CDC Brooklyn Campus · Australia · CDC Data Centres
CDC campus in Brooklyn, Melbourne, operating since 2024. Victorian government reporting dated 26 February 2026 confirms two operational facilities and planning for a third. CDC reports ultimate campus capacity exceeding 350 MW without specifying the power basis. Its undated location page still describes remaining Brooklyn facilities as under construction; current construction scope requires reconciliation.
Capacity statements: 1 · Sources: 11
350 MW (gt) · unspecified · Ultimate completed Brooklyn campus, including operational and future facilities · 2026-10-09