AM5 · Telecity AMS5 · Telecity AMS 5

Operational

Operational Equinix colocation facility in Amsterdam, formerly Telecity AMS5. Its first phase opened in early 2012. Telecity reported a 9 MW full-build customer-capacity design; current commissioned IT load and facility/grid capacity remain unresolved. Secondary power figures have differing definitions and cannot be combined.

Last researched 2026-10-10Last verified Not independently verifiedPublished revision 2
AM5 property view, identified by Baxtel as formerly Telecity AMS 5; capture date unknown.

Site / building photo

AM5 property view, identified by Baxtel as formerly Telecity AMS 5; capture date unknown.

Published date unknown · Captured date unknown · Checked 2026-10-09

Research-selected property image; reviewer must confirm site identity, suitability and rights before publication.

baxtel.com · Source and attribution ↗
Image rights and date notes

Baxtel labels the source as Baxtel. Photographer, capture date and reuse licence are undisclosed; permission must be resolved before import. Publication and capture dates were not independently established.

Site profile

Operator
Equinix
Ownership
Unknown / not established
Business model / scale
Colocation / Unknown
Region / metro
Noord-Holland / Amsterdam
City / locality
Amsterdam
Address
Schepenbergweg 42, 1105 AT Amsterdam, Netherlands
Location
Approximate AM5 property point from PeeringDB's facility geocode, closely corroborated by an address geocode for the operator-confirmed Schepenbergweg 42. Municipal address evidence confirms the property locality. Geocoder independence and building boundaries are unresolved; no surveyed or Google Maps place-marker precision is claimed.
Precision: approximate · 52.293351, 4.945054
View location on map →
Parent
Not assigned

Location detail

Approximate AM5 property point from PeeringDB's facility geocode, closely corroborated by an address geocode for the operator-confirmed Schepenbergweg 42. Municipal address evidence confirms the property locality. Geocoder independence and building boundaries are unresolved; no surveyed or Google Maps place-marker precision is claimed.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.

Schepenbergweg 42, 1105 AT Amsterdam, Netherlands

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
13.5 MW
Unspecified power
AM5 facility; reported access to power
Operational · unclear
2026-10-09Conflicting claim ↗

Excluded from capacity totals. As_of is the retrieval date, not a disclosed capacity effective date. Undefined power basis; differs from the municipal 2020 band. Other entries on this page contain apparent unit/data errors, reducing confidence. Requires reviewer reconciliation.

9 MW
IT load
Southeast AMS5 ultimate full-build customer capacity
Planned · cumulative
2012-06-19Reported claim ↗

Excluded from capacity totals. As_of is the announcement date. Source calls this customer capacity, interpreted as IT/customer power. First phase had opened, but 9 MW was the future full-build figure; commissioned delivery and phase allocations were not stated. Not additive to secondary facility/access figures.

13 MW
Unspecified power
AM5 facility headline power capacity
Operational · unclear
NoneConflicting claim ↗

Excluded from capacity totals. Undated secondary listing; detailed power field is blank. Basis and effective date unavailable. Differs from InterIX's 13.5 MW; neither reconciles current delivered IT load with the historical 9 MW design.

Development timeline

  1. 2017-05 · actual acquisition

    AM5 property acquisition

    Equinix reported acquisition of AM5 land and building for €26.7 million, settling its prior financing arrangement; the disclosure also identifies a ground-lease interest.

    Supporting source ↗
  2. 2012-02-27 · announcement of construction

    AMS5 construction and AMS-IX agreement

    Telecity described AMS5 under construction and announced an AMS-IX point of presence planned from facility opening.

    Supporting source ↗
  3. 2012 · actual opening

    First phase opened in early 2012

    June 19, 2012 Telecity announcement reports that the first phase opened earlier that year. Exact opening date and initial power allocation are undisclosed.

    Supporting source ↗
  4. 2017-05 · actual acquisition

    AM5 property acquisition

    Equinix reported a €26.7 million land/building transaction terminating the prior financing arrangement, with a ground-lease interest also recognized.

    Supporting source ↗

Disclosed specifications

Colocation space

6,000 m²

Operator-disclosed colocation area, not total building or parcel area.

Source ↗

Building

Four-storey reinforced concrete

Operator specification.

Source ↗

Power redundancy

N+1 UPS

Redundancy does not establish MW capacity.

Source ↗

Cooling redundancy

N+2

Operator specification.

Source ↗

Minimum cabinet density

4 kVA

Apparent-power cabinet specification, not campus capacity.

Source ↗

Generator autonomy

At least 30 hours at full load

Operator specification; generator redundancy unavailable on the current page.

Source ↗

Sustainability features

Heat recovery, efficient UPS, LED lighting and decoupled dehumidification

Operator-listed features; implementation extent and measured savings unspecified.

Source ↗

Historical municipal power band

1–10 MW

2020 report; undefined site-specific basis. Range cannot be represented faithfully as a single capacity claim and does not establish greater-than-5-MW eligibility.

