Digital Edge PUS1 Busan Data Center · South Korea · Digital Edge
Digital Edge colocation and interconnection facility in Centum City, Busan, integrated with the former Sejong Telecom C2C cable landing station. Operator capacity disclosures conflict between 14 MW and 4.5 MW; current IT load and expansion commissioning remain unresolved.
Capacity statements: 4 · Sources: 10
14 MW (exact) · unspecified · PUS1 facility description; commissioned versus ultimate scope unspecified · 2026-10-07
4.5 MW (exact) · unspecified · PUS1 capacity table with planned update wording · 2026-10-07
14 MW (exact) · unspecified · PUS1 Chinese-language capacity table; updating qualifier · 2026-10-07
4.8 MW (exact) · unspecified · Directory fully built-out power for PUS1 · 2026-10-07