Map
Sign in
← BDx CGK5 Suryacipta campus

Published history

Restoring content creates a new revision. Previous revisions remain in the audit trail.

Revision 3 · Current

2026-09-11 12:15 UTC

Published profile snapshot

BDx CGK5 Suryacipta campus · Indonesia · BDx Data Centers

CSV-authorized Karawang extension. 300 MW is a development figure, separate from 385 MVA secured power.

Capacity statements: 2 · Sources: 5

300 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11

290 MW (exact) · it · CGK5 secured phased IT development · 2026-09-11

Revision 2

2026-09-11 11:26 UTC

Published profile snapshot

BDx CGK5 Suryacipta campus · Indonesia · BDx Data Centers

CSV-authorized Karawang extension. 300 MW is a development figure, separate from 385 MVA secured power.

Capacity statements: 2 · Sources: 3

300 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11

290 MW (exact) · it · CGK5 secured phased IT development · 2026-09-11

Revision 1

2026-09-11 10:44 UTC

Published profile snapshot

BDx CGK5 Suryacipta campus · Indonesia · BDx Data Centers

CSV-authorized Karawang extension. 300 MW is a development figure, separate from 385 MVA secured power.

Capacity statements: 1 · Sources: 1

300 MW (exact) · unspecified · Reported design/development capacity; delivered share unconfirmed · 2026-09-11