South Korea / Facility

Digital Seoul 2 (ICN11)

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

ICN11 · 6877-9 Gurae-dong (ICN11) · ICN11 Gimpo Data Center

Under Construction

Digital Realty's second South Korean facility is being developed in Gimpo, separately from ICN10 in Seoul. The operator announced up to 64 MW of critical IT capacity in 2021. Subsequent construction reporting retains a 64 MW total IT design; no operational capacity or opening was established. October 2026 reporting gives September 18, 2028 as the amended construction-contract end date, not a confirmed service commencement date.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Digital Realty
Ownership
Unknown / not established
Business model / scale
Colocation / Unknown
Region / metro
Gyeonggi-do / Greater Seoul
City / locality
Gimpo
Address
6877-9 Gurae-dong, Gimpo-si, Gyeonggi-do, South Korea
Location
Parcel address corroborated by exchange disclosure and project consultant; no independently established property-marker coordinates.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
≈64 MW
IT load
ICN11 ultimate development capacity
Planned · cumulative
2021-07-29Reported claim ↗

Excluded from capacity totals. Operator announcement says up to 64 MW of critical IT capacity. The schema lacks an upper-bound qualifier; approx preserves the non-guaranteed ceiling, not an exact installed amount. As-of is announcement date.

64 MW
IT load
ICN11 total design IT load
Under Construction · cumulative
2026-10-04Reported claim ↗

Excluded from capacity totals. As-of is news publication date reporting the October 2 amended contract. Design load for the construction project; no commissioned IT load established. Overlaps c1 and must not be added to it.

10.6 MW
IT load
ICN11 Phase 1 within 64 MW ultimate development
Planned · incremental
2026-10-07Reported claim ↗

Excluded from capacity totals. As-of is retrieval date, not publication or commissioning date. Historical 1H 2024 report labels this Phase 1. Later 2H 2025 report also shows 10.6 MW with 64 MW total and UC status; current phase delivery remains unresolved. Included within total capacity.

Development timeline

  1. 2021-07-29 · announcement

    ICN11 development announced

    Digital Realty announced acquired land in Gurae-dong for its second South Korean facility.

    Supporting source ↗
  2. 2023-H1 · planned

    Historical operational target

    2021 release forecast full operation in the first half of 2023; subsequent construction evidence shows this is not evidence of delivery.

    Supporting source ↗
  3. 2025-05-12 · actual_contract

    Construction contract awarded

    KRX disclosure records contract award for ICN11 to DL E&C, with Digital Seoul 2 Ltd. as counterparty.

    Supporting source ↗
  4. 2025-05-25 · planned_contract_start

    Construction-contract period begins

    Contract start date; does not independently establish physical groundbreaking.

    Supporting source ↗
  5. 2026-10-02 · announcement_contract_amendment

    Construction contract amended

    Secondary disclosure reproduction reports revised amount and end date; linked DART original was inaccessible.

    Supporting source ↗
  6. 2028-09-18 · planned_contract_end

    Latest reported construction-contract end

    October reporting gives this amended contract end date. It is subject to change and is not a confirmed opening date.

    Supporting source ↗

Disclosed specifications

Planned facility area, original announcement

970,000 square feet

2021 forecast; not an as-built measurement. Differs from later project area descriptions.

Source ↗

Reported project area

95,051 square metres

2H 2025 market report SQM field; measurement definition and as-built status unresolved.

Source ↗

Consultant project area

94,928.53 square metres

Undated portfolio; differs from market-report and original-announcement figures.

Source ↗

Reported building levels

4 basement levels; 8 above-ground levels

October 2026 construction reporting. Consultant portfolio instead describes 2 basement levels; retain conflict pending current approved design.

Source ↗

Construction contractor and commissioning entity

DL E&C; Digital Seoul 2 Ltd.

Contractor and contract counterparty respectively. Counterparty identity does not establish registered property ownership.

Source ↗

Amended construction-contract amount

KRW657,448,735,562 excluding VAT

Secondary reproduction of October 2, 2026 disclosure, supported by October 4 news. Construction-contract amount, not total investment or valuation.

