← LG Uplus Pyeongchon Mega Center

Published history

Restoring content creates a new revision. Previous revisions remain in the audit trail.

Revision 1 · Current

2026-10-07 12:47 UTC

Published profile snapshot

LG Uplus Pyeongchon Mega Center · South Korea · LG Uplus

LG Uplus operates this commercial data-center site in Anyang, comprising two data-center buildings and one office building. First-stage service opened in August 2015. The operator reports 165 MW maximum electricity receiving capacity; this is not a disclosed IT load. Pyeongchon 2 is a separate facility at a different address.

Capacity statements: 3 · Sources: 11

165 MW (exact) · grid · Pyeongchon Mega Center site; maximum electricity receiving capacity · 2026-10-07

165 MW (exact) · grid · Pyeongchon IDC development · 2014-04-24

165 MW (exact) · unspecified · Both internal phases of Pyeongchon Mega Center once delivered · 2015-06-01