XTX Markets Kajaani data center complex · Finland · XTX Markets
XTX Markets is developing a campus for its own machine-learning computing in Kajaani. The first building was announced with 22.5 MW IT capacity and planned 2026 operation; operation has not been established. September 2026 evidence confirms third-building construction progress. Additional buildings remain part of the announced five-building plan.
Capacity statements: 3 · Sources: 14
22.5 MW (exact) · it · First campus building, three data halls combined · 2025-01-22
250 MW (exact) · unspecified · Intended Kajaani campus expansion · 2025-04-16
250 MW (exact) · unspecified · Five-building Kajaani development · 2025-06-10