Japan / Site

AirTrunk TOK1

TOK1 Tokyo East · AirTrunk Tokyo East · AirTrunk 印西

OperationalUnder ConstructionPlanned

A hyperscale campus in Inzai serving the Tokyo market. Operating phases coexist with later development announcements and an advertised 300+ MW build-out. Historical phase claims overlap or lack explicit measurement definitions; current operational IT capacity is unresolved.

Last researched 2026-09-11Last verified Not independently verifiedPublished revision 3
TOK1 building exterior from the operator’s current location-page gallery.

Site / building photo

TOK1 building exterior from the operator’s current location-page gallery.

Published date unknown · Captured date unknown · Checked 2026-09-11

Preferred clear property view from the operator gallery. Capture and publication dates are unknown; the dated construction photo is retained below.

AirTrunk · Source and attribution ↗
Image rights and date notes

Operator-hosted copyrighted asset; no open reuse license found in reviewed source. Attribution retained; public reuse rights unconfirmed. Upload path is not proof of capture/publication date.

TOK1 Phase 3 construction, published with the operator’s topping-out update on 14 August 2024.

Site / building photo

TOK1 Phase 3 construction, published with the operator’s topping-out update on 14 August 2024.

Published 2024-08-14 · Captured date unknown · Checked 2026-09-11

Latest dated actual site/building image identified among checked operator releases. 2025 release image shows a ceremony; 2026 release image is a rendering.

AirTrunk · Source and attribution ↗
Image rights and date notes

Operator-hosted copyrighted asset; no open reuse license found in reviewed source. Attribution retained; public reuse rights unconfirmed. Publication date established; actual capture date not disclosed. Historical construction image does not establish current construction status.

Site profile

Operator
AirTrunk
Ownership
AirTrunk corporate acquisition by a Blackstone-led consortium with CPP Investments announced complete in December 2024; direct property title not established.
Business model / scale
Colocation / Hyperscale
Region / metro
Chiba Prefecture / Tokyo / Inzai
City / locality
Inzai
Address
Makinodai 2-chome, Inzai, Chiba, Japan; TOK1-B: 2-1-2; TOK1-D: part of 2-1-1
Location
Makinodai 2-chome campus block; directory pin corroborated by registered building addresses, not a surveyed building point
Precision: block · 35.8167, 140.16001
View location on map →
Parent
Not assigned

Location detail

Makinodai 2-chome campus block; directory pin corroborated by registered building addresses, not a surveyed building point. Coordinate precision: block. Street-map detail does not increase the accuracy of the sourced point.

Makinodai 2-chome, Inzai, Chiba, Japan; TOK1-B: 2-1-2; TOK1-D: part of 2-1-1

Loading local map…

Capacity evidence

Statements retain their dates, definitions and development scope. Do not add these rows together.

Claim / measurementScope and statusAs ofEvidence and accounting
>300 MW
Unspecified power
Ultimate advertised campus build-out
Planned · cumulative
2026-03-10Reported claim ↗

Excluded from capacity totals. Not an additional planned remainder or operational IT total.

>60 MW
Unspecified power
Initial operating phases at 2021 opening
Operational · incremental
2021-11-30Reported claim ↗

Excluded from capacity totals. Historical value; measurement basis not specified.

55 MW
Unspecified power
Building expansion announced in 2023
Under Construction · unclear
2023-03-14Reported claim ↗

Excluded from capacity totals. Phase relationship and current completion unknown.

50 MW
Unspecified power
Phase 3
Under Construction · unclear
2024-08-14Reported claim ↗

Excluded from capacity totals. Topping-out does not establish commissioning.

>40 MW
Unspecified power
Phase announced at June 2025 groundbreaking
Under Construction · unclear
2025-06-19Reported claim ↗

Excluded from capacity totals. Potential overlap with later construction scope.

>100 MW
IT load
Additional IT load in March 2026 announcement
Under Construction · incremental
2026-03-10Reported claim ↗

Eligible for compatible measurement statistics after overlap checks. Use once as a dated lower-bound claim; do not add earlier phase figures. Current completion requires recheck.

Development timeline

  1. 2021-11-30 · actual · opening

    Initial phases opened

    More than 60 MW disclosed, with further campus build-out planned.

    Supporting source ↗
  2. 2023-03-14 · announcement

    55 MW building development

    Expansion financing announcement; mapping to subsequent phases unresolved.

