Published profile snapshot

Colt Osaka Keihanna Data Centre · Japan · Colt Data Centre Services

Colt-operated hyperscale colocation site in Keihanna Science City, Seika, Kyoto Prefecture, serving the Osaka/Kansai market. Opened in March 2023 with phased delivery. Ultimate design claims of 45 and 45.9 MW differ from an undated operator completion post reporting 40.5 MW delivered; current commissioned IT capacity remains unresolved. The 2024 report also schedules expansion through Q3 2030, which requires reconciliation with the completion post.

Capacity statements: 5 · Sources: 14

45 MW (exact) · it · Ultimate consolidated site capacity · 2026-10-09

45.9 MW (exact) · unspecified · Designed capacity of consolidated site · 2023-03-13

8.1 MW (exact) · unspecified · Phase one · 2023-12-31

40.5 MW (exact) · unspecified · Total delivered across four phases · 2026-10-09

45.9 MW (exact) · it · Ultimate site capacity, phase seven schedule · 2030-09-30