Firebird Hrazdan AI Factory campus · Armenia · Firebird
AI campus with an opened first phase and further expansion. The 300 MW roadmap is a future total, not commissioned IT load. DC-2 is a 280 MW roadmap component; its precise boundary and reconciliation with the campus total require review.
Capacity statements: 3 · Sources: 10
300 MW (exact) · unspecified · Ultimate Armenian campus roadmap by end-2027 · 2026-08-08
18 MW (exact) · facility · Phase 1 design total power · 2026-06-05
280 MW (exact) · unspecified · DC-2 / Phase 2 roadmap component · None
Revision 1
2026-10-07 06:44 UTC
Published profile snapshot
Firebird Hrazdan AI Factory campus · Armenia · Firebird
AI campus with an opened first phase and further expansion. The 300 MW roadmap is a future total, not commissioned IT load. DC-2 is a 280 MW roadmap component; its precise boundary and reconciliation with the campus total require review.
Capacity statements: 3 · Sources: 5
300 MW (exact) · unspecified · Ultimate Armenian campus roadmap by end-2027 · 2026-08-08
18 MW (exact) · facility · Phase 1 design total power · 2026-06-05
280 MW (exact) · unspecified · DC-2 / Phase 2 roadmap component · None