    Supporting source ↗
  3. 2024-08 · reported construction milestone

    Phase 3 topping-out

    50 MW planned phase capacity; operational completion not established.

    Supporting source ↗
  4. 2024-12-23 · corporate announcement

    AirTrunk acquisition completion announced

    Blackstone-led consortium and CPP Investments. This is an organization-level ownership event.

    Supporting source ↗
  5. 2025-06-19 · actual · groundbreaking

    40+ MW phase groundbreaking

    Keep separate from operating capacity and later cumulative statements.

    Supporting source ↗
  6. 2026-03-10 · construction announcement

    Over 100 MW additional IT load

    Operator reports construction recently commenced. The exact start date and subsequent completion remain unknown.

    Supporting source ↗

Disclosed specifications

Design PUE

1.15

Design specification, not measured operating PUE.

Source ↗

Advertised data-hall area

80,000 m²

Data-hall area, not gross building area; delivered extent not established.

Source ↗

Sources and references

Source attribution does not imply independent verification or permission to reuse images.

AirTrunk · TOK1 Tokyo East profile ↗

Published Date unavailable · Retrieved 2026-09-10

Campus specifications: 300+ MW, multiple buildings, 80,000 square meters of data-hall area and design PUE 1.15. Full operational capacity is not established.

AirTrunk · TOK1 opening ↗

Published 2021-11-30 · Retrieved 2026-09-10

Initial phases provide more than 60 MW; future campus scalable beyond 300 MW and to seven buildings. Measurement basis unspecified.

AirTrunk · Phase 3 progress ↗

Published 2024-08-14 · Retrieved 2026-09-10

Phase 3 expected to provide 50 MW; topping-out milestone. Not an operational commissioning announcement.

Baxtel · AirTrunk TOK1 location ↗

Published Date unavailable · Retrieved 2026-09-11

Directory map pin 35.816699, 140.160013 and address 2 Chome Makinodai, Inzai; corroborated at neighborhood/block level by the prefectural register. Exact building, entrance, parcel boundary and survey accuracy remain unverified.

AirTrunk · Official site photograph ↗

Published 2024-08-14 · Retrieved 2026-09-11

TOK1 Phase 3 construction, published with the operator’s topping-out update on 14 August 2024. Original image: https://airtrunk.com/wp-content/uploads/2024/08/TOK1-Phase-3-1024x573.png

AirTrunk · Official operator logo ↗

Published Date unavailable · Retrieved 2026-09-11

Operator logo from official site header. Original image: https://airtrunk.com/wp-content/uploads/2017/07/airtrunk-logo-horizontal-white-2.png

AirTrunk · TOK1 property exterior gallery ↗

Published Date unavailable · Retrieved 2026-09-11

Clear street-level exterior showing the TOK1 property. Visually checked as a photograph. Capture and publication dates are undisclosed. Original image: https://airtrunk.com/wp-content/uploads/2020/09/No.4-scaled.jpg

Profile field evidence

Name: AirTrunk · TOK1 Tokyo East profile

Operator: AirTrunk · TOK1 Tokyo East profile

Country: AirTrunk · TOK1 opening

Region: AirTrunk · TOK1 opening

Metro: AirTrunk · TOK1 Tokyo East profile

Business Model: AirTrunk · TOK1 opening

Scale: AirTrunk · TOK1 Tokyo East profile

Owner: AirTrunk · Completion of Blackstone-led acquisition

Statuses: AirTrunk · TOK1 opening; AirTrunk · TOK1 green loan and further construction

Summary: AirTrunk · TOK1 Tokyo East profile; AirTrunk · TOK1 opening; AirTrunk · TOK1 green loan and further construction

Location: Chiba Prefecture · Registered emission facilities, Inzai section; Baxtel · AirTrunk TOK1 location

City: Chiba Prefecture · Registered emission facilities, Inzai section; Baxtel · AirTrunk TOK1 location

Address: Chiba Prefecture · Registered emission facilities, Inzai section; Baxtel · AirTrunk TOK1 location

Media: AirTrunk · TOK1 property exterior gallery; AirTrunk · Official site photograph

Operator Logo: AirTrunk · Official operator logo

Stable identifier: a214a365-a7d2-4338-a43e-433e2f97719b