Finland / Site

Bitzero Kokemäki data center site

Unknown MWTotal facility power not establishedSee capacity evidence for reported claims.

Bitzero Pori

Planned

Proposed hyperscale AI/HPC campus in Kokemäki's Kirkkokallio area with expansion land south of Highway 2. September 2026 operator disclosure describes an initial plot supporting 80 MW gross load and prospective service in Q4 2027–Q1 2028. Operational IT capacity is unverified; the earlier pilot was reportedly abandoned.

Last researched 2026-10-07Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
Bitzero Holdings Inc.
Ownership
Bitzero Finland Oy (acquired plot); remaining expansion land subject to agreements/options
Business model / scale
Colocation / Hyperscale
Region / metro
Satakunta / Unknown
City / locality
Kokemäki
Address
Unknown
Location
Kirkkokallio, Kokemäki; expansion also described south of Highway 2. Area identified through municipal land-sale records and local reporting; no sourced property point established.
Precision: area
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
10 MW
Unspecified power
Site power advertised as available now
Unknown · unclear
2026-10-07Conflicting claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated page, not commissioning date. Availability does not establish operating IT load; subsequent pilot cancellation and future service disclosures complicate this claim.

40 MW
Unspecified power
Near-term site capacity with substation
Planned · unclear
2026-10-07Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated page. Relationship to later 80 MW and 200 MW plans is unresolved.

1000 MW
Unspecified power
Ultimate campus growth capacity
Planned · cumulative
2025-12-02Reported claim ↗

Excluded from capacity totals. Announcement-date planned capacity; not an operating load or independently established connection entitlement.

200 MW
Unspecified power
Capacity marketed by CBRE for prospective hyperscale development
Planned · unclear
2026-01-13Reported claim ↗

Excluded from capacity totals. Announcement-date commercialization scope; pre-design and prospective tenants, not leased or commissioned IT capacity.

≈520 MW
Unspecified power
Upper scope of engineering due diligence and pre-design
Planned · unclear
2026-04-24Reported claim ↗

Excluded from capacity totals. Source says up to 520 MW; schema lacks a less-than-or-equal qualifier. Engineering scope overlaps campus development and must not be added to other claims.

≈600 MW
Unspecified power
Lower endpoint of longer-term campus capacity range
Planned · cumulative
2026-04-24Reported claim ↗

Excluded from capacity totals. Source range is 600–1,000 MW; this is its lower endpoint, not a separate additive capacity.

≈1000 MW
Unspecified power
Upper endpoint of longer-term campus capacity range
Planned · cumulative
2026-04-24Reported claim ↗

Excluded from capacity totals. Source range is 600–1,000 MW; overlaps earlier 1 GW aspiration.

≈80 MW
Facility power
Expected gross load supported by first Finland plot
Planned · unclear
2026-09-01Reported claim ↗

Excluded from capacity totals. Announcement-date expectation explicitly described as gross load, not IT load. Prospective service window is Q4 2027–Q1 2028.

Development timeline

  1. 2025-01 · actual_acquisition_reported

    Initial Finland acquisition

    Operator's December release dates initial acquisition to January 2025; exact closing date and parcel coverage unresolved.

    Supporting source ↗
  2. 2025-12-02 · announcement

    Phase I development announced

    Operator announced ground-breaking/development; this does not establish completed or operational buildings.

    Supporting source ↗
  3. 2026-03-06 · actual_plan_change_reported

    Small pilot abandoned

    Yle reports cancellation of the small pilot and a larger revised initial development ambition.

    Supporting source ↗
  4. 2026-04-24 · announcement

    Engineering due diligence completed

    Operator reports Red Engineering pre-design assessment for up to 520 MW and an initial 80 MW phase.

    Supporting source ↗
  5. 2027-H1 · planned_superseded_target

    Earlier initial power target

    April disclosure targeted initial 80 MW power deployment in the first half of 2027; later disclosure gives a later service window.

    Supporting source ↗
  6. Q4 2027–Q1 2028 · planned

    Prospective ready-for-service window

    September update gives this window for potential Nordic tenants, including 80 MW in Finland; no actual commissioning established.

    Supporting source ↗

Disclosed specifications

Operator-reported acquired land

150,000 m²

Potential total plot 971,500 m², remaining under option; parcel-by-parcel reconciliation required.

Source ↗

Municipal land agreements

Acquired industrial plot, preliminary agreement for another plot, approximately 70 ha reserved under option

Municipal record distinguishes purchase from agreements and reservations; not all potential campus land is established as owned.

