The HIVE

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

The Hive Data Center · HIVE Hybrid Data Center · BodaData PH

Operational

Beeinfotech PH operates The HIVE colocation facility in Campus One, Bridgetowne. Newly located operator announcements report Phase 1 transformer energization on December 23, 2024, inauguration on March 18, 2025, and LEED Gold achievement in July 2025. These do not resolve the relationship to earlier operations, conflicting locality descriptions, or power-capacity definitions.

Last researched 2026-09-11Last verified Not independently verifiedPublished revision 4
The HIVE property image accompanying SunStar's February 11, 2022 general-availability report. Identified by the publisher as a contributed photo; capture date and visual suitability were not established because the image fetch failed.

Site / building photo

The HIVE property image accompanying SunStar's February 11, 2022 general-availability report. Identified by the publisher as a contributed photo; capture date and visual suitability were not established because the image fetch failed.

Published date unknown · Captured date unknown · Checked 2026-09-11

Research-selected property image; reviewer must confirm site identity, suitability and rights before publication.

www.sunstar.com.ph · Source and attribution ↗
Image rights and date notes

Publisher credits a contributed photo; photographer and reuse license are unspecified. Public availability does not establish permission to republish. Publication and capture dates were not independently established.

Site profile

Operator
Beeinfotech PH
Ownership
Robinsons Land Corporation (building landlord; data-center business ownership unresolved)
Business model / scale
Colocation / Unknown
Region / metro
National Capital Region / Metro Manila
City / locality
Pasig
Address
88 Bridgetowne East, Barangay Rosario, Pasig City, Philippines 1609
Location
Property identified through operator street address and Campus One tenancy evidence. Supplied point 14.595113, 121.086958 remains user-reported and uncorroborated; no sourced building point established.
Precision: block · 14.595113, 121.086958
View location on map →
Parent
Not assigned

Location detail

Property identified through operator street address and Campus One tenancy evidence. Supplied point 14.595113, 121.086958 remains user-reported and uncorroborated; no sourced building point established.. Coordinate precision: block. Street-map detail does not increase the accuracy of the sourced point.

88 Bridgetowne East, Barangay Rosario, Pasig City, Philippines 1609

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
>20 MW
Unspecified power
The HIVE, advertised AI and traditional colocation capacity
Operational · unclear
2026-09-11Conflicting claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated live page. Source says 20 MW+ without distinguishing IT load, facility power or available commissioned capacity; plus preserved as greater-than.

20 MW
Unspecified power
Lower endpoint of reported 20–22 MW dual-power-supply range
Operational · unclear
2025-03-21Reported claim ↗

Excluded from capacity totals. As-of is article publication date. Paired with c3 to retain a range; neither endpoint is a separate additive capacity. Per-feed versus combined rating is unclear.

22 MW
Unspecified power
Upper endpoint of reported 20–22 MW dual-power-supply range
Operational · unclear
2025-03-21Reported claim ↗

Excluded from capacity totals. As-of is article publication date. Same range as c2; not an increment or independently established grid connection.

50 MW
Unspecified power
The HIVE site described by operator as ready to use
Operational · unclear
2026-09-11Conflicting claim ↗

Excluded from capacity totals. As-of is retrieval date; exact post date unavailable. Operational scope reflects the operator’s availability language, not verification of commissioned 50 MW. Relationship to homepage 20 MW+ and 2025 supply figures is unresolved.

50 MW
Unspecified power
The HIVE infrastructure cooling-design claim
Unknown · unclear
2026-09-11Conflicting claim ↗

Excluded from capacity totals. As-of is retrieval date of a post referring to Earth Day 2026. Infrastructure is described as designed for hybrid cooling; delivery stage is not quantified. Overlaps c4 and must not be added.

Development timeline

  1. 2021-07-15 · announcement

    Opening reported

    BusinessWorld reported that Beeinfotech had recently opened its Pasig facility. Exact commissioning date was not given.

    Supporting source ↗
  2. 2022-02-14 · announcement

    General availability reported

    DCD reported general availability of The Hive; this later milestone is retained separately from the 2021 opening report.

    Supporting source ↗
  3. 2025-03-21 · announcement

    Formal inauguration reported

    Newsbytes reported inauguration of the Hive. The report does not explain the relationship to earlier operation or establish a separate phase.

