Evolution PH01 Manila campus · Philippines · Evolution Data Centres
Current 100+ MW plan targets Q3 2027. Older 69 MW/Q3 2026 plan retained as historical scope; completion not established.
Capacity statements: 2 · Sources: 4
100 MW (gte) · it · Advertised full-build/design capacity; commissioned share unconfirmed · 2026-09-11
69 MW (exact) · it · Historical/different-scope design claim; not additive · 2026-09-11
Revision 1
2026-09-11 09:58 UTC
Published profile snapshot
Evolution PH01 Manila campus · Philippines · Evolution Data Centres
Current 100+ MW plan targets Q3 2027. Older 69 MW/Q3 2026 plan retained as historical scope; completion not established.
Capacity statements: 2 · Sources: 3
100 MW (gte) · it · Advertised full-build/design capacity; commissioned share unconfirmed · 2026-09-11
69 MW (exact) · it · Historical/different-scope design claim; not additive · 2026-09-11