Source ↗

Parcel area

10,890 m²

Secondary property-register presentation, parcel WPK02 M 992; requires original cadastral confirmation.

Source ↗

Cooling technology

Cooling towers, ATES and water-cooled chillers with free cooling

Industry directory report; not independently confirmed against a current operator technical sheet.

Source ↗

Google Cloud connectivity

Dedicated Interconnect: 10 and 100 Gbps

Google lists AM5 in Amsterdam under ams-zone1-1236 and ams-zone2-1236; connectivity presence does not establish tenant occupancy.

Source ↗

Colocation space

6,000 m²

Current operator disclosure; distinct from total building and parcel area.

Source ↗

Redundancy and autonomy

N+1 UPS; N+2 cooling; generator autonomy at least 30 hours at full load

Operator disclosures; generator redundancy unavailable. These do not establish MW capacity.

Source ↗

Minimum cabinet density

4 kVA

Operator apparent-power specification, not a current maximum rack density.

Source ↗

2025 renewable-energy instruments

Wind guarantees of origin from Sweden/Finland vPPAs; EU wind/solar and supplier-bundled mixed guarantees of origin

Operator's year-labelled disclosure; does not establish direct physical renewable supply or measured environmental performance.

Source ↗

Historical cooling design

Aquifer Thermal Energy Storage (ATES)

Telecity's 2012 announcement describes seasonal groundwater storage for cooling; current extent and performance require confirmation.

Source ↗

Ground-energy regulatory evidence

BES Telecitygroup, Schepenbergweg 42; record 84404

Listed in the 2023 municipal ground-energy plan. Supports asset-specific ground-energy infrastructure, not current water consumption.

Source ↗

Historical municipal power band

1–10 MW

2020 policy range; site-specific electrical basis unclear. Retained as a range, not converted into a point claim.

Source ↗

Historical property and capital relationship

€26.7 million transaction in May 2017; €6.7 million allocated to ground lease

Ground-lease allocation amortized through December 2054. Disclosure does not identify today's legal title holder, ground lessor or current lease conditions.

Source ↗

Campus connectivity relationship

Equinix Amsterdam South East; cross-connect relationships with AM1/AM2, AM7 and AM11

PeeringDB describes separate connected IBXs. No parent record or shared physical parcel is inferred.

Source ↗

Historical disclosed customer

Uniserver: 114 racks reported in July 2012

Historical customer allocation; neither total rack count nor current occupancy.

Source ↗

Public service-provider presence

Zenlayer AMS4 service location at Equinix AM5

Provider identifies the matching address; its AMS4 code is not Equinix AM4. No contracted MW disclosed.

Source ↗

Public customer infrastructure disclosure

ACC ICT Mission Critical Cloud uses Equinix AM5 Amsterdam

Customer technical guide identifies AM5 among three facilities. Its PUE range covers the portfolio and is not assigned to AM5.

Source ↗

Attributed exterior photography

Acid Clouds: Equinix AM5 exterior, photographs credited to Niels Schrader and Roel Backaert

Original publication dated September 11, 2019. Image pixels could not be inspected; capture date and reproduction permission unresolved. Source: https://onlineopen.org/acid-clouds

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Equinix AM5 facility page ↗

Published Date unavailable · Retrieved 2026-10-09

Operator identifies AM5 at Schepenbergweg 42, Amsterdam, Netherlands; lists colocation space, infrastructure and interconnection services.

InterIX — Locations ↗

Published Date unavailable · Retrieved 2026-10-09

AM5 entry gives the matching address and says it has access to 13.5 MW of power; basis and effective date are absent.

Google Cloud — All colocation facilities ↗

Published Date unavailable · Retrieved 2026-10-09

Amsterdam entries identify Equinix Amsterdam Schepenbergweg AM5, formerly Telecity AMS5, with 10 and 100 Gbps Dedicated Interconnect links.

Schepenbergweg 42 — KadastraleKaart ↗

Published Date unavailable · Retrieved 2026-10-09

Public property-data intermediary places the address in Amsterdam, Noord-Holland; reports parcel WPK02 M 992, 10,890 m², and building ID 0363100012239632.

Equinix 2017 Annual Report ↗

Published Date unavailable · Retrieved 2026-10-09

Page 149 records the May 2017 AM5 land/building acquisition for €26.7 million and allocation to a ground lease amortized through December 2054; also records the January 2016 TelecityGroup acquisition.

Equinix Amsterdam AM5 — Baxtel ↗

Published Date unavailable · Retrieved 2026-10-09

Identifies AM5 as fully operational at Schepenbergweg 42 and supplies property-photo references.