    Supporting source ↗
  4. 2025-06-05 · announcement

    PCI-DSS achievement announced

    Operator announcement dated June 5 was published June 10; current certificate validity and assessment scope were not independently checked.

    Supporting source ↗
  5. 2030 · planned

    Renewable energy and LEED goals

    Reported targets are 100% renewable energy and LEED certification by 2030.

    Supporting source ↗
  6. 2024-12-23 · actual_reported

    Phase 1 transformer energization

    Operator reports successful 34.5 kV, 10 MVA transformer power delivery. This establishes an electrical milestone, not commissioned IT load or completion of all phases.

    Supporting source ↗
  7. 2025-03-18 · actual_reported

    Hybrid data-center inauguration

    Operator reports the launch ceremony on this date. Relationship to the 2021 opening and 2022 general availability remains unresolved.

    Supporting source ↗
  8. 2025-07 · actual_reported

    LEED v4 Gold achievement

    Operator reports July 2025 achievement under LEED v4 BD+C: Data Centers for The HIVE and Energy Building. This updates the earlier reported 2030 LEED ambition; registry confirmation remains outstanding.

    Supporting source ↗

Disclosed specifications

Rack capacity

3,600+ total cabinet racks

Current advertised capacity; installed, occupied and available counts are not distinguished.

Source ↗

Historical rack specification

At least 3,000 racks across three floors

Reported at 2022 general availability; later rack claims differ.

Source ↗

Building area

Approximately 19,000 m² leasable space

2022 reporting; floor area, not site land area.

Source ↗

Landlord area disclosure

18,500 m² office building

2021 annual-report lease description; differs from rounded 19,000 m² reporting, without a reconciled measurement basis.

Source ↗

Adjacent power-center land

1,500 m² planned

Reported in 2021 as an adjacent power-center development; completion and parcel extent unconfirmed.

Source ↗

Building developer and landlord

Robinsons Land Corporation

Whole-building lease to Beeinfotech; broader Bridgetowne estate is mixed-use and is not modeled as a data-center parent campus.

Source ↗

BodaData relationship

Reported affiliate; probable matching Pasig facility listing

Beeinfotech names Boda as an affiliate. Legal ownership and equivalence to BodaData Philippines No. 1 AIDC Base remain unresolved.

Source ↗

Resilience and conventional cooling

Tier 3 design; minimum N+1; hot-aisle containment

Operator specifications, not independently confirmed certification or subsystem audit.

Source ↗

Hybrid cooling

Hybrid, closed-loop and direct-to-chip design; AI-supported DCIM

Operator’s 2026-themed statement; installed coverage and measured performance unknown.

Source ↗

Security

Aspiration fire detection and seven security layers

Operator marketing specifications.

Source ↗

Renewable energy

30% reported in March 2025

Procurement mechanism and measurement period unspecified; 100% is a 2030 target.

Source ↗

PCI-DSS

Achievement announced June 2025

Operator reports certification; assessment scope, version and current validity not established.

Source ↗

Connectivity services

Carrier-neutral interconnection; cloud connect/DCI; VPN/SD-WAN; 1/10/100GE access

Advertised services; no verified site-specific carrier or exchange list.

Source ↗

Public business contact

info@beeinfotech.ph; +632 8888 0087

Published general business contact; no contact made.

Source ↗

Phase 1 electrical infrastructure

34.5 kV; 10 MVA transformer energization

Reported energized December 23, 2024. Transformer count and per-unit versus combined rating are unclear. MVA is apparent power and has not been converted to MW.

Source ↗

Building area disclosure

25,000 m²

Operator claim dated March 14, 2025. Scope differs or conflicts with historical 18,500–19,000 m² descriptions; no expansion or measurement reconciliation established.

Source ↗

Reported PUE

Annual average below 1.35

Operator claim in the March 14, 2025 announcement. No measurement period, load conditions or audit supplied; not treated as independently measured performance.

Source ↗

MEP main contractor

ZTE Corporation

Named by the operator for the hybrid data-center project; this does not establish ownership.

Source ↗

LEED certification

LEED v4 BD+C: Data Centers — Gold, July 2025

Operator-reported achievement covering The HIVE Hybrid Data Center and Energy Building; public certifier-directory confirmation was not obtained.

Source ↗

BERDE

Certification being pursued

Status reported in August 2025; no completion evidence located.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Contact Us | Beeinfotech PH ↗

Published Date unavailable · Retrieved 2026-09-11

Public business address: 88 Bridgetowne East, Barangay Rosario, Pasig City, Philippines 1609; telephone and general email.

