Netherlands / Site

QTS Eemshaven

OperationalUnder ConstructionPlanned

QTS campus in Eemshaven Green Data Port with operational DC1, DC2 described as phased delivery, and DC3 under construction. The operator reports 200 MW planned gross renewable power across campus phases; this is not current IT load or a building allocation.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
Exterior of the Eemshaven facility, labeled by Baxtel; capture date unknown and campus phase not specified.

Site / building photo

Exterior of the Eemshaven facility, labeled by Baxtel; capture date unknown and campus phase not specified.

Published date unknown · Captured date unknown · Checked 2026-10-09

Research-selected property image; reviewer must confirm site identity, suitability and rights before publication.

baxtel.com · Source and attribution ↗
Image rights and date notes

Source attributes image to Baxtel. Photographer and reuse license not disclosed; permission must be resolved before import. Publication and capture dates were not independently established.

Site profile

Operator
QTS Data Centers
Ownership
Unknown / not established
Business model / scale
Colocation / Hyperscale
Region / metro
Groningen / Unknown
City / locality
Eemshaven
Address
Huibertgatweg 2, 9979 XZ Eemshaven, Netherlands
Location
Operator address corroborated by government property descriptions; no independently established point coordinate.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
200 MW
Facility power
Ultimate Eemshaven campus gross renewable power delivered in phases
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated operator page. Gross power classified as facility power; not IT load, current consumption or an allocation to DC1/DC2/DC3.

36 MW
Facility power
Facility described on Dutch operator page; building allocation unspecified
Unknown · unclear
2026-10-09Reported claim ↗

Excluded from capacity totals. Retrieval-date observation; page says total power consumption but does not establish measurement period or relationship to the 200 MW campus plan.

48 MW
IT load
EEMS02 permitted development comprising four data halls
Planned · cumulative
2023-01-12Reported claim ↗

Excluded from capacity totals. As-of is permit decision dispatch date. Permitted design capacity does not establish installed or operational capacity; overlaps the wider campus plan.

≈20 MW
Facility power
Original Eemshaven facility acquired in 2019
Unknown · cumulative
2019-04-30Reported claim ↗

Excluded from capacity totals. As-of uses release dateline; webpage header is April 29. Approximately 20 gross MW built out, but facility was vacant and due for recommissioning. Separate Groningen capacity excluded.

36 MW
Grid connection
Legacy Eemshaven facility described by Baxtel
Operational · unclear
2026-10-09Reported claim ↗

Excluded from capacity totals. Undated directory retrieved on this date reports utility power (2N); current configuration and overlap with Dutch operator figure unresolved.

24 MW
IT load
Legacy facility critical power, dependent on configuration
Operational · unclear
2026-10-09Reported claim ↗

Excluded from capacity totals. Retrieval date, not commissioning date. Critical power classified as IT provision; conditional on configuration and not independently confirmed.

20 MW
Unspecified power
Directory fully built-out power for QTS Eemshaven
Unknown · unclear
2026-10-09Conflicting claim ↗

Excluded from capacity totals. Retrieval-date claim lacks basis and building scope; potentially stale against 36 MW facility descriptions. Retained for reconciliation rather than selected as current capacity.

Development timeline

  1. 2019-04-23 · actual_acquisition

    QTS acquired original Eemshaven facility

    Closed acquisition of Eemshaven and Groningen assets from TCN SIG Telehousing B.V.; no combined capacity allocated to Eemshaven.

    Supporting source ↗
  2. 2019 · planned_recommissioning

    Sellable Eemshaven capacity targeted for late 2019

    Historical acquisition announcement anticipated recommissioning; this target alone does not establish completion.

    Supporting source ↗
  3. 2022-07-06 · actual_permit_notice

    EEMS02 wildlife exemption published

    Notice locates expansion north of Kwelderweg between Huibertgatweg 2 and Oostereemsweg 4.

    Supporting source ↗
  4. 2023-01-12 · actual_permit_decision

    EEMS02 environmental permit decision dispatched

    Permits new four-hall development with 48 MW IT design capacity.

    Supporting source ↗
  5. 2026-01-30 · actual_permit_decision

    EEMS03 data-center decision

    Provincial permit index records decision date; underlying final PDF could not be retrieved through the tool because of its size.

    Supporting source ↗

Disclosed specifications

Campus development area

Up to 18 hectares

Ultimate development extent, not demonstrated completed footprint.

