Canberra | CDC Data Centres ↗
Published Date unavailable · Retrieved 2026-10-09
Separately identifies Hume Campus One and Hume Campus Two; Two contains HU4/HU5 and reports current operating capacity of 51 MW.
Australia / Site
Hume Campus Two · CDC Hume Campus 2 · Hume Two
CDC campus in Hume, Canberra, separate from Hume Campus One. The operator reports 51 MW current operating capacity for HU4/HU5 without identifying IT, facility or grid basis. The 26 March 2026 investor presentation identifies HU6 as under construction within Hume Two. The proposed address follows PeeringDB; alternative street addresses remain unresolved. Ownership is attributed to CDC at group level, not a verified legal titleholder.
Shared HU4/HU5 geocode published by PeeringDB for 7 Tralee Street; campus identity corroborated by CDC and a H5 planning document, but the point was not independently matched to a parcel or building. No block or surveyed accuracy claimed.. Coordinate precision: approximate. Street-map detail does not increase the accuracy of the sourced point.
Loading local map…
Statements retain their dates, definitions and development scope. Do not add these rows together.
| Claim / measurement | Scope and status | As of | Evidence and accounting |
|---|---|---|---|
| 51 MW Unspecified power | Hume Campus Two operating HU4/HU5 campus capacity Operational · cumulative | 2026-10-09 | Reported claim ↗ Excluded from capacity totals. As_of is retrieval date of the undated current operator page, not a commissioning or measurement date. Power basis is unstated. Exceeds 5 MW on reported capacity only. Do not add constituent-building claims or Canberra portfolio figures. |
| 25 MW Unspecified power | Hume Campus Two H4 total project capacity Unknown · unclear | 2026-10-09 | Reported claim ↗ Excluded from capacity totals. As_of is retrieval date of an undated builder project page. Historical design/project capacity; source does not establish when it became operational. H4 is a constituent building already within the campus total, so this is not additive. |
| 25 MW Unspecified power | Campus Two Building 2 in BSE's engineering account Unknown · unclear | 2026-10-09 | Reported claim ↗ Excluded from capacity totals. As_of is retrieval date of an undated engineering page. Building 2 naming is unresolved and may overlap H4 or other historical works. Do not assign to HU5 or add to the campus total. |
CDC's retrospective timeline records construction beginning for the new Hume campus HU4 building.
Supporting source ↗CDC's timeline places HU5 under construction in 2021; no commissioning date established.
Supporting source ↗Sense records its door-package project completion in 2023. This is a contractor milestone, not proof of facility commissioning.
Supporting source ↗Future Fund and Infratil announced acquisition of shares offered by CSC; corporate equity ownership is distinct from campus legal title.
Supporting source ↗Dated investor presentation places HU6 under construction at Hume Two alongside operational HU4/HU5.
Supporting source ↗Retained as one campus record, separate from Hume One; no constituent records created.
Source ↗Planning-document property identifier for Building 5; does not establish the entire campus boundary.
Source ↗DA amendment design area, not an as-built measurement or campus total; roof plant/chiller areas of 2,353 m² excluded.
Source ↗BSE engineering account; numbering and area basis need reconciliation with H5 planning figures. Do not sum.
Source ↗Builder's design description; independently issued Tier certification not established.
Source ↗Builder delivered structure while client procured major plant and engaged mechanical/electrical contractors directly.
Source ↗Operator states this is implemented in every facility built; no Hume Two equipment schedule or cooling performance established.
Source ↗HU5 PeeringDB record; not proof of a complete carrier roster or fibre-route diversity.
Source ↗Published CDC sales contact on HU5's PeeringDB record; no contact made.
Source ↗Report period ends 31 March 2026. Certificate/contractual matching is not real-time renewable supply; no separately disclosed Hume Two energy balance.
Source ↗Source attribution does not imply independent verification or permission to reuse images.
Published Date unavailable · Retrieved 2026-10-09
Separately identifies Hume Campus One and Hume Campus Two; Two contains HU4/HU5 and reports current operating capacity of 51 MW.
Published Date unavailable · Retrieved 2026-10-09
Lists CDC Data Centres, campus CDC Hume Campus 2, 7 Tralee Street, Hume ACT 2620, Australia, and geocode -35.394572, 149.162027. Record displays last update 26 September 2025.
Published Date unavailable · Retrieved 2026-10-09
Lists HU5 at the same address and coordinate as HU4, linked to CDC Hume Campus 2; lists CDC Networks ASN 137486 and sales phone +61 1300 232 232.