Property photo · baxtel.com ↗

Published Date unavailable · Retrieved 2026-10-09

AM5 property view, identified by Baxtel as formerly Telecity AMS 5; capture date unknown. Original image: https://cdn.baxtel.com/data-center/equinix-amsterdam-am5/photos/flickity_display_Equinix-Amsterdam-AM5-AM5-was-formerly-Telecity-AMS-5.jpg

Equinix AM5 facility page ↗

Published Date unavailable · Retrieved 2026-10-10

Current operator page identifies AM5 and its Netherlands street address; offers cabinets/cages and interconnection, and reports 6,000 m² colocation space, N+1 UPS and N+2 cooling.

Equinix AM5 — Amsterdam, Schepenbergweg — PeeringDB ↗

Published Date unavailable · Retrieved 2026-10-10

Matching facility/address and Equinix organization; displayed geocode 52.293351, 4.945054. Describes South East campus connectivity across separate IBXs. Record displays last update September 26, 2025.

Equinix Amsterdam AM5 Data Center — Baxtel ↗

Published Date unavailable · Retrieved 2026-10-10

Matching address, operational designation, North Holland province, Amsterdam metro and former Telecity AMS 5 name. Lists 2012 construction year and exterior/satellite references.

Gemeenteblad 2023, 76083 — Amsterdam bodemenergieplan ↗

Published 2023-02-21 · Retrieved 2026-10-10

Official ground-energy plan lists BES Telecitygroup at Schepenbergweg 42, Amsterdam-Zuidoost, record 84404. Corroborates site-specific ground-energy infrastructure; does not establish electrical capacity or current water consumption.

Equinix 2017 Annual Report ↗

Published Date unavailable · Retrieved 2026-10-10

Printed page 149, PDF page index 148: May 2017 AM5 land/building transaction for €26.7 million; financing arrangement terminated, and €6.7 million allocated to a ground lease amortized through December 2054.

Locations — InterIX ↗

Published Date unavailable · Retrieved 2026-10-10

Rechecked AM5 entry still reports access to 13.5 MW. Other entries have conspicuous unit/data errors; no current primary capacity definition provided.

Equinix: Amsterdam AM5 — OCOLO ↗

Published Date unavailable · Retrieved 2026-10-10

Matching address and South East campus description; headline power capacity 13.00 MW, while detailed power-capacity field is blank. Electrical basis and effective date absent.

Amsterdam Data Center — AMS4 — Zenlayer ↗

Published Date unavailable · Retrieved 2026-10-10

Zenlayer identifies its AMS4 service location at Schepenbergweg 42, powered by Equinix, with bare metal, transit, CDN and colocation offerings. Its AMS4 code must not be confused with Equinix AM4.

Mission Critical Cloud technische gids — ACC ICT ↗

Published Date unavailable · Retrieved 2026-10-10

Customer's technical guide names Equinix AM5 Amsterdam among its three geographically separated data centers. Portfolio-wide PUE range cannot be assigned specifically to AM5.

Acid Clouds — Open! ↗

Published 2019-09-11 · Retrieved 2026-10-10

Original publication captions an exterior photograph as Equinix AM5 Datacenter, Amsterdam and attributes photographs to Niels Schrader and Roel Backaert. Linked image fetch timed out; capture date and reuse permission unresolved.

Profile field evidence

Name: Equinix AM5 facility page; Equinix Amsterdam AM5 Data Center — Baxtel

Aliases: Equinix AM5 facility page; Google Cloud — All colocation facilities; Equinix Amsterdam AM5 — Baxtel; Equinix Amsterdam AM5 Data Center — Baxtel; TelecityGroup introduces innovative underground energy storage system in new Amsterdam facility

Kind: Equinix AM5 facility page

Country: Equinix AM5 facility page

Region: Schepenbergweg 42, 1105 AT Amsterdam, Netherlands — GEOCORDS; Equinix Amsterdam AM5 Data Center — Baxtel

City: Equinix AM5 facility page; Adres — Schepenbergweg 42 — Amsterdam Data en Informatie

Metro: Equinix Amsterdam AM5 Data Center — Baxtel

Address: Equinix AM5 facility page; Adres — Schepenbergweg 42 — Amsterdam Data en Informatie

Operator: Equinix AM5 facility page; Equinix AM5 — Amsterdam, Schepenbergweg — PeeringDB

Business Model: Equinix AM5 facility page

Statuses: Equinix AM5 facility page; Equinix Amsterdam AM5 Data Center — Baxtel

Summary: Equinix AM5 facility page; Equinix Amsterdam AM5 Data Center — Baxtel; TelecityGroup introduces innovative underground energy storage system in new Amsterdam facility; Locations — InterIX; Equinix: Amsterdam AM5 — OCOLO

Location: Equinix AM5 facility page; Equinix AM5 — Amsterdam, Schepenbergweg — PeeringDB; Schepenbergweg 42, 1105 AT Amsterdam, Netherlands — GEOCORDS; Adres — Schepenbergweg 42 — Amsterdam Data en Informatie

Media: Property photo · baxtel.com

Stable identifier: f6ff4de3-a56e-47ef-850b-4ec2bc29ab02