Revision 1 · Current
2026-10-09 05:35 UTC
Published profile snapshot
Colt Tokyo Inzai 4 Data Centre · Japan · Colt Data Centre Services
Colt-operated hyperscale facility in Inzai, Chiba, serving the Tokyo market. Phase one was operational at 4.8 MW on 2025-02-26; ultimate design capacity is 20 MW IT. Developed under the Fidelity Investments–Mitsui joint venture and fully pre-let. Remaining buildout completion is unconfirmed.
Capacity statements: 2 · Sources: 7
4.8 MW (exact) · unspecified · Inzai 4 first phase · 2025-02-26
20 MW (exact) · it · Inzai 4 ultimate facility buildout · 2025-02-26