atNorth FIN02 · Finland · atNorth
Operational atNorth colocation campus in Espoo, Helsinki metro, with an adjoining expansion under construction. Initial announced IT capacity was 15 MW; the current operator page advertises 40 MW campus power, while the expansion contractor reports 45 MW gross capacity upon completion. These figures are not additive or established live IT load.
Capacity statements: 5 · Sources: 13
15 MW (exact) · it · Initial FIN02 campus IT capacity · 2026-10-07
40 MW (exact) · facility · FIN02 advertised campus power capacity · 2026-10-07
45 MW (exact) · facility · Total FIN02 gross capacity following adjoining expansion · 2026-05-04
25 MW (exact) · it · Directory-reported total FIN02 IT capacity · 2026-10-07
11.2 MW (exact) · unspecified · Directory-reported fully built-out power; campus/phase boundary unspecified · 2026-10-07