Source ↗

Connectivity positioning

Carrier-neutral; PlatformDIGITAL

Operator development positioning; no site-specific live carrier list established.

Source ↗

Public sales contact

sales@digitalrealty.com; +1 877 378 3282

Corporate sales contact displayed on the operator announcement webpage; not a dedicated ICN11 local contact.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

DL: corrected construction supply contract disclosure ↗

Published 2026-07-14 · Retrieved 2026-10-07

Accessible KRX disclosure identifies ICN11 Data Center, Digital Seoul 2 Ltd. as counterparty, DL E&C as contractor, Gyeonggi-do Gimpo Gurae-dong 6877-9 as project location, and a contract running from May 25, 2025 to October 24, 2027. This schedule predates later amendments.

Seoul Data Centre MarketBeat, 2H 2025 ↗

Published Date unavailable · Retrieved 2026-10-07

Greater Seoul market report lists Digital Seoul 2 (ICN11), Gimpo, Digital Realty, 95,051 square metres, 10.6 MW with 64 MW total capacity, and UC status in significant construction updates. Exact publication day is not displayed in the accessed text.

DL E&C expands Gimpo data-centre contract to KRW657.4 billion ↗

Published 2026-10-04 · Retrieved 2026-10-07

News report cites the October 2 amended disclosure: ICN11 is being built in Gimpo for Digital Seoul 2 Ltd.; 64 MW IT load, four basement and eight above-ground levels, amended construction-contract end September 18, 2028. Reports KRW657,448,735,562 excluding VAT.

[ICN11] Gimpo Data Center — C5PLAN-G project portfolio ↗

Published Date unavailable · Retrieved 2026-10-07

Project consultant identifies ICN11, DL E&C, the parcel 6877-9 Gurae-dong, Gimpo, an area of 94,928.53 square metres and two basement/eight above-ground levels; undated and inconsistent with later four-basement reporting.

Seoul Data Centre MarketBeat, 1H 2024 ↗

Published Date unavailable · Retrieved 2026-10-07

Lists ICN11 in Gimpo with Digital Realty, 95,051 square metres and 64 MW IT load, explicitly identifying Phase 1 as 10.6 MW. Exact publication day unavailable.

6877-9 Gurae-dong (ICN11) — Data Center Map ↗

Published Date unavailable · Retrieved 2026-10-07

Directory corroborates alias, parcel address and under-construction classification. Its historical timeline is not treated as current construction verification.

Profile field evidence

Name: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; Seoul Data Centre MarketBeat, 2H 2025

Aliases: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; [ICN11] Gimpo Data Center — C5PLAN-G project portfolio; 6877-9 Gurae-dong (ICN11) — Data Center Map

Kind: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; [ICN11] Gimpo Data Center — C5PLAN-G project portfolio

Country: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea

Region: DL: corrected construction supply contract disclosure; [ICN11] Gimpo Data Center — C5PLAN-G project portfolio

City: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; DL: corrected construction supply contract disclosure; Seoul Data Centre MarketBeat, 2H 2025

Metro: Seoul Data Centre MarketBeat, 2H 2025

Address: DL: corrected construction supply contract disclosure; [ICN11] Gimpo Data Center — C5PLAN-G project portfolio

Operator: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; Seoul Data Centre MarketBeat, 2H 2025

Business Model: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; 6877-9 Gurae-dong (ICN11) — Data Center Map

Statuses: Seoul Data Centre MarketBeat, 2H 2025; DL E&C expands Gimpo data-centre contract to KRW657.4 billion

Location: DL: corrected construction supply contract disclosure; [ICN11] Gimpo Data Center — C5PLAN-G project portfolio

Summary: Digital Realty to Extend Global Reach of PlatformDIGITAL with Development of 64-Megawatt Facility in South Korea; Seoul Data Centre MarketBeat, 2H 2025; DL E&C expands Gimpo data-centre contract to KRW657.4 billion; DL E&C corrected supply contract, October 2, 2026 — disclosure summary

Stable identifier: 4ccdae40-f5ca-42ec-84a1-ec5f1b942b8c