6 nearing completion. Portfolio diagram states 100% asset ownership.
OpenStreetMap-derived EC1 building record gives 17 Roberts Road, NSW 2766, Australia and coordinates -33.818, 150.83948; identifies nearby campus buildings separately.
Campus record identifies CDC, Eastern Creek, Australia and linked EC1–EC4 facility records. Lists Vocus, CDC and MegaIX Sydney connectivity; these are directory disclosures rather than a complete circuit inventory.
Reproduces Infratil announcement of acquisition from DXC Technology, approximately 145,000 square metres of land and near-term expansion potential to 19 MW.
Describes customer ICT footprints, rack deployment and operation services across CDC campuses; supports classification as third-party colocation provision, by inference.