Published Date unavailable · Retrieved 2026-10-09
Campus record identifies Hume, Australia, CDC Data Centres and constituent facilities HU4/HU5; displays last update 28 January 2026.
Published 2026-03-26 · Retrieved 2026-10-09
Our ANZ Presence diagram groups HU4/HU5 as operational and HU6 as under construction at Hume Two; states 100% asset ownership at portfolio level.
Published Date unavailable · Retrieved 2026-10-09
CDC describes itself as developer, owner and operator. Timeline records HU4 construction beginning in 2018 and HU5 under construction in 2021. Says closed-loop cooling is implemented in every facility built.
Published Date unavailable · Retrieved 2026-10-09
Builder describes H4 as a 25 MW total-capacity project delivered through construction management, designed to Tier IV and government security requirements; no certification certificate or power basis supplied.
Published Date unavailable · Retrieved 2026-10-09
Planning document identifies CDC, Hume Campus 2 Building 5 and Block 103 Section 7 Hume. Proposed gross floor area totals 10,574 m², excluding 2,353 m² roof plant/chiller areas.
Published Date unavailable · Retrieved 2026-10-09
Engineering account lists Campus Two Building 2 as a 25 MW facility and Building 4 as a 15,000 m² Tier IV design. Its numbering is not reconciled with CDC's HU4/HU5 names.
Published Date unavailable · Retrieved 2026-10-09
Identifies H4/H5, Hindmarsh as builder and 2023 completion of its door-package project; photograph attributed to Canberra Data Centres.
Published Date unavailable · Retrieved 2026-10-09
Describes painting work across Campus Two H4/H5, completed in 2023, but gives 54 Sheppard Street, creating an unresolved address discrepancy.
Published Date unavailable · Retrieved 2026-10-09
Identifies operational HU4 in Canberra, ACT, Australia, with 2020 year built, but lists 5 Tralee Street rather than PeeringDB's 7 Tralee Street.
Published Date unavailable · Retrieved 2026-10-09
CSIRO places Virga at CDC's Hume Data Centre in Canberra and describes hybrid direct liquid cooling. Page last updated 1 July 2024; it does not identify Campus Two or HU4/HU5.
Published Date unavailable · Retrieved 2026-10-09
Operator announces certification across its Australian and New Zealand data centres but does not enumerate Hume Two buildings or provide their individual certificates.
Published 2025-02-18 · Retrieved 2026-10-09
Announces shareholder transaction: resulting holdings stated as Future Fund 34.55%, Infratil 49.75%, CSC 12.04% and management 3.66%; these are corporate equity interests, not campus title ownership.
Published Date unavailable · Retrieved 2026-10-09
Describes customer ICT footprints, rack deployment, migration and operations support across CDC campuses, supporting classification as customer colocation infrastructure.
Published Date unavailable · Retrieved 2026-10-09
FY26 portfolio report states all grid electricity consumption was matched with renewable electricity through certificates, contractual arrangements or customer programs; expressly distinguishes matching from real-time renewable consumption.
Name: Canberra | CDC Data Centres
Aliases: Canberra | CDC Data Centres; CDC Hume Campus 2 - PeeringDB; CDC investor presentation and guidance update
Kind: Canberra | CDC Data Centres; CDC Hume Campus 2 - PeeringDB
Country: CDC Canberra HU4 - PeeringDB; CDC Hume Campus 2 - PeeringDB
Region: CDC Canberra HU4 - PeeringDB; Hume Campus Two - H4, ACT - Hindmarsh; CDC: Hume 4 Data Center — Baxtel
City: Canberra | CDC Data Centres; CDC investor presentation and guidance update
Metro: Canberra | CDC Data Centres; CDC: Hume 4 Data Center — Baxtel
Address: CDC Canberra HU4 - PeeringDB; CDC Canberra HU5 - PeeringDB
Operator: Canberra | CDC Data Centres; CDC Canberra HU4 - PeeringDB
Owner: CDC investor presentation and guidance update; About CDC Data Centres
Business Model: CDC Data Centre Services; Hume Campus Two - H4, ACT - Hindmarsh
Statuses: Canberra | CDC Data Centres; CDC investor presentation and guidance update
Summary: Canberra | CDC Data Centres; CDC Canberra HU4 - PeeringDB; CDC investor presentation and guidance update; About CDC Data Centres; CDC Data Centre - One Star Group; CDC: Hume 4 Data Center — Baxtel
Location: CDC Canberra HU4 - PeeringDB; CDC Canberra HU5 - PeeringDB; Hume Campus 2 Building 5 — DA amendment cover sheet