GC1 Gold Coast Data Centre · GC1 Gold Coast

Planned

Planned NEXTDC data centre in Southport, Gold Coast, Queensland, Australia. The operator advertises 6 MW of IT capacity and 4,600 square metres of technical space. The August 2026 presentation retains design and town planning status, approximately 6 MW total planned power subject to development approval, and approximately 1 MW initial capacity. Property-level location and ownership remain unresolved.

Last researched 2026-10-09Last verified Not independently verifiedPublished revision 1
No approved site photo yet. Photos and their source dates are published after evidence review.

Site profile

Operator
NEXTDC
Ownership
Unknown / not established
Business model / scale
Unknown / Edge
Region / metro
Queensland / Unknown
City / locality
Gold Coast
Address
Unknown
Location
Operator establishes Southport locality only; no corroborated property coordinate or street address.
Precision: unknown
Parent
Not assigned

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
6 MW
IT load
GC1 advertised proposed full facility IT capacity
Planned · cumulative
2026-10-09Reported claim ↗

Excluded from capacity totals. As-of is retrieval date of an undated live facility page. Advertised design capacity, not commissioned capacity; exceeds 5 MW on a planned IT basis.

≈6 MW
Unspecified power
GC1 total power planned
Planned · cumulative
2026-08-27Reported claim ↗

Excluded from capacity totals. As-of is presentation date. Subject to development approval. The slide does not explicitly identify IT, facility or grid basis; overlaps the advertised 6 MW and must not be added to it.

≈1 MW
Unspecified power
GC1 initial capacity
Planned · incremental
2026-08-27Reported claim ↗

Excluded from capacity totals. As-of is presentation date. Initial subset of total planned capacity, not additional to 6 MW; power basis unspecified.

≈1.2 MW
Unspecified power
GC1 historical initial capacity proposal
Planned · incremental
2025-02-24Reported claim ↗

Excluded from capacity totals. As-of is presentation date. Historical initial proposal differs from approximately 1 MW in February and August 2026 materials; reason for revision undisclosed. Not additive to full facility capacity.

Development timeline

  1. 2025-02-24 · announcement

    Design and town planning reported

    Half-year presentation identifies GC1 as a planned approximately 6 MW development with approximately 1.2 MW initial capacity.

    Supporting source ↗
  2. 2026-02-25 · announcement

    Initial capacity proposal approximately 1 MW

    Half-year presentation retains design and town planning status and approximately 6 MW total planned power.

    Supporting source ↗
  3. 2026-08-27 · announcement

    Planning status retained in FY26 results

    Full-year presentation continues to show design and town planning; no GC1 practical completion date is stated in its project entry.

    Supporting source ↗

Disclosed specifications

Locality

Southport

Operator-disclosed locality; does not identify a street or parcel.

Source ↗

Regional positioning

South East Queensland

Operator describes GC1 as supporting regional digital demand; portfolio grouping under Brisbane does not establish Brisbane as the property city.

Source ↗

Technical space

4,600 m²

Advertised proposed technical space; not land area or confirmed total building floor area.

Source ↗

Certification target

Uptime Institute Tier IV

Target certification only; achieved certification is not established.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

GC1 Gold Coast — NEXTDC ↗

Published Date unavailable · Retrieved 2026-10-09

Facility page identifies Southport, planning status, 6 MW IT capacity, 4,600 m² technical space and target Tier IV Uptime Institute certification.

NEXTDC FY26 Results Presentation ↗

Published 2026-08-27 · Retrieved 2026-10-09

Page 30: GC1 Gold Coast remains in design and town planning; approximately 6 MW total planned power subject to development approval and approximately 1 MW initial capacity.

NEXTDC FY26 Annual Report & Appendix 4E ↗

Published Date unavailable · Retrieved 2026-10-09

Page 4 includes GC1 Gold Coast in the Australian portfolio. Corporate certification tables do not establish GC1 certification.

NEXTDC FY24 ESG Report ↗

Published Date unavailable · Retrieved 2026-10-09

Page 5 describes advanced negotiations for Gold Coast GC1 and Geelong GE1 as additional edge facilities.

Gold Coast Data Centers — Data Center Map ↗

Published Date unavailable · Retrieved 2026-10-09

Lists NEXTDC GC1 within Southport, Gold Coast, Queensland, Australia; repeats operator planning and 6 MW description without a street address.

NEXTDC 1H25 Results Presentation ↗

Published 2025-02-24 · Retrieved 2026-10-09

Page 27 reports approximately 6 MW total planned power, subject to development approval, and approximately 1.2 MW initial capacity; design and town planning.

NEXTDC 1H26 Results Presentation ↗

Published 2026-02-25 · Retrieved 2026-10-09

Page 29 reports approximately 6 MW total planned power subject to approval, approximately 1 MW initial capacity, and design and town planning.

Profile field evidence

Name: GC1 Gold Coast — NEXTDC; NEXTDC FY26 Results Presentation

Aliases: GC1 Gold Coast — NEXTDC

Kind: GC1 Gold Coast — NEXTDC

Country: NEXTDC FY26 Annual Report & Appendix 4E; Gold Coast Data Centers — Data Center Map

Region: Gold Coast Data Centers — Data Center Map

City: GC1 Gold Coast — NEXTDC; Gold Coast Data Centers — Data Center Map

Operator: GC1 Gold Coast — NEXTDC; NEXTDC FY26 Annual Report & Appendix 4E

Scale: NEXTDC FY24 ESG Report

Statuses: GC1 Gold Coast — NEXTDC; NEXTDC FY26 Results Presentation

Summary: GC1 Gold Coast — NEXTDC; NEXTDC FY26 Results Presentation; Gold Coast Data Centers — Data Center Map

Location: GC1 Gold Coast — NEXTDC

Stable identifier: 9bba431f-2be0-4fb1-9c12-88ab8dd530d5