Finland / Site

atNorth FIN05 Salo

FIN05 · Salo mega site – FIN05

Planned

Planned atNorth campus in Kärkkä, Salo. Municipal records link the development to Regant DC1 Oy; legal ownership of the complete campus remains unresolved. Power claims describe future phases, not operating capacity.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
atNorth
Ownership
Unknown / not established
Business model / scale
Colocation / Unknown
Region / metro
Varsinais-Suomi / Unknown
City / locality
Salo
Address
Unknown
Location
Municipal announcement identifies Kärkkä in Salo; no independently corroborated facility point established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
75 MW
Unspecified power
FIN05 first phase
Planned · incremental
2026-10-05Reported claim ↗

Excluded from capacity totals. Announcement-date claim: first-phase power secured; release does not explicitly classify this as IT or gross facility power. Not operating load.

230 MW
Facility power
Ultimate FIN05 campus gross power capacity
Planned · cumulative
2026-10-07Reported claim ↗

Excluded from capacity totals. Retrieval-date observation of undated facility page. Announcement describes a path to up to this figure; not fully secured or operating capacity.

≈160 MW
IT load
Ultimate FIN05 campus IT capacity
Planned · cumulative
2026-10-07Reported claim ↗

Excluded from capacity totals. Retrieval-date observation of undated facility page; explicitly qualified as up to 160 MW, an upper design limit rather than guaranteed delivery. Schema has no upper-bound qualifier.

60 MW
IT load
FIN05 first-phase IT capacity
Planned · incremental
2026-10-07Reported claim ↗

Excluded from capacity totals. Retrieval-date observation of undated facility page. Overlaps the first-phase power claim and is included within ultimate campus IT capacity; do not add these figures.

Development timeline

  1. 2026-08-10 · actual

    Municipal land sale approved

    Council approved sale of industrial land to Regant DC1 Oy.

    Supporting source ↗
  2. 2026-10-05 · announcement

    FIN05 publicly announced

    atNorth announced plans for its Salo development.

    Supporting source ↗
  3. 2028-Q3 · planned

    First-phase power availability

    Operator facility page targets power availability; commissioning is not independently established.

    Supporting source ↗

Disclosed specifications

Campus land area

28.6 hectares

Whole proposed development, distinct from the municipal land-sale component.

Source ↗

Development partner

Regant Oy / Regant DC1 Oy

Municipal record identifies Regant DC1 as Regant-owned project company; ownership of all FIN05 assets is unresolved.

Source ↗

Planned grid connection

Through a Fingrid substation

Substation identity and connection commissioning were not established.

Source ↗

Energy and heat reuse

Local power purchase agreements and heat reuse under exploration

Plans and discussions, not completed supply or heat-delivery arrangements.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

High Density Data Center in Salo - FIN05 ↗

Published Date unavailable · Retrieved 2026-10-07

Operator facility page initially opened; indexed text distinguishes 230 MW gross and up to 160 MW IT campus capacity, 60 MW first-phase IT capacity and Q3 2028 power availability. Subsequent fetches timed out.

atNorth rakentaa datakeskuksen Saloon ↗

Published 2026-10-05 · Retrieved 2026-10-07

City identifies FIN05 in Kärkkä and reports a completed sale of approximately seven hectares to project participant Regant DC1 Oy during the preceding week.

Profile field evidence

Name: atNorth to develop new data center in Salo, Finland; High Density Data Center in Salo - FIN05

Aliases: atNorth to develop new data center in Salo, Finland; High Density Data Center in Salo - FIN05

Kind: High Density Data Center in Salo - FIN05

Country: atNorth to develop new data center in Salo, Finland

Region: Miksi Salo ja Asuntomessut?

City: atNorth to develop new data center in Salo, Finland; atNorth rakentaa datakeskuksen Saloon

Operator: atNorth to develop new data center in Salo, Finland

Business Model: atNorth to develop new data center in Salo, Finland

Statuses: atNorth to develop new data center in Salo, Finland; Jättedatacenter för två miljarder euro byggs i Salo

Summary: atNorth to develop new data center in Salo, Finland; atNorth rakentaa datakeskuksen Saloon; Kaupunginhallitus Pöytäkirja 10.08.2026/Pykälä 260

Location: atNorth rakentaa datakeskuksen Saloon

Stable identifier: 2030f277-6841-467c-9759-158f040e108f