Philippines / Site

Evolution PH01 Manila campus

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

Planned

Current 100+ MW plan targets Q3 2027. Older 69 MW/Q3 2026 plan retained as historical scope; completion not established.

Last researched 2026-09-11Last verified Not independently verifiedPublished revision 2
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Evolution Data Centres
Ownership
Unknown / not established
Business model / scale
Unknown / Unknown
Region / metro
Cavite / Greater Manila
City / locality
General Trias
Address
Gateway Business Park, General Trias, Cavite
Location
Property coordinate not established; no city centroid substituted.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
≥100 MW
IT load
Advertised full-build/design capacity; commissioned share unconfirmed
Planned · cumulative
2026-09-11Reported claim ↗

Excluded from capacity totals. Retrieval date, not measurement date. Design ceiling is not proof of delivered/occupied load. Excluded from aggregates pending reconciliation. Current 100+ MW plan targets Q3 2027. Older 69 MW/Q3 2026 plan retained as historical scope; completion not established.

69 MW
IT load
Historical/different-scope design claim; not additive
Planned · cumulative
2026-09-11Reported claim ↗

Excluded from capacity totals. Retrieval date, not measurement date. Design ceiling is not proof of delivered/occupied load. Excluded from aggregates pending reconciliation. Historical 69 MW plan and Q3 2026 target; replaced by current 100+ MW/Q3 2027 plan, not additional capacity.

Development timeline

  1. No dated milestones established.

Disclosed specifications

No additional specifications established.

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Historical capacity plan ↗

Published Date unavailable · Retrieved 2026-09-11

Historical 69 MW plan and Q3 2026 target; replaced by current 100+ MW/Q3 2027 plan, not additional capacity.

Operator logo · evolutiondatacentres.com ↗

Published Date unavailable · Retrieved 2026-09-11

Evolution operator brand mark. Image reference: https://evolutiondatacentres.com/wp-content/uploads/2024/11/EVO_LOGO_WHITE_TRANSPARENT4-650-135.png Visually inspected against the cited source and profile identity.

Profile field evidence

Name: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Operator: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Country: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Region: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Metro: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

City: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Address: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Kind: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Statuses: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Summary: Evolution PH01 Manila campus — capacity evidence; Data Center Map discovery and identity comparison

Operator Logo: Operator logo · evolutiondatacentres.com

Stable identifier: 6a8b3afb-516d-4e5b-9aaa-84644b961588