NEXTDC S5 Sydney

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

S5 Sydney Data Centre · NEXTDC S5 Data Centre and Innovation Hub · S5 Macquarie Park

Planned

Planned NEXTDC data centre and innovation hub in Macquarie Park, Sydney, distinct from S1 and S2. The operator advertises 80MW+ of future IT capacity and 16,000 m² of technical space. NSW application SSD-63168959 remains under assessment with more information required. Operational capacity and commissioning dates are unestablished.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
NEXTDC
Ownership
NEXTDC group; precise registered landholding entity unconfirmed
Business model / scale
Colocation / Hyperscale
Region / metro
New South Wales / Sydney
City / locality
Sydney
Address
269 Lane Cove Road, Macquarie Park, NSW 2113, Australia
Location
Address and cadastral parcel established from NSW planning records: 269 Lane Cove Road, Lot 3 DP 1129811. No corroborated geographic point established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
≥60 MW
IT load
S5 whole-site target once built
Planned · cumulative
2023-04-12Reported claim ↗

Excluded from capacity totals. Date is the ASX announcement date. Source uses 60MW+ and makes delivery conditional on development approval; historical target subsequently revised.

≥80 MW
IT load
S5 whole-site future IT capacity
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of undated live operator page, not announcement or commissioning date. Source uses 80MW+; no operational availability established.

≈20 MW
Unspecified power
S5 expected Phase 1 capacity
Planned · incremental
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of the 2025 AGM presentation; exact publication date unestablished. Table labels this expected capacity, not delivered capacity. Power basis is not explicitly defined on the S5 table. Phase 1 overlaps the whole-site target and must not be added to it.

Development timeline

  1. FY23 · actual_acquisition_reported

    S5 site acquired

    FY23 annual report records acquisition near S1 and S2; exact transaction date and landholding entity unestablished.

    Supporting source ↗
  2. 2023-04-12 · announcement

    S5 target disclosed

    NEXTDC disclosed a 60MW+ IT target subject to development approval.

    Supporting source ↗
  3. 2023-11-08 · actual_planning

    Environmental assessment requirements issued

    NSW issued SEARs for SSD-63168959 at 269 Lane Cove Road.

    Supporting source ↗
  4. 2025-08-28 · announcement

    S5 capacity target revised

    FY25 results presentation reports a revision from 60MW to 80MW while planning works continue.

    Supporting source ↗

Disclosed specifications

Locality and local government

Macquarie Park; City of Ryde

Sydney locality identified by operator and NSW planning records.

Source ↗

Cadastral parcel

Lot 3 DP 1129811

Government assessment requirements identify the subject property.

Source ↗

Technical space

16,000 m²

Planned operator specification; not completed usable floor space.

Source ↗

Land area

Approximately 22,600 m²

Historical 2024 proposal specification, subject to approval and final engineering design.

Source ↗

Certification target

Uptime Institute Tier IV

Target only; awarded certification not established.

Source ↗

Planned connectivity

Data Centre Interconnect and AXON links with Sydney facilities

2024 proposal; current commissioned S5 connectivity unestablished.

Source ↗

Estimated development cost

AUD 1,532,941,000 excluding GST

WT Partnership estimate dated 29 September 2025; not expenditure incurred.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

S5 Sydney NEXTDC Data Centre ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies S5 in Macquarie Park as in planning, with future 80MW+ IT capacity, 16,000 m² technical space and target Uptime Tier IV certification.

NEXTDC Contracted Utilisation Update ↗

Published 2023-04-12 · Retrieved 2026-10-09

ASX release states expansion land secured for S5 and target IT capacity of 60MW+ once built, subject to development approval.

NEXTDC FY23 Annual Report ↗

Published Date unavailable · Retrieved 2026-10-09

Directors’ report for year ended 30 June 2023 states a new S5 site was acquired close to S1 and S2.

NEXTDC FY25 Results Presentation ↗

Published 2025-08-28 · Retrieved 2026-10-09

Presentation dated 28 August 2025 reports planning works for S5 and a capacity revision from 60MW to 80MW.

NEXTDC Annual General Meeting 2025 presentation ↗

Published Date unavailable · Retrieved 2026-10-09

S5 appears under hyperscale development projects: total power planned approximately 80MW+, expected approximately 20MW for Phase 1, design and town planning, subject to approval.

NEXTDC 2024 Entitlement Offer materials ↗

Published Date unavailable · Retrieved 2026-10-09

S5 specification slide reports approximately 22,600 m² land and 16,000 m² technical space; proposed interconnection through Data Centre Interconnect and AXON. Specifications subject to approval and final engineering design; image labelled artist’s impression.

Profile field evidence

Name: S5 Sydney NEXTDC Data Centre; NEXTDC S5 Data Centre and Innovation Hub — NSW Planning Portal

Aliases: S5 Sydney NEXTDC Data Centre; NEXTDC S5 Data Centre and Innovation Hub — NSW Planning Portal

Kind: NEXTDC S5 Data Centre and Innovation Hub — NSW Planning Portal; Planning Secretary’s Environmental Assessment Requirements letter — S5

Country: Planning Secretary’s Environmental Assessment Requirements letter — S5; Sydney Data Centre Colocation Services

Region: Planning Secretary’s Environmental Assessment Requirements letter — S5

City: S5 Sydney NEXTDC Data Centre; Sydney Data Centre Colocation Services

Metro: S5 Sydney NEXTDC Data Centre; Sydney Data Centre Colocation Services

Address: Planning Secretary’s Environmental Assessment Requirements letter — S5; NEXTDC S5 Data Centre — Estimated Development Cost

Operator: S5 Sydney NEXTDC Data Centre; Planning Secretary’s Environmental Assessment Requirements letter — S5

Owner: NEXTDC FY23 Annual Report

Business Model: Sydney Data Centre Colocation Services

Scale: NEXTDC Annual General Meeting 2025 presentation

Statuses: S5 Sydney NEXTDC Data Centre; NEXTDC S5 Data Centre and Innovation Hub — NSW Planning Portal

Summary: S5 Sydney NEXTDC Data Centre; NEXTDC S5 Data Centre and Innovation Hub — NSW Planning Portal; Planning Secretary’s Environmental Assessment Requirements letter — S5; Sydney Data Centre Colocation Services

Location: Planning Secretary’s Environmental Assessment Requirements letter — S5; NEXTDC S5 Data Centre — Estimated Development Cost

Stable identifier: dc70b325-6b0c-4fe6-8163-026bdeeef2f7