Digital Edge Seoul Bupyeong Campus (SEL2 & SEL3)

Seoul Bupyeong Campus · Digital Edge Bupyeong Campus

OperationalUnder Construction

Digital Edge campus developed with SK ecoplant. SEL2 operates; adjacent SEL3 is under construction. Campus power claims differ across dated sources and should not be aggregated.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Digital Edge
Ownership
Unknown / not established
Business model / scale
Colocation / Hyperscale
Region / metro
Incheon / Seoul metropolitan area
City / locality
Incheon
Address
422 Cheongcheon-dong, Bupyeong-gu, Incheon, South Korea
Location
Operator SEL2 specification-sheet point, used as an approximate campus reference; parcel address corroborated by local reporting, but footprint and point placement were not independently verified.
Precision: approximate · 37.518, 126.7109
View location on map →
Parent
Not assigned

Location detail

Operator SEL2 specification-sheet point, used as an approximate campus reference; parcel address corroborated by local reporting, but footprint and point placement were not independently verified.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.

422 Cheongcheon-dong, Bupyeong-gu, Incheon, South Korea

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
36 MW
Unspecified power
SEL2 first phase
Operational · incremental
2024-10-16Reported claim ↗

Excluded from capacity totals. Announcement date; rated capacity, not demonstrated utilization. Original release does not explicitly distinguish IT and facility power.

60 MW
Unspecified power
SEL3 second phase
Under Construction · incremental
2025-07-10Reported claim ↗

Excluded from capacity totals. Announcement date; future addition, not operational capacity.

96 MW
Unspecified power
Entire campus after SEL3 completion
Under Construction · cumulative
2025-07-10Conflicting claim ↗

Excluded from capacity totals. Announcement date; ultimate mixed-status campus scope. Conflicts with older totals; not added to phase claims.

≥100 MW
Unspecified power
Ultimate campus described at SEL2 launch
Planned · cumulative
2024-10-16Conflicting claim ↗

Excluded from capacity totals. Announcement date. Source writes 100+ MW; preserved as a lower-bound claim. Differs from subsequent 96 MW total.

120 MW
IT load
Historical full Bupyeong joint-venture development
Planned · cumulative
2022-05-05Conflicting claim ↗

Excluded from capacity totals. Industry article publication date, not commissioning date. Historical total IT power conflicts with later campus scope; operator sheet and developer article also retain 120 MW without an explicit basis.

120 MW
Unspecified power
Bupyeong development described by SK ecoplant
Under Construction · cumulative
2024-01-05Conflicting claim ↗

Excluded from capacity totals. Developer article date; historical development description, not proof of delivered capacity or a separate addition.

Development timeline

  1. 2024-08 · actual_reported

    SEL2 Ready-for-Service

    Later operator release dates SEL2 RFS to August 2024.

    Supporting source ↗
  2. 2024-10-16 · announcement

    SEL2 availability announced

    Public launch announcement confirms service availability.

    Supporting source ↗
  3. 2025-05 · actual_reported

    SEL3 construction began

    Operator reports start of second-phase construction.

    Supporting source ↗
  4. 2025-07-10 · announcement

    SEL3 financing secured

    KRW 800 billion Green Loan announced.

    Supporting source ↗
  5. 2027-Q4 · planned

    SEL3 service target

    Target Ready-for-Service quarter; not an achieved milestone.

    Supporting source ↗

Disclosed specifications

Developer

SK ecoplant, in partnership with Digital Edge

Partnership is established; legal ownership allocation remains unresolved.

Source ↗

SEL2 cabinet density

Up to 130 kW with liquid cooling

Conditional design capability; not evidence of installed customer density.

Source ↗

SEL2 design PUE

1.25 annualized

Design figure at launch, distinct from current advertised annual PUE.

Source ↗

Advertised annual PUE

1.28

Current campus page; measurement period and phase scope unspecified.

Source ↗

Colocation area and cabinets

10,966 m²; 3,480 cabinets

Shown beside 36 MW details, apparently SEL2; not established as total campus floor area.

Source ↗

Power redundancy and density

10 kVA per cabinet; N+1 SUPS; 100% dual-power SLA

Operator marketing specifications beside SEL2 details.

Source ↗

Advertised certifications

ISO 9001, 14001, 14064, 27001, 45001, 50001; SOC 2 Type II; PCI DSS; Tier 3; LEED Silver

Listed by operator; certificates, certification body and phase scope not inspected.

Source ↗

Connectivity

Cross Link to SEL1 and third-party telecommunications services

Historical sheet describes opening plans; current implementation not independently established.

Source ↗

Auxiliary energy proposal

330 kW solid oxide fuel cell

Developer's January 2024 planned auxiliary supply; commissioning not established. Excluded from load-capacity totals.

Source ↗

Public business contact

info@digitaledgedc.com

Operator general inquiry address.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

SEL2 Seoul Data Center ↗

Published Date unavailable · Retrieved 2026-10-07

Operator identifies SEL2 as the first phase of a 100+ MW Bupyeong-gu project.

SEL2 specification sheet ↗

Published Date unavailable · Retrieved 2026-10-07

Operator sheet provides parcel address and coordinates, historical 120 MW scope and connectivity plans. Copyright 2023 is not treated as publication date; an apparent Yeoksam access-text error reduces confidence in ancillary directions.

Profile field evidence

Name: South Korea Data Centers in Seoul and Busan

Aliases: South Korea Data Centers in Seoul and Busan; Digital Edge Secures Financing to Complete Major Data Center Campus

Kind: South Korea Data Centers in Seoul and Busan; Digital Edge Secures Financing to Complete Major Data Center Campus

Country: South Korea Data Centers in Seoul and Busan; Digital Edge Announces Availability of 36MW Data Center in South Korea; SEL2 specification sheet

Region: South Korea Data Centers in Seoul and Busan; SEL2 specification sheet

City: South Korea Data Centers in Seoul and Busan; SEL2 specification sheet

Metro: Digital Edge Announces Availability of 36MW Data Center in South Korea; Digital Edge Secures Financing to Complete Major Data Center Campus

Address: SEL2 specification sheet

Operator: South Korea Data Centers in Seoul and Busan; Digital Edge Announces Availability of 36MW Data Center in South Korea; Digital Edge Secures Financing to Complete Major Data Center Campus

Business Model: South Korea Data Centers in Seoul and Busan; Digital Edge Announces Availability of 36MW Data Center in South Korea

Scale: Digital Edge Secures Financing to Complete Major Data Center Campus

Statuses: South Korea Data Centers in Seoul and Busan; Digital Edge Secures Financing to Complete Major Data Center Campus

Summary: South Korea Data Centers in Seoul and Busan; Digital Edge Announces Availability of 36MW Data Center in South Korea; Digital Edge Secures Financing to Complete Major Data Center Campus; SEL2 specification sheet

Location: SEL2 specification sheet

Stable identifier: dd3f3081-f6e4-4668-8df1-03c67ff6fae3