Finland / Site

Nebius Mäntsälä data center

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

Yandex Mäntsälä Data Center

OperationalPlanned

Nebius's AI cloud data-center site in Mäntsälä, Finland. The operator reported completion of expansion up to 75 MW earlier in 2026 without specifying the power basis. A new adjacent 70 MW building is announced, with its substation scheduled for autumn 2027. This site is distinct from Verne's Gneissitie development and Nebius's Lappeenranta project.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
Exterior side view of a Mäntsälä data-center building, published under its former Yandex identity; capture date unknown.

Site / building photo

Exterior side view of a Mäntsälä data-center building, published under its former Yandex identity; capture date unknown.

Published date unknown · Captured date unknown · Checked 2026-10-07

Research-selected property image; reviewer must confirm site identity, suitability and rights before publication.

baxtel.com · Source and attribution ↗
Image rights and date notes

Hosted by Baxtel; photographer and original provenance not established. No reuse license found. Rights require review before import; displayed page date is not a verified capture date. Publication and capture dates were not independently established.

Site profile

Operator
Nebius
Ownership
Unknown / not established
Business model / scale
Owner Operated / Unknown
Region / metro
Uusimaa / Unknown
City / locality
Mäntsälä
Address
Moreenikatu 6, 04600 Mäntsälä, Finland
Location
Address associated with the facility by an industry directory and corroborated by Nebius DC Oy's registered visiting address; no independently sourced property point or accessible Google Maps marker established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
75 MW
Unspecified power
Total site capacity after announced expansion
Planned · cumulative
2024-10-08Reported claim ↗

Excluded from capacity totals. Announcement date; headline target. Does not explicitly define IT or facility power.

75 MW
Unspecified power
Existing Mäntsälä site after completed expansion
Operational · cumulative
2026-03-31Reported claim ↗

Excluded from capacity totals. Announcement date; operator says expansion up to this capacity completed earlier in 2026. Capacity ceiling, not measured consumption; overlaps c1.

70 MW
Unspecified power
New adjacent second data-center building
Planned · incremental
2026-10-02Reported claim ↗

Excluded from capacity totals. Contract announcement date; building described as alongside existing 75 MW site. Not operating capacity.

70 MW
Grid connection
Substation serving new adjacent building
Planned · incremental
2026-10-02Reported claim ↗

Excluded from capacity totals. Contract announcement date; completion expected autumn 2027. Supports the same expansion as c3 and must not be added to it.

≈75 MW
IT load
Current campus IT-power estimate
Operational · cumulative
2026-10-05Estimate claim ↗

Excluded from capacity totals. Displayed directory update date. Third-party estimate labels power as IT; primary operator announcement does not establish that basis.

≈145 MW
IT load
Projected campus IT power in Q4 2027
Planned · cumulative
2026-10-05Estimate claim ↗

Excluded from capacity totals. Displayed directory update date, not commissioning date. Third-party projection includes adjacent expansion and overlaps existing-capacity claims; no independently confirmed operator campus IT total.

Development timeline

  1. 2024-10-08 · announcement

    Expansion to 75 MW announced

    Operator announced tripling site capacity with potential deployment of up to 60,000 GPUs.

    Supporting source ↗
  2. 2025-04 · actual

    Technical expansion project started

    Contractor reports extension of existing building and construction of two new buildings.

    Supporting source ↗
  3. 2025-12-17 · announcement

    GB300 deployment operational

    Operator announced live production GB300 NVL72 deployment at expanded Finnish data center.

    Supporting source ↗
  4. 2026 · actual

    Expansion up to 75 MW completed

    March 31 operator announcement says completion occurred earlier in 2026; precise date unavailable.

    Supporting source ↗
  5. 2026-10-02 · announcement

    Adjacent expansion substation contracted

    Caverion announced substation contract serving new 70 MW building alongside existing site.

    Supporting source ↗
  6. 2027 autumn · planned

    New substation completion

    Contractor schedule; does not establish commissioning of the entire new building.

