Finland / Site

XTX Markets Kajaani data center complex

Under ConstructionPlanned

XTX Markets is developing a campus for its own machine-learning computing in Kajaani. The first building was announced with 22.5 MW IT capacity and planned 2026 operation; operation has not been established. September 2026 evidence confirms third-building construction progress. Additional buildings remain part of the announced five-building plan.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
XTX Markets
Ownership
XTX Markets
Business model / scale
Owner Operated / Unknown
Region / metro
Kainuu / Unknown
City / locality
Kajaani
Address
Unknown
Location
Sources identify Tihisenniemi and the Sokajärventie vicinity in Kajaani; no corroborated facility point or street number established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
22.5 MW
IT load
First campus building, three data halls combined
Under Construction · cumulative
2025-01-22Reported claim ↗

Excluded from capacity totals. As_of is operator announcement date. Design IT capacity, not measured operation or ultimate campus capacity; independently repeated by the construction consultant.

250 MW
Unspecified power
Intended Kajaani campus expansion
Planned · cumulative
2025-04-16Reported claim ↗

Excluded from capacity totals. As_of is Yle publication date. Report attributes expansion plans to the country head; IT versus facility/grid basis is not established. Expansion depends on transmission development.

250 MW
Unspecified power
Five-building Kajaani development
Planned · cumulative
2025-06-10Reported claim ↗

Excluded from capacity totals. As_of is regional report date. Report calls the project under construction but does not show all 250 MW built or operational; ultimate figure retained as planned and overlaps c2.

Development timeline

  1. 2025-01-22 · announcement

    Campus investment and expansion announced

    Operator announced investment above €1 billion, first-building construction and intention to pursue four additional buildings.

    Supporting source ↗
  2. 2026 · planned

    First-building operation target

    Original target for first-building operation; achievement remains unconfirmed.

    Supporting source ↗
  3. 2026-03-18 · actual

    Second-building fit-out underway

    YIT reported fit-out and building-services work underway after structural completion.

    Supporting source ↗
  4. 2027 · planned

    Second-building completion target

    Expected completion reported by YIT; not an actual commissioning date.

    Supporting source ↗
  5. 2026-06-17 · announcement

    Third-building shell-and-core contract

    YIT announced agreement and planned summer 2026 construction start.

    Supporting source ↗
  6. 2026-09-25 · actual

    Third-building shell and core completed

    YIT reported successful shell-and-core completion and signed fit-out, MEP and commissioning agreement.

    Supporting source ↗
  7. late 2026 · planned

    Third-building fit-out phase start

    Latest construction phase scheduled to start in late 2026.

    Supporting source ↗

Disclosed specifications

Land area

478 acres

Operator-reported owned campus site area; legal subsidiary and cadastral extent unresolved.

Source ↗

First-building floor area

15,000 square meters

Building-specific, not campus total.

Source ↗

First-building accommodation

Three data halls; mechanical plant, warehouse and office space for 50 people

Announced design configuration.

Source ↗

Cooling

Use of naturally low ambient air temperature; no water consumption in core operations planned

Operator design claim, without operating measurements or detailed cooling architecture.

Source ↗

Heat reuse

Exploring free waste-heat provision to the local community

Intent only; no commissioned heat-delivery scheme established.

Source ↗

Electrical and fiber infrastructure

110 kV cabling, two approximately 3 km runs, and fiber works

Eltel contractor scope; June 2026 completion was a target in the presentation, not verified achievement. Voltage is not MW capacity.

Source ↗

Proposed grid reinforcement

Approximately 30 km 400 kV Suksisuo–Vuottolahti connection

Government EIA describes pending route alternatives; not an energized connection or a disclosed MW allocation.

Source ↗

Developer and contractors

XTX Markets developer; YIT main contractor; AINS construction-management consultant; Bravida electrical installations

Roles supported by dated project announcements; contractors are not site operators.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Eltel AB Q3 2025 presentation ↗

Published Date unavailable · Retrieved 2026-10-07

Slide 19 labels Kajaani project 250 MW, describes five buildings, but separately states 2.5 MW IT power without a clear scope; also describes 110 kV cabling and fiber work.

Profile field evidence

Name: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; XTX Markets plans to invest over €1bn in large-scale data centre project in Kajaani, Finland

Kind: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; YIT continues the construction of XTX Markets’ data center campus in Kajaani - delivers the fit-out and MEP works for the third data center

Country: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; XTX Markets plans to invest over €1bn in large-scale data centre project in Kajaani, Finland

Region: National and International Cooperation

City: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; XTX Markets, Suksisuo - Vuottolahti 400 kV voimajohtohanke, Kajaani

Operator: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; YIT and XTX Markets agree on interior finishing and building services contract for the second data center building in Kajaani

Owner: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland

Business Model: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland

Statuses: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; YIT continues the construction of XTX Markets’ data center campus in Kajaani - delivers the fit-out and MEP works for the third data center; YIT and XTX Markets agree on interior finishing and building services contract for the second data center building in Kajaani

Summary: XTX Markets plans to invest over €1bn in large-scale data centre project in Finland; YIT continues the construction of XTX Markets’ data center campus in Kajaani - delivers the fit-out and MEP works for the third data center; YIT and XTX Markets agree on interior finishing and building services contract for the second data center building in Kajaani; AINS Group supports XTX Markets in its data center project

Location: XTX Markets, Suksisuo - Vuottolahti 400 kV voimajohtohanke, Kajaani; Kajaaniin tulee datakeskus, jonka taustayhtiön perustaja on Iso-Britannian suurin veronmaksaja

Stable identifier: 16c613b5-103d-407c-9a59-b4fe3560e6ec