Brooklyn Campus · CDC Brooklyn Campus One

OperationalPlanned

CDC campus in Brooklyn, Melbourne, operating since 2024. Victorian government reporting dated 26 February 2026 confirms two operational facilities and planning for a third. CDC reports ultimate campus capacity exceeding 350 MW without specifying the power basis. Its undated location page still describes remaining Brooklyn facilities as under construction; current construction scope requires reconciliation.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
CDC Data Centres
Ownership
Unknown / not established
Business model / scale
Colocation / Unknown
Region / metro
Victoria / Melbourne
City / locality
Brooklyn
Address
Unknown
Location
PeeringDB geocode for constituent facility BK1 at 598 Geelong Road; used as an approximate campus locator, not a verified campus centroid or surveyed point. Address numbering and campus boundaries remain unresolved.
Precision: approximate · -37.818303, 144.842294
View location on map →
Parent
Not assigned

Location detail

PeeringDB geocode for constituent facility BK1 at 598 Geelong Road; used as an approximate campus locator, not a verified campus centroid or surveyed point. Address numbering and campus boundaries remain unresolved.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.

Address unknown

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
>350 MW
Unspecified power
Ultimate completed Brooklyn campus, including operational and future facilities
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated operator page, not announcement or commissioning date. Ultimate campus claim establishes greater-than-5-MW eligibility; it is not current operating capacity or explicitly IT load.

Development timeline

  1. 2024 · actual

    Brooklyn campus enters operations

    Operator and investor reporting identify 2024 as the start of campus operations.

    Supporting source ↗
  2. 2024-07 · actual

    Civil project completed

    Green Civil reports completion of its May 2022–July 2024 project; this includes BK1 civil works and BK2 enabling works and is not proof that both buildings commissioned in July 2024.

    Supporting source ↗
  3. 2025-Q4 · actual

    Second Brooklyn facility enters operations

    Investor quarter update reports inaugural operations at the second Brooklyn data centre during the December 2025 quarter.

    Supporting source ↗
  4. 2026-02-26 · actual

    Campus official opening

    Victorian government confirms two facilities operating at the official opening.

    Supporting source ↗
  5. 2026-02-26 · announcement

    Third facility in planning

    Government reports planning underway for a third facility; no completion date is provided.

    Supporting source ↗

Disclosed specifications

Cooling

LiquidCore closed-loop cooling

Operator’s Brooklyn opening announcement reports water not consumed for primary cooling and WUE 0.01; no independent facility measurement supplied.

Source ↗

Energy

Access to 100% renewable energy through Progress Energy

Customer access offering; does not establish campus hourly renewable supply or on-site generation.

Source ↗

Civil works scale

70,000 m²

Contractor project scale and BK1 building-pad/external-pavement work area; not established campus land area or gross floor area.

Source ↗

Substation demand

33 MVA initially; 99 MVA ultimate; N-1 redundancy

Contractor-described requested maximum demand at Jemena’s 598 Geelong Road substation. Not converted to MW or equated with campus IT capacity.

Source ↗

Connectivity

MegaIX Melbourne listed at BK1

PeeringDB facility record; not a campus-wide carrier inventory.

Source ↗

BK2 project team

EJE Architecture; ICON Constructions

Named by access-system supplier; relates specifically to BK2.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Melbourne | CDC Data Centres ↗

Published Date unavailable · Retrieved 2026-10-09

Identifies Brooklyn as CDC’s first Melbourne campus, operating since 2024, with expected capacity over 350 MW upon completion; BK1 operational and remaining facilities described as under construction.

CDC Melbourne BK1 - PeeringDB ↗

Published Date unavailable · Retrieved 2026-10-09

Lists CDC Data Centres, 598 Geelong Road, Brooklyn VIC 3012, AU, geocode -37.818303, 144.842294, and MegaIX Melbourne connectivity. Record displays last update 26 September 2025.

CDC Brooklyn Campus One ↗

Published Date unavailable · Retrieved 2026-10-09

Campus listing uses 594 Geelong Road, Brooklyn, Australia; explicitly groups BK1 and BK2 and lists cabinet, cage and suite services.

Brooklyn Data Centre VIC ↗

Published Date unavailable · Retrieved 2026-10-09

Civil contractor identifies Total and CDC as clients, May 2022–July 2024 project period, 70,000 m² project scale, and distinct BK1 works and BK2 enabling works.

Brooklyn substation civil works ↗

Published Date unavailable · Retrieved 2026-10-09

Contractor case study identifies Jemena substation at 598 Geelong Road with initial requested maximum demand 33 MVA and ultimate 99 MVA, both N-1; these are not MW figures.

CDC Development Pipeline — Infratil filing ↗

Published Date unavailable · Retrieved 2026-10-09

December 2025 quarter update states the second Brooklyn data centre entered operations; capacity tables are regional and are not attributed here to this campus.

CDC BK2 Data Centre, Brooklyn VIC | Kattsafe ↗

Published Date unavailable · Retrieved 2026-10-09

Identifies BK2 as part of CDC’s Brooklyn campus; names EJE Architecture and ICON Constructions and describes roof and generator access systems.

Profile field evidence

Name: Melbourne | CDC Data Centres; CDC opens its first Melbourne data centre campus, expanding Australia’s sovereign digital infrastructure

Aliases: Melbourne | CDC Data Centres; CDC Brooklyn Campus One

Kind: CDC’s data centres fueling jobs and growth in the west; CDC Brooklyn Campus One

Country: CDC Melbourne BK1 - PeeringDB; CDC Brooklyn Campus One

Region: CDC’s data centres fueling jobs and growth in the west; CDC Melbourne BK1 - PeeringDB

City: CDC Melbourne BK1 - PeeringDB

Metro: Melbourne | CDC Data Centres; CDC’s data centres fueling jobs and growth in the west

Operator: CDC opens its first Melbourne data centre campus, expanding Australia’s sovereign digital infrastructure; CDC Melbourne BK1 - PeeringDB

Business Model: CDC Brooklyn Campus One

Statuses: CDC’s data centres fueling jobs and growth in the west; CDC Development Pipeline — Infratil filing

Location: CDC Melbourne BK1 - PeeringDB; Brooklyn substation civil works

Summary: Melbourne | CDC Data Centres; CDC’s data centres fueling jobs and growth in the west; CDC Development Pipeline — Infratil filing; CDC hosts Melbourne data centre site visit

Stable identifier: 2be8a0b3-ed99-4e04-b32b-2cb777175338