    Supporting source ↗

Disclosed specifications

Cooling

Free cooling; existing air cooling supplemented by liquid cooling

Contractor describes expansion systems; no rack-level density established.

Source ↗

Heat recovery

Approximately 20,000 MWh annually; equivalent to heating 2,500 Finnish homes

Contractor's reported figure at publication, not independently measured during this research.

Source ↗

District heating partner

Nivos

Municipality describes recovery of server heat into municipal district heating.

Source ↗

PUE

As low as 1.1 under high IT loads

Operator claim from 2024 announcement; conditional minimum, not current annual average.

Source ↗

GPU deployment potential

Up to 60,000 GPUs

Expansion potential announced in 2024; not a confirmed installed inventory.

Source ↗

Expansion building scope

Extension of existing building and two new buildings

Describes expansion to 75 MW; distinct from subsequently announced adjacent 70 MW building.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Nebius DC Oy - Rekisteritiedot ↗

Published Date unavailable · Retrieved 2026-10-07

Lists Nebius DC Oy, business ID 2541661-9, with visiting and postal address Moreenikatu 6, 04600 Mäntsälä.

Uudenmaan alue ja kunnat ↗

Published Date unavailable · Retrieved 2026-10-07

Regional council lists Mäntsälä among Uusimaa's 26 municipalities; page displays update date 2026-10-02.

Nebius Mantsala | AI data centers | Epoch AI ↗

Published Date unavailable · Retrieved 2026-10-07

Displays update October 5, 2026; estimates 75 MW IT power currently and 145 MW IT power in Q4 2027. Microsoft use is explicitly speculative; heat figure uses kWh rather than contractor's MWh.

Property photo · baxtel.com ↗

Published Date unavailable · Retrieved 2026-10-07

Exterior side view of a Mäntsälä data-center building, published under its former Yandex identity; capture date unknown. Original image: https://cdn.baxtel.com/data-center/yandex-mantsala-finland/photos/gallery_display_Yandex-Mantsala-Finland-Side-of-one-of-the-Yandex-data-center-buildings.jpeg

Profile field evidence

Name: Nebius to construct 310 MW AI factory in Finland; Mäntsälässä hyrrää pian yksi maailman tehokkaimmista datakeskuksista

Aliases: Nebius Mäntsälä DC1 Data Center in Helsinki | Moreenikatu 6

Kind: Caverion strengthens its position as key partner in major infrastructure investments in Europe; Caverion Finland strengthens its position in the data centre market and will deliver a €15 million substation for AI cloud company Nebius

Country: Nebius to construct 310 MW AI factory in Finland

Region: Uudenmaan alue ja kunnat

City: Nebius to construct 310 MW AI factory in Finland; Mäntsälässä hyrrää pian yksi maailman tehokkaimmista datakeskuksista

Address: Nebius DC Oy - Rekisteritiedot; Nebius Mäntsälä DC1 Data Center in Helsinki | Moreenikatu 6

Operator: Nebius to construct 310 MW AI factory in Finland; Caverion strengthens its position as key partner in major infrastructure investments in Europe

Business Model: Mäntsälässä hyrrää pian yksi maailman tehokkaimmista datakeskuksista; Nebius delivers Europe’s first live NVIDIA GB300 NVL72 deployment

Statuses: Nebius to construct 310 MW AI factory in Finland; Caverion Finland strengthens its position in the data centre market and will deliver a €15 million substation for AI cloud company Nebius

Summary: Nebius to construct 310 MW AI factory in Finland; Caverion Finland strengthens its position in the data centre market and will deliver a €15 million substation for AI cloud company Nebius; Datakeskustoimija Verne alkaa rakentaa uutta datakeskuskampusta Mäntsälään

Location: Nebius DC Oy - Rekisteritiedot; Nebius Mäntsälä DC1 Data Center in Helsinki | Moreenikatu 6

Media: Property photo · baxtel.com

Stable identifier: f396e0b1-c605-4d19-b26c-4c9e1457d279