Digital Seoul 2 (ICN11) · South Korea · Digital Realty
Digital Realty's second South Korean facility is being developed in Gimpo, separately from ICN10 in Seoul. The operator announced up to 64 MW of critical IT capacity in 2021. Subsequent construction reporting retains a 64 MW total IT design; no operational capacity or opening was established. October 2026 reporting gives September 18, 2028 as the amended construction-contract end date, not a confirmed service commencement date.
Capacity statements: 3 · Sources: 8
64 MW (approx) · it · ICN11 ultimate development capacity · 2021-07-29
64 MW (exact) · it · ICN11 total design IT load · 2026-10-04
10.6 MW (exact) · it · ICN11 Phase 1 within 64 MW ultimate development · 2026-10-07