Revision 1 · Current
2026-10-07 12:47 UTC
Published profile snapshot
Equinix Hyangdong xScale campus (SL2x and SL3x) · South Korea · Equinix
Campus-level grouping of adjacent Equinix SL2x and SL3x in Hyangdong, Goyang. SL2x is operational and contains the SL4 retail IBX. SL3x contractor records describe construction with a September 2025–December 2027 contract period; commissioning is unconfirmed. SL2x capacity publications conflict between 20 MW and 22 MW IT, with additional 24 MW whole-building reporting. No reconciled campus total is adopted.
Capacity statements: 7 · Sources: 11
22 MW (exact) · it · SL2x · 2026-10-07
20 MW (exact) · unspecified · SL2x xScale offering · 2026-10-07
24 MW (exact) · unspecified · SL3x future capacity · 2026-10-07
45 MW (gt) · unspecified · SL2x and SL3x combined joint-venture development · 2022-01-26
24 MW (exact) · unspecified · SL2x whole building including general-enterprise allocation · 2024-09-26
40 MW (exact) · facility · SL2x active electrical supply design · 2026-10-07
12 MW (exact) · unspecified · SL2x first phase, Seoul 2x-1 · 2023-11-24