← BDx CGK4 Jatiluhur AI campusPublished history
Restoring content creates a new revision. Previous revisions remain in the audit trail.
Revision 3 · Current
2026-09-11 12:15 UTC
Published profile snapshot
BDx CGK4 Jatiluhur AI campus · Indonesia · BDx Data Centers
CSV-authorized extension outside Jabodetabek. Ultimate ceiling; 788 MVA grid contract is separate and not converted to MW.
Capacity statements: 2 · Sources: 5
650 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11
640 MW (exact) · it · Secured phased CGK4 ultimate IT development; not all operational · 2026-09-11
Revision 2
2026-09-11 11:26 UTC
Published profile snapshot
BDx CGK4 Jatiluhur AI campus · Indonesia · BDx Data Centers
CSV-authorized extension outside Jabodetabek. Ultimate ceiling; 788 MVA grid contract is separate and not converted to MW.
Capacity statements: 2 · Sources: 3
650 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11
640 MW (exact) · it · Secured phased CGK4 ultimate IT development; not all operational · 2026-09-11
Revision 1
2026-09-11 10:44 UTC
Published profile snapshot
BDx CGK4 Jatiluhur AI campus · Indonesia · BDx Data Centers
CSV-authorized extension outside Jabodetabek. Ultimate ceiling; 788 MVA grid contract is separate and not converted to MW.
Capacity statements: 1 · Sources: 1
650 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11