Source ↗

Building area

200,000 ft² facility

Operator does not identify the building or establish that this is campus-wide area.

Source ↗

Dutch-page area

Over 22,000 m²

Different scope or legacy presentation; not reconciled with English-page building area.

Source ↗

Campus components

DC1 operational; DC2 phased delivery; DC3 under construction

DC2 wording does not establish full completion or which portions are operational.

Source ↗

EEMS02 grid design

20 kV substation; 70 MVA main connection

Permit design; MVA is not converted to MW.

Source ↗

EEMS02 cooling design

Air-cooled cooling, ventilation and heating systems using refrigerant

Permitted expansion design; not generalized to original facility or entire campus.

Source ↗

Legacy cooling

N+1; chillers, cooling towers and water-side economizers

Undated industry description; may concern original facility and differs from newer expansion cooling.

Source ↗

Connectivity

Netherlands–UK subsea cable landfall

Operator disclosure; current carriers and service availability require confirmation.

Source ↗

Renewable energy

Renewable-sourced power available

Availability claim does not establish actual campus-wide renewable consumption.

Source ↗

Municipality

Het Hogeland

Groningen Seaports expansion documentation identifies municipality.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Netherlands-Eemshaven — QTS Data Centers ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies the address, three-building development, mixed delivery statuses, up to 18 hectares, and 200 MW planned gross renewable campus power.

Netherlands-Eemshaven (NL) — QTS Data Centers ↗

Published Date unavailable · Retrieved 2026-10-09

Dutch facility page lists the same address, over 22,000 m², 36 MW total power consumption and Netherlands–UK subsea connectivity; scope is not reconciled with the campus page.

Definitief besluit QTS, Kwelderweg, Eemshaven ↗

Published Date unavailable · Retrieved 2026-10-09

Decision sent 12 January 2023 permits four data halls totaling 48 MW IT power; describes EEMS02 documents, air-cooled systems and a 70 MVA main connection.

QTS Eemshaven Data Center — Baxtel ↗

Published Date unavailable · Retrieved 2026-10-09

Industry directory identifies Groningen province and reports legacy 36 MW utility power and configuration-dependent 24 MW critical power, with cooling/connectivity details and a labeled exterior photo.

QTS Eemshaven — Specs — Data Center Map ↗

Published Date unavailable · Retrieved 2026-10-09

Directory lists 20 MW fully built-out power, 10,500 m² whitespace and 18,580 m² building area; postcode differs from the operator and capacity scope/date are unclear.

Property photo · baxtel.com ↗

Published Date unavailable · Retrieved 2026-10-09

Exterior of the Eemshaven facility, labeled by Baxtel; capture date unknown and campus phase not specified. Original image: https://cdn.baxtel.com/data-center/qts-eemshaven/photos/flickity_display_QTS-Eemshaven-Exterior-of-the-Eemshaven-facility.jpg

Profile field evidence

Name: Netherlands-Eemshaven — QTS Data Centers

Aliases: Netherlands-Eemshaven — QTS Data Centers; QTS Eemshaven Data Center — Baxtel

Kind: Netherlands-Eemshaven — QTS Data Centers

Country: Netherlands-Eemshaven — QTS Data Centers; QTS Expands International Platform with the Strategic Acquisition of Two Data Centers in the Netherlands

Region: Provinciaal blad 2022, 7903 — QTS EEMS02 wildlife exemption; QTS Eemshaven Data Center — Baxtel

City: Netherlands-Eemshaven — QTS Data Centers; Provinciaal blad 2022, 7903 — QTS EEMS02 wildlife exemption

Address: Netherlands-Eemshaven — QTS Data Centers; Netherlands-Eemshaven (NL) — QTS Data Centers

Operator: Netherlands-Eemshaven — QTS Data Centers; Provinciaal blad 2022, 7903 — QTS EEMS02 wildlife exemption

Business Model: Bundel — Vergadering Algemeen Bestuur GSP van 8 juli 2022

Scale: QTS Expands International Platform with the Strategic Acquisition of Two Data Centers in the Netherlands

Statuses: Netherlands-Eemshaven — QTS Data Centers

Summary: Netherlands-Eemshaven — QTS Data Centers

Location: Netherlands-Eemshaven — QTS Data Centers; Provinciaal blad 2022, 7903 — QTS EEMS02 wildlife exemption

Media: Property photo · baxtel.com

Stable identifier: e97d6581-5043-4f4d-ac1d-ffca3521e7a7