Source ↗

Energy mix claim

Hydro, nuclear, solar and wind

Operator description of intended low-carbon supply; no site-specific metered mix or power purchase agreement verified.

Source ↗

Engineering consultant

Red Engineering Design Ltd.

Company reports completed due diligence and progression toward building design.

Source ↗

High-voltage connection point

400 kV

Operator-reported confirmed point; no executed connection agreement or energized capacity independently established.

Source ↗

Backup power arrangement

Neighboring petrochemical site secured

September disclosure does not identify the property, technology, capacity or legal agreement.

Source ↗

Industrial zoning

First plot and two other plots reported industrially zoned

Further campus parcels require phased development; zoning does not establish building completion.

Source ↗

Commercial broker

CBRE

Advisory and brokerage role for prospective Finland tenants; not owner, operator or confirmed tenant.

Source ↗

Public business contact

info@bitzero.com

General operator contact published on facility page; no contact made.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

Bitzero Data Center ↗

Published Date unavailable · Retrieved 2026-10-07

Names Kokemäki, Finland; reports 150,000 m² acquired within a potential 971,500 m² site, 10 MW available now, 40 MW near-term with substation and 1 GW total growth capacity.

Kokemäen kaupunki — Talousarvio 2026 ↗

Published 2025-12-17 · Retrieved 2026-10-07

Pages 30–31 record sale of a Kirkkokallio industrial plot to Bitzero Finland Oy, preliminary agreement for another plot and approximately 70 hectares reserved under option; municipal infrastructure work and an early-2026 pilot were then anticipated.

Bitzero Pori Data Center ↗

Published Date unavailable · Retrieved 2026-10-07

Directory alias Bitzero Pori and address clue Härkisuontie & Pääväylä 2, 32800 Kokemäki. Its operational stage entry conflicts with primary-source future-development disclosures.

City of Kokemäki information ↗

Published Date unavailable · Retrieved 2026-10-07

Municipal information places Kokemäki in Satakunta, western Finland, approximately 40 kilometres from Pori.

Profile field evidence

Name: Bitzero Data Center; Bitzero Holdings Inc. Breaks Ground on Phase I Development at Giga-scale Finland Site

Aliases: Bitzero Pori Data Center

Kind: Bitzero Holdings Inc. Breaks Ground on Phase I Development at Giga-scale Finland Site; Bitzero Provides Corporate Update on Balance Sheet, Site Readiness and Leasing Progress

Country: Bitzero Data Center; Bitzero Holdings Inc. Breaks Ground on Phase I Development at Giga-scale Finland Site

Region: City of Kokemäki information

City: Bitzero Holdings Inc. Breaks Ground on Phase I Development at Giga-scale Finland Site; Kokemäen kaupunki — Talousarvio 2026

Operator: Bitzero Holdings Inc. Breaks Ground on Phase I Development at Giga-scale Finland Site; Bitzero Provides Corporate Update on Balance Sheet, Site Readiness and Leasing Progress

Owner: Kokemäen kaupunki — Talousarvio 2026; Bitzero Holdings Inc. Partners with CBRE & Hydra Host to Commercialize & Deploy AI Compute Capability Across Hyperscale & GPU Demand Channels

Business Model: Bitzero Holdings Inc. Partners with CBRE & Hydra Host to Commercialize & Deploy AI Compute Capability Across Hyperscale & GPU Demand Channels; Bitzero Provides Corporate Update on Balance Sheet, Site Readiness and Leasing Progress

Scale: Bitzero Holdings Inc. Partners with CBRE & Hydra Host to Commercialize & Deploy AI Compute Capability Across Hyperscale & GPU Demand Channels; Bitzero Holdings Inc. Provides Engineering Update at its Finland and Norway Sites — Exhibit 99.95

Statuses: Bitzero Provides Corporate Update on Balance Sheet, Site Readiness and Leasing Progress; Kokemäen datakeskuksen pieni pilotti jää väliin – Bitzero aikoo aloittaa toiminnan sadoilla megoilla ensi vuonna

Location: Kokemäen kaupunki — Talousarvio 2026; Kokemäen datakeskuksen pieni pilotti jää väliin – Bitzero aikoo aloittaa toiminnan sadoilla megoilla ensi vuonna

Summary: Bitzero Provides Corporate Update on Balance Sheet, Site Readiness and Leasing Progress; Kokemäen kaupunki — Talousarvio 2026; Kokemäen datakeskuksen pieni pilotti jää väliin – Bitzero aikoo aloittaa toiminnan sadoilla megoilla ensi vuonna

Stable identifier: 6e594282-b06c-4029-9bd7-74b8e2b9573d