Southeast Asia | BodaData ↗

Published Date unavailable · Retrieved 2026-09-11

Opened page lists BodaData Philippines No. 1 AIDC Base in Pasig, Philippines, Tier 3+, with an ambiguous IT Capacity entry of 3600++. Search index also surfaced the name BodaData PH Data Center.

Foundational Services | Beeinfotech PH ↗

Published Date unavailable · Retrieved 2026-09-11

Advertises customizable colocation, Tier 3 design, minimum N+1 configuration, hot-aisle containment, aspiration fire detection and seven security layers.

Connectivity Services | Beeinfotech PH ↗

Published Date unavailable · Retrieved 2026-09-11

Lists dedicated/shared bandwidth, carrier dedicated lines, cloud connect/DCI, VPN/SD-WAN and on-demand 1/10/100GE access.

Beeinfotech PH now ready to accept global hyperscalers ↗

Published 2022-02-11 · Retrieved 2026-09-11

Press-release article reports general availability and identifies its contributed property image as The Hive in Bridgetowne, an estate spanning Pasig and Quezon City. Image fetch failed; visual suitability remains unchecked.

Property photo · www.sunstar.com.ph ↗

Published Date unavailable · Retrieved 2026-09-11

The HIVE property image accompanying SunStar's February 11, 2022 general-availability report. Identified by the publisher as a contributed photo; capture date and visual suitability were not established because the image fetch failed. Original image: https://cf-images.assettype.com/sunstar%2Fimport%2Fuploads%2Fimages%2F2022%2F02%2F11%2F338150.jpg?auto=format%2Ccompress&fit=max&w=480

operator ↗

Published Date unavailable · Retrieved 2026-09-11

..

Operator logo · www.beeinfotech.ph ↗

Published Date unavailable · Retrieved 2026-09-11

Beeinfotech operator brand mark. Image reference: https://static.wixstatic.com/media/6a6b17_21a58146de564dce8d78a20c1e249e75~mv2.png/v1/fill/w_169,h_46,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/final_beeinfotech_logo.png Visually inspected against the cited source and profile identity.

Profile field evidence

Name: Home | Bee Information Technology PH, Inc. Data Center; Beeinfotech opens its first data center in the Philippines

Aliases: operator

Kind: Beeinfotech opens its first data center in the Philippines

Country: Contact Us | Beeinfotech PH; Beeinfotech opens its first data center in the Philippines

Region: Beeinfotech PH Achieves PCI-DSS Certification, Strengthening Data Security for Clients

City: Contact Us | Beeinfotech PH; Beeinfotech PH Earns LEED v4 Gold for The HIVE Hybrid Data Center

Metro: Beeinfotech PH Achieves PCI-DSS Certification, Strengthening Data Security for Clients

Address: Contact Us | Beeinfotech PH

Operator: Home | Bee Information Technology PH, Inc. Data Center; Beeinfotech PH Earns LEED v4 Gold for The HIVE Hybrid Data Center

Owner: Robinsons Land Corporation: Campus One tenancy announcement; Robinsons Land Corporation 2026 Definitive Information Statement

Business Model: Home | Bee Information Technology PH, Inc. Data Center; Beeinfotech PH Earns LEED v4 Gold for The HIVE Hybrid Data Center

Statuses: Beeinfotech opens its first data center in the Philippines; Home | Bee Information Technology PH, Inc. Data Center; AIDC Driving the Digital Leap of the Philippines – Grand Opening of Beeinfotech PH HIVE Hybrid Data Center

Summary: Contact Us | Beeinfotech PH; Beeinfotech opens its first data center in the Philippines; Robinsons Land Corporation 2026 Definitive Information Statement; Successful Energization of 34.5kV 10MVA Power at Beeinfotech PH's HIVE Data Center (Phase 1); AIDC Driving the Digital Leap of the Philippines – Grand Opening of Beeinfotech PH HIVE Hybrid Data Center; Beeinfotech PH Earns LEED v4 Gold for The HIVE Hybrid Data Center

Location: operator

Media: Property photo · www.sunstar.com.ph

Unknowns: operator

Operator Logo: Operator logo · www.beeinfotech.ph

Stable identifier: 152a2e1a-c012-4d1b-8c26-97d684f69d89