Australia / Facility

Lanceley Place Data Centre, Artarmon · Goodman SYD 01

Under ConstructionPlanned

Goodman is developing and will operate this Artarmon facility. Construction is underway, with phased IT deployment and first service planned for Q2 2028. Utility power and IT capacity describe different scopes.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Goodman
Ownership
Goodman Group
Business model / scale
Colocation / Hyperscale
Region / metro
New South Wales / Sydney
City / locality
Artarmon
Address
2–8 Lanceley Place and 14 Campbell Street, Artarmon NSW 2064, Australia
Location
Property identified by planning address and cadastral lots; no corroborated coordinate established.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
61 MW
IT load
Ultimate facility across five phases
Planned · cumulative
2026-03-02Reported claim ↗

Excluded from capacity totals. Announcement-date design claim; not operational capacity.

12.2 MW
IT load
First phase; same nominal capacity stated for each of five phases
Planned · incremental
2026-03-02Reported claim ↗

Excluded from capacity totals. Announcement-date phase claim already included in the 61 MW total; first phase forecast for Q2 2028.

90 MW
Grid connection
Secured utility power for facility
Under Construction · cumulative
2026-03-02Reported claim ↗

Excluded from capacity totals. Announcement-date secured-power claim, not IT load or demonstrated energised capacity. April planning assessment instead specifies 90 MVA feeder capacity; no conversion assumed.

Development timeline

  1. 2026-03-02 · announcement

    Construction commencement marked

    Goodman publicly marked construction commencement; ceremony date does not establish the first physical-work date.

    Supporting source ↗
  2. 2026-04-14 · actual_approval

    Modification 2 approved

    Capacity, plant, generators and facade changes approved.

    Supporting source ↗
  3. 2026-09 · actual_construction_update

    Construction status update

    Official indexed page describes ongoing concrete works and upcoming facade, jumpform and crane works.

    Supporting source ↗
  4. 2028-Q2 · planned_service

    First phase ready for service

    Forecast availability of first IT phase; not an achieved milestone.

    Supporting source ↗

Disclosed specifications

Developer and planning applicant

Goodman Property Services (Aust) Pty Limited

Applicant identified in government assessment.

Source ↗

Cadastral identification

Lot 11 DP 606737 and Lots 12–15 DP 233037

Property immediately east of Gore Hill Technology Park.

Source ↗

Land area

1.4 hectares

Operator announcement; approximate presentation.

Source ↗

Connectivity

Carrier-neutral; two meet-me rooms and four diverse entry points

Planned facility configuration.

Source ↗

Utility feeder capacity

90 MVA; two 33 kV feeders

Modification increases earlier 80 MVA provision; MVA is not converted to MW.

Source ↗

Sustainability design targets

PUE 1.28; 5.5-star NABERS; ability to achieve net zero emissions by 2050

Assessment describes design intentions, not measured performance or awarded certification.

Source ↗

Backup generation

42 × 2.82 MW / 3.6 MVA generators plus one 908 kW / 1135 kVA generator

Modified design; generator ratings are not facility IT capacity and are not summed.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Goodman SYD01 ↗

Published Date unavailable · Retrieved 2026-10-09

Official project page; search-indexed content includes September 2026 construction status and aerial captions. Direct extraction exposes only limited page content.

Goodman Data centre overview ↗

Published Date unavailable · Retrieved 2026-10-09

Official indexed portfolio lists Goodman SYD01 at 2 Lanceley Place, Artarmon NSW 2064, Australia, with secured power and five data halls.

Lanceley Place Data Centre, Artarmon ↗

Published Date unavailable · Retrieved 2026-10-09

Government project SSD-66777221 is approved; portal displays determination date 11 April 2025 and an earlier 80 MVA scheme.

Goodman: Artarmon Data Center ↗

Published Date unavailable · Retrieved 2026-10-09

Industry directory corroborates project address and construction status; reports former ABC property acquisition in 2022. Its photograph is attributed to Google Maps.

Profile field evidence

Name: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B; Goodman SYD01

Aliases: Lanceley Place Data Centre, Artarmon; Modification 2 – Lanceley Place Data Centre: Assessment Report

Kind: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B; Modification 2 – Lanceley Place Data Centre: Assessment Report

Country: Goodman Data centre overview

Region: Goodman Data centre overview; Modification 2 – Lanceley Place Data Centre: Assessment Report

City: Goodman Data centre overview; Modification 2 – Lanceley Place Data Centre: Assessment Report

Metro: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B; Modification 2 – Lanceley Place Data Centre: Assessment Report

Address: Goodman Data centre overview; Modification 2 – Lanceley Place Data Centre: Assessment Report

Operator: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B

Owner: Goodman Group Q4 FY2026 Earnings Call Transcript - August 19, 2026

Business Model: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B

Scale: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B

Statuses: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B; Goodman SYD01; Modification 2 - Lanceley Place Data Centre

Summary: Goodman marks construction of data centre in Sydney’s north as global work in progress grows to $18B; Goodman SYD01

Location: Modification 2 – Lanceley Place Data Centre: Assessment Report

Stable identifier: 22004ef9-a605-48d8-b486-c9